| BLOG | DIRECTIONS | SCHEDULE | STORE | |
Sunday, November 30. 2008Weekend track report
Saturday was myself, Tom, Frank and Trackbolt (Frank's daughter). We split ourselves into two separate gangs for the day. Tom and I spent the full day out on the mainline cutting brush with the recently debugged Amtrak brush cutter while Frank and Emily did a bunch of smaller essential tasks. The day started out like most any other day. The cutter wouldn't start. Immediately thought it was a dead battery (now only 2 weeks old) so we attempted a jump but nothing. Turned out the 60A main breaker fuse was busticated so Frank made quick work getting the last two from Napa. With a new fuse she started right up given the 32deg temps. Ready to roll, Tom set the cutter on the rails at Central Ave and we rolled out to Karsten's crossing to continue where we last left off. Things went well for the first five minutes when a hydraulic line failed...Typical day. Thankfully we were not stuck on the mainline without a way back cause Frank was on the grounds and went through our stock of used hoses and ran the motorcar out to us with the correct hose! We were back up and running in 10 min flat. A new record I think! From then on out the cutter ran great and we finished the first "section" from Karsten's crossing to the big tree were the RoW runs next to a field and we don't need to cut the south side. Satisfied we ran the mower back to Karsten's crossing and started the other direction cutting through the curve. Low light came upon us far too quickly and we quit a few poles west of the crossing.
Frank and Emily not only saved the day (twice), but also replaced a heel block bolt on the East Station 1/2 switch and capped off the leaking line on the Model 50 Burro crane. I'm pretty sure the two of them had to travel to every hardware store in the county to find the correct fittings, but they did and until we can repair the cylinder we'll at least be left without a puddle of oil on the machine. Frank mentioned an issue with a wheel locking up on the Santa Fe truck. We'll need to send it to Dave D. in B&G to take a look at it. Today I was out primarily to prepare for the Santa trains running the next two weekends. I cleaned the pockets on the 50th Ave/ West wye switch as well as the East/ West wye switch near Central Ave. Both locks on the switches on a shot of lub/ de-icer as well. The 50Ave switch got a little TLC and the switch ties are now spaced evenly and no longer crooked. Quick work with a lining bar. The mainline from East Switch to Seeman Rd, including Johnson Siding, was inspected and thankfully nothing major, pull aparts, were found. Julie, there will be a copy of the inspection sheet in your mailbox Saturday. I noted that the flange ways in Karsten's crossing were badly fouled so I cleaned them out. I think I've seen more derailments due to frozen crossings than anything and those CTA cars aren't that heavy. I finished the day with a cleaning out the bed of the Santa Fe truck and cleaning a few smudge pots for service next weekend. We have two pallets of kerosene switch heaters in the material yard so I found enough caps, wicks and pieces to get 6 put together. I was able to get 5 lit and working but I'll need to get another wick for the 6th. I dug them in and tested them out on the East/ West wye switch just after dark. They will be cool to use for the next couple weekends. I'm gonna try to be festive and get the two electric switch lanterns lit on the East Wye/ Yd 4 switch and the East/ West Wye switch lit as well. What's cooler than that...don't answer. Next Sat I plan a quick inspection of the mainline and get the pots and lanterns running and deal with any snow we'll have. Sayin 6-8 inches tonight for Union. Adam Robillard Sunday, November 30. 2008Wood Shop Update November 29, 2008First, we see John Faulhaber trimming one of the eight new windows for the Illinois Central 9792 caboose. These are almost ready to start priming and painting. Next, Richard Block got our new (1880) Fay Molder running, wheels balanced, wired up permanently, and ready to go. He spent a few hours oiling around, getting belts to track properly, and checking and debugging the mechanical operation. This was the first time we have done this, and the next test will be to cut wood! (The stripwood 'guard' is a mockup and the steel for the permanent belt guard is to be delivered next week.) Looking on this historic moment are Krystine Tempinski and Stan Wdowikowski. Finally, Wayne Baksic shot a pic of me working on a Pullman passenger ladder. For such a simple thing, the joints and shapes are almost hopelessly complex with scarcely a right angle anywhere. Saturday, November 29. 2008
CB&Q 504 update 11/29 Posted by James Kolanowski
in Chicago, Burlington & Quincy 504 at
22:32
Comments (0) CB&Q 504 update 11/29The work for the weekend actually started on Friday night. Nathaniel and I started by cleaning up the engineers side radiator compartment, which had only half of it painted. Nathaniel finished the prep and wiped it down with lacquer thinner to get it ready for painting while I started shaking and mixing some gray centari paint. We also setup the longest main reservoir pipe, cleaned and wiped it down. I sprayed a couple coats on the main res pipe, and three coats on the inside area of the radiator intake area. We also prep'ed the four footboard supports for the front pilot. Two were sandblasted and the other two needlechipped and sanded. Saturdays goal was to get the two main reservoirs that had been painted the week before off the stands and put the last two on the stands and prep them for paint. They weigh close to 500lbs each, so it took every bit of effort from Warren, Roger, Stephanie, Kyle, Scott and myself to get them moved and up on a pipe to start working on them. Roger worked on priming the ends of the tanks since that had not been done as they were primed standing upright and the ends were not accessible. We stored the winterization hatch and setup the last three main res pipes to prep and paint, along with two radiator shutters. We all grabbed some scotch brite pads and went to work cleaning and scuffing all the surfaces on all of the components. The shutters were the most time consuming, but with that many of us, it did go pretty quick. Everything is set for wiping with lacquer thinner and painting during the coming week. There are a couple of pictures added to the photo gallery, those can be viewed at this link: http://www.irm.org/gallery/cbq504restoration-2008 Thursday, November 27. 2008Woodshop Update November 26, 2008For some time the Illinois Central 9792 caboose has been outdoors since it is often used in our operating trains during the summer months. The windows in that car have suffered as a result of this. So, we decided to make a new set for the entire car. Here, the eight new frames are being 'processed' through the Berlin sander (after gluing) by (l to r) Kirk Warner, Ed Chase, and Victor Humphreys. Wednesday, November 26. 2008
URTX 26640 Update November 26, 2008 Posted by Robert Kutella
in URTX 26640 Insulated Boxcar at
16:34
Comments (0) URTX 26640 Update November 26, 2008Monday, November 24. 2008
ME 28 Update - November 23, 2008 Posted by Robert Kutella
in Michigan Electric 28 at
16:37
Comments (0) ME 28 Update - November 23, 2008Norm Krentel stands in front of one of the baggage doors removed from the 28. The damage and deterioration is extreme so the first step is to document and create a drawing before starting to make new doors. Monday, November 24. 2008 |
Blog AdministrationFind us on FacebookCategory TreeCalendarQuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!
Sun, 05-05-2013 18:53
Ah yes, I have made such Jibs myself. If it were me, I would add in each corner an angled piece from the base to the Jib to act as sway bracing. [...]