| BLOG | DIRECTIONS | SCHEDULE | STORE | |
Monday, February 16. 2009
CB&Q 504 update 2/15 Posted by James Kolanowski
in Chicago, Burlington & Quincy 504 at
19:26
Comments (6) CB&Q 504 update 2/15This weekend some parts started going back onto the 504. On Saturday, the last coat of gray was sprayed on the engineers side shutters and screens. Joe did some work on the roof to begin prepping the area where the tanks and winterization hatch will get reinstalled. On Sunday, all the radiator shutters and screens that were recently painted were installed by Roger, Warren, Charlie, Kyle and Jamie. The next set of parts, including the dynamic brake intakes, were laid out to be cleaned, wiped, and painted. Additional photos can be viewed in the 504 restoration gallery. Sunday, February 15. 2009L7 update for 2/15A good amount of progress was made today on the L7. On Saturday, Joel sampled some T&G wood for the cab floor in order to replace the sections that are missing. Today, Joe and Joel spent some time testing the resistor grids, they identified at least one short that will need to be repaired. Charlie, Warren, Kyle, and Jamie spent some time making a lot more progress on painting. This started with Charlie grinding some holes on the deck and then Jamie welded them closed, and Charlie grinding the welded spots smooth and then priming. Charlie and Warren did a bit of work sanding the hood and deck. Everyone pitched in on masking areas not to be painted, and then wiped everything down with lacquer thinner. Jamie then sprayed the first coat of green on the hood and deck. The fun part was keeping Alco from walking across the wet paint. Sunday, February 15. 2009
Passenger Dept Update 2009-02-14 Posted by Phil Stepek
in Passenger Car Department at
19:27
Comments (0) Passenger Dept Update 2009-02-14Another week of steady progress in the background. Mike found and repaired several holes in the walls of ATSF 2544 sanded and prepped them to get ready to paint. Mark hoffman was going at it sunday when we left Its still looking like we will be able to have one side of the restoration seating installed for this season, and he wants to do the other side next winter. In addition the seats we are removing have no where to go , so anyone interested can email or comment. The seats are photographed in the cars' gallery. http://www.irm.org/gallery/ATSF2544 The sample lens for the reading lights in ATSF 1534 fit ok after several tries, and so we hope to have the rest done soon, and then we can install. The hood lights in Birminghams kitchen are done, and the new exhaust fans for the hood area are in, so the kitchen area is almost finished for the winter. All I want to do now is get the air curtain working, and then enclose the end wall which has been missing since we got the car in 2005. I keep being surprised by the different visual it is now in the area with a much more yellow light. It really looks more subdued, and yet its a warmer feel. when folks stop by this year take a peek. We have ten weekends until we open for display, and we have a two page list of things to do before then, so anyone that wants to can stop out and pitch in.... If you dont have the time or desire to "build or scrape" you are welcome to check in and lend a hand in April as we clean and spruce up the displays. As always, if you prefer to help with the displays themselves during season, we need docents and/or tourguides. And for our remote friends, donations are gratefully received to continue the work, either for heavyweights or streamliners. Much of our department funding went to the new barn, so we are going to be a bit cash strapped this year. hope to have new photos of the work soon. Thursday, February 12. 2009
CTA S-105 update 2/12 Posted by James Kolanowski
in Chicago Transit Authority S-105 at
23:55
Comments (0) CTA S-105 update 2/12Work continues on the S-105. Over the past several months, new windows frames and doors have been made and most of them installed, with just a few more to be installed once the body is prepped. Work continues on where the frames get installed into the body to make a good tight fit. The old coupler pocket from one end and all the coupler pocket bolts have been removed and those areas cleaned, primed and painted. The new coupler pockets are slightly larger and have a different hole spacing, so blocks were cut and are being welded into place and new holes will be drilled with the correct spacing to match the pilot. Some preliminary work has been scoped out to get the rust holes in the roof sealed up. This will continue over the next few months. Additional photos can be viewed in the S-105 Restoration gallery. Thursday, February 12. 2009
Another night of painting... Posted by James Kolanowski
in Chicago, Burlington & Quincy 504 at
23:45
Comments (0) Another night of painting...Along with some work on the L7 Thursday night, the 504 also had some of its parts painted. The short hood hatch had its final coat of gray sprayed on. The Engineers side radiator shutters and intake screens had the first coat of gray sprayed. Some touch up work was done to some smaller parts that will be bolted to the long hood. Additional photos can be viewed in the 504 gallery. Thursday, February 12. 2009
L7 gets another coat of paint Posted by James Kolanowski
in TMER&L L7 Locomotive at
23:28
Comments (0) L7 gets another coat of paintThe side and end of the cab received a second coat of paint on Thursday night. After some touch up around some hinges and a 3rd coat in these areas, work will move on to the hoods and decks. Additional photos can be found in the L7 gallery. Tuesday, February 10. 2009
General Track Update and Recent ... Posted by Adam Robillard
in Track Department at
17:14
Comment (1) General Track Update and Recent HappeningsDespite the cold and snow the last few months the Track Dept has continued to press on. Since the museum has been closed after the Santa Trains in December we've been spending time on the mainline cutting brush along the Right-of-Way. The primary focus of this is to clean up the railroad to increase visibility for train crews and prevent brush from coming in contact with the sides of equipment... We have a majority of the railroad cut west of Johnson Siding and as weather and time allow we will continue eastward. This is a very slow process due to the number of line poles along our railroad but we've made significant progress. We are pushing to have the railroad fully cut before revenue operations begin as not to tie up the line during the spring. Other cold weather projects have been happening in our shop area inside Barn 2 on Track 24. We've spend time giving a number of our track machines oil and filter changes and repairing them as needed. A short list of those projects include reattaching any missing hoses on the broom of the ballast regulator, cleaning and maintaining our work area in the shop and prepping the engine in the switch tamper for removal and repair. This past weekend the warm temperatures brought us outside to begin work on the line. Saturday Frank Devries and Adam Robillard were out and the first order of bussiness was to help the Signal/ DC Line dept replace a bad impedance bond on the far west end of the railroad. We brought out the tie crane, loaded up the new bond on a track cart and Frank ran the crane to West Schmidt. I met him out there and we had the new one installed fairly quickly. Returning from the field we switched track 24 getting the switch tamper in order to allow the engine to be removed during the week. The clean work space in Tk 24 made this task a lot easier. After finishing up we headed over to the Model 50 Burro Crane in Yd 11 to troubleshoot the travel. We began having problems with the transmission nearly two months ago and were now unable to get the crane into reverse.... It turns out a 3/8" X 1-1/2" bolt had been replaced in the past with a smaller bolt underneath the machine. This smaller bolt allowed too much play and prevented the piston from engaging into reverse on the transmission... A quick exchange with the correct size bolt solved that problem and the travel works, dare I say, reliably. We still need to change the hydraulic filter and troubleshoot the outriggers, but the crane is back in service. Sunday Frank and I were joined by Steve Lewkowycz and we decided to tackle the first of many switch timbers that need replacement along our streetcar line. We got materials and tools out from their winter hiding spots and began by replacing a 16' timber in the switch leading to Yard 10 on the south end of the carline. We used the tie crane for the hard work and air compressor to spike it all up. The job ran quicker than any of us expected it too and next we tackled two head block ties in the switch leading to Yard 4 West near Depot Street. The existing ties were in horrible condition and were unable to hold the switchstand in place. The ties broke into 30 pieces when we attempted to pull them proving their ineffectiveness. A few hours and a few slices of pizza from Rosatti's later we got the two new 15' ties installed and spiked up. We needed to regage about 15ft of track off of the points to bring the switch back into gage. The switch stand was reinstalled and we called it quits after that. Kudos to Steve for venturing out for the day and helping with the work. We have many carline switch timbers to replace this season so any help would be much appreciated. The next few weeks will include more brush cutting on the mainline and machine maintenance. If we can get a good crew together and a few nice days we can continue replacing ties. There is more than enough work to keep us busy before operations make our jobs much more difficult. We will begin inspections in early March. This includes a complete walking inspection of all revenue tracks (mainline, carline, sidings) and building a list of defects we need to fix before operations begin in April. Typically we will find enough work to keep us busy for two weekends repairing the defects. Help is always needed during this time to ensure the line is open without speed restrictions or Out-of-Services for the operations dept. If you'd like to help us out in the Track Dept. feel free to send me a line at lzeje657@msn.com. Did I mention the good exercise you gain from working with us? Check out updated photos of our work at my photos folder here. http://www.irm.org/gallery/lzeje657 As I learn more about this blog i'll incorporate pics in the future..
|
Blog AdministrationFind us on FacebookCategory TreeCalendarQuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!
Sun, 05-05-2013 18:53
Ah yes, I have made such Jibs myself. If it were me, I would add in each corner an angled piece from the base to the Jib to act as sway bracing. [...]