Our task this past weekend was to
construct the new 11-4 track inside of the Barn in yard 11. We had a
really good group out Saturday to work taking time from their normal tasks to
help us out. The crew was the regular track gang, Frank D, Tom H, Steve L
and Adam R and we were joined by Jamie K, Pete P, Warren L from the diesel dept
and Erik M, a long distance volunteer from Nebraska.
Friday Frank D, Andy C and Erik M came out to prep for the day. They
spiked up the remaining ties from last weekend and got tools, machines and
material ready for Saturday. When we arrived Saturday we split into three
groups. The first group used the Model 50 Burro crane and shuttled panels
into the Barn and set them into place. That group consisted of Tom H at
the controls of the Burro and Jamie K and Warren L hooking, walking and setting
each panel into place. The second group consisted of Frank D, Pete P and
Erik M hooking each panel up and inserting ties under joints. The last
gang was myself, Adam R, on the X-17 Model 30 Burro topping off the ballast
cars from our ballast pile out the Barn door.
By lunch we had all but
three panels set, and both ballast cars loaded (kinda overloaded...) ready to
be dumped. It was very hot out so we kept cool with a cooler of ice and
water. Dave Diamond also came over to help realign the track at the Barn
door sill with the backhoe.
After lunch we regained our strength and finished up building the entire track
to the west end of the Barn! Bob Olson and myself ran into the material
yard for a quick trip to locate more joint bars while the Erik ran our
hydraulic rail saw cropping the ends of the rails and getting the last short
panel set. The next step before ballast was to finish up the Quality
Control work and spiked up all of the joint ties with the air compressor
suspended from the Burro crane and spiking gun. Steve L did a great job
nipping the ties while Frank D and Jamie K preset the spikes. Adam R ran
the spiking gun and Tom H kept the air compressor moving along in the Burro
Crane. Once we cleaned up our mess from the construction it was time to do
a rough alignment of the track to make surfacing easier later on.
We hooked a chain to the Burro and at an
angle and tugged on the track to drag it into place, 15’ from 11-3 track.
With a motivated crew, we figured the next reasonable step
would be to dump ballast on our new track.
Jamie K and Pete P grabbed the USA 8537 to dump the ballast. An attempt to move the cars with the Model 50
burro proved to be too much on the tough grade into the barn. Adam R, Pete P, Tom H and Steve L ran the
four ballast doors while Frank D and Jamie K ran the move. We dumped the entire track with a car and a
half of stone in a matter of minutes.
Our last task, due to the dwindling light, was to plow out the ballast
with our new Amtrak Ballast regulator to prep for the tamper. This was the first time we’ve used this
machine and I think we can all say it was an amazing success. A few minor tweaks and lack of use issues came
up, but we did manage to run the machine down the entire track without any real
problems. It will be a good machine once
we get it through ‘our shop.’
With this said, 11-4 track is completely built! This
Saturday we will begin the process of getting the Amtrak Jackson 6000 tamper
adjusted, lubed and running and hopefully continue to reload our ballast
cars. Until the electrical portions of
the building are complete, we will work on raising 11-4 track inside the barn
and tamping the approaches to the doors outside of the barn. This will be a process of raising, dumping
stone, regulating, raising…and so on. We
need to raise the track up nearly a foot in some places and that will take
time.
Congrats to everyone so far who’s
helped on this project.
The help from
within the museum really makes things easier for everyone working and shows the
commitment they have toward the museum.
To
find more pics on the Yard 11 project Frank D regularly updates his page here:
http://www.irm.org/gallery/album182
Check ‘em out. Thanks,
Adam Robillard
IRM Roadmaster
Comments
Sun, 05-19-2013 22:13
Hello again. I had an idea that was (somewhat rudely, mid-sentence) dismissed in talking to a museum volunteer a few years back, but here it goes [...]
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!