Earlier in the week on Monday morning, Dave Diamond drove the wheelset that was removed from 6847 along with the new motor to a shop just outside of Chicago. They pressed off the wheels and gear, machined the bearing surfaces on the axle, and pressed the gear and wheels back onto the axle and reassembled the combo with new support bearings. Initially there was over .350" of lateral between the old motor and wheels, which is out of tolerance. After the machining and pressing the gear into the correct place and after reassembly with the new motor and bearings, the lateral was .079" where it should be. Dave Diamond helped us out again and picked up the combo on Wednesday morning and unloaded it in the steam shop under the overhead crane.
Saturday morning, Roger Broms, Dan Currens and myself arrived and started to do some other prep work including replacing a broken bolt on the nose pack, and then compressing it to be reinstalled once the motor is back in the truck. The nose pack is basically a rubber pad sandwiched between two thick bars of steel, which supports the nose end of the motor against the truck frame. We also mounted the blower duct and roller bearing boxes and then moved the motor to the drop table.
The Steam Department volunteers helped us out again as well by getting the drop table ready to go and helping get some tools and supplies, as well as operating the crane to stage the combo on the drop table for the installation. The 8537 was used to push the 6847 onto the drop table, centering the #5 axle over the table. The position of the pedestals was marked on the table, and then the table was lowered a bit and moved to the west side of the pit. The centerline for the wheels were marked and then the combo was placed with the nose of the motor blocked up.
The table was lowered and moved back to the east side of the pit under the loco, and raised back up stopping occasionally to check clearances and to line up the roller boxes with the pedestals. We had to push the firemans side wheel over just a bit with a bottle jack to get it to line up exactly in the pedestals, then raised up some more. Eventually the motor nose supports lined up with those on the truck frame and we slid in the support pack and pinned it in, lowered a bit to remove the blocking under the motor, and then continued to raise the table until the springs seated properly over the roller boxes. The table was clamped back into place and the loco was moved back into the shop.
We then put the pedestal cross bars back on, remounted the brake shoes and shock absorbers, released the bolts holding tension on the rubber nose pack, hooked up the traction motor leads and inspected a few other items. After all that, we moved the loco back outside and Jim West helped move the 428 and Shay back into the steam shop.
There is a gallery setup with some random photos during the process of changing the combo, http://www.irm.org/gallery/diesel-november2010, they are mostly in order from the prep work, to removing the wheelset and old motor, to installing the new motor and wheelset. Thanks to everyone that helped during the entire process. Next year when the weather is warmer, we'll test everything out operationally and CNW 6847 will be back in service again.
We seem to be falling into a winter work pattern, with Saturday by far the busiest day in the shop areas inside Barn 4, then Wednesday, and Sunday holding onto third place. So take note that there is more space and less competition for machine time and bench space on the latter two days, if you want to work on your favorite project, or to just show up to watch and help the others.
Jeff Brady is working to glaze the top three openings on a new baggage door for Michigan Electric 28. This is a good cold weather project, when the barn space is really too cold to accomplish a lot. Ray Schmid is in the background painting the retainer beading for the glass.
Bill Moran was on hand and we decided to start the process of planing stock for a new roof on the Los Angeles coach using the planer to reduce the thickness of the new lumber (sawn on Saturday), to the planned 7/16". Here he is removing one of those 16 foot long strips from the outfeed end of the planer.
Comments
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!
Sun, 05-05-2013 18:53
Ah yes, I have made such Jibs myself. If it were me, I would add in each corner an angled piece from the base to the Jib to act as sway bracing. [...]