For a change of pace I will shake up the order in which I usually report things this time.
Last Saturday I mentioned about an upcoming project to extend the north (west) end of our Electric Trolley Bus line. Less than a week later the grass and topsoil has been removed, and new crushed limestone sub grade spread and leveled. The Thomas Event entry area will certainly look different this year.
Rich Witt is constructing a new fixture to be used on the Glen Springs windows and behind him Victor Humphreys is sanding panels for the new station door. These are a bit tricky to be fit absolutely the best way we can.
John Mc Kelvey has been doing a lot of work all related to his particular expertise in upholstering. This week he has repaired and reupholstered a chair back for the INGLEHOME. Seen here, he is cutting the new fabric.
Gerry Dettloff is helping out on the Lake Shore Electric 810. Much of the structural woodwork has been repaired on the north side. Now he is pulling down the tie rods within the side framing, one at a time, and welding threaded extensions on them. The existing ends were so corroded and rust thinned as to be useless. Hmm, he seems skeptical of my new camera.
Comments
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!
Sun, 05-05-2013 18:53
Ah yes, I have made such Jibs myself. If it were me, I would add in each corner an angled piece from the base to the Jib to act as sway bracing. [...]