Progress in the Steam shop continued steadily over the last two weekends.
Jeff has continued the shop reorganization to the point that many of the large parts are now arranged on the East side while still allowing plenty of space to work on the super heater flues when they return. He is now moving on to the machine shop which, when complete, will free up a lot more space around the wheel lathe.
Bob and others made use of the space around the wheel lathe to work on getting this operational.
The McCabe was refitted to its modified timbers, which allow it to be lifted on the pallet jack. Thanks to Bob Kutela for his help and use of tools for this. The modified timbers will allow us to move this machine, although moving what we estimate at about 6 tons will never be easy.
The trouble with this machine is that it needs a lot of space around it when it operates but is used only infrequently. However, what it does, in smoothly bending heavy boiler plates, is critical It was used last weekend in a first test for bending the new corner patch for 1630's firebox. This successfully demonstrated that we have the dies of the machine correctly set up to make the critical curve.
On 1630 substantial progress was made on the boiler cleaning.
· Having successfully tested the breathing system and sand blasting equipment, the next major job was to minimize the flow of dust into the shop. The last time this was done the locomotive was pulled outside but we certainly do not want to wait for Spring to do this !!
· Collin and I closed up the boiler with tarpaulins and set up ducted extraction from the chimney. With fans on the footplate we can establish a flow from back to front and "most" of the dust is pumped out of the door.
· The first blasting was very successful. We largely cleaned the critical firebox top and side seam areas in about 20 minutes. Glad to say it all looks good and free of any sign of cracks so far.
· From this exercise we learned that the blast medium we were using works well, so we can order in a large quantity for next weekend. We also learned that, while the ducting works pretty well, the missing firebox corner creates a significant leak that will need to be plugged next weekend. Collin was very comfortable in the boiler with the new breathing system ..... the rest of the team, outside in the shop, were less comfortable than he was!!.
· Cleaning of the boiler interior can now be moved forward quickly.
Getting the super heater flues back from sand blasting is proving problematic. They have been ready since New Year. Snag is that they must not get wet and need to be collected weekdays or early on a Saturday morning. Each time we have set up a crew to take the truck on a Saturday, the weather has turned cold ...... and the truck does not operate reliably is really cold weather.
In other areas a good deal of machining was progressed for 428.
I am now away on business for two weeks so no update next week. However, as the trip is to the UK, I may actually see some working steam next weekend.
Nigel Bennett
Comments
Sun, 05-19-2013 22:13
Hello again. I had an idea that was (somewhat rudely, mid-sentence) dismissed in talking to a museum volunteer a few years back, but here it goes [...]
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!