It was a low turnout at the Steam Department today, in part because several of the team were at Harper staffing the stand at the High Wheeler show. The weather may have deterred some and it certainly was not kind to the shop!. The ice brought down a large section of guttering and the machine shop furnace failed, which lead to some time spent investigating the gas leak.
Glenn and Mike made great progress on the super heater flues. 7 of 16 are now cut and ready for safe ending.
Sand blasting was on hold as Collin was away. Jason tried but found it difficult to work in the boiler due to the accumulation of blasting sand. This made for an unstable base on which to stand in the confined space of the barrel.
We therefore brought forward the task of clearing sand from the boiler. The technique may not look pretty but it works. The material is so dense that suction is not effective. It is not easy to sweep or push in the confined space of the boiler but pushing it to the main drain plug and setting up a chute there proved to be the most effective method.
In this way we have now removed several hundred pounds of the material from the boiler.
Several key additional pieces of equipment arrived that should allow us to move forward next week. We now have the angled tips for the sand blaster that will allow the corners of the firebox to be cleaned. A dust collector was installed that improves the extraction of dust from the boiler during sand blasting.
With the arrival of a new and more powerful vacuum, substantial progress was made in removing residual lagging material. This tends to accumulate everywhere as the material fragments as it is removed. Cleaning this up to enable inspection and refitting is one of many mundane but essential steps in the overhaul.
Mike was working on the mud ring where the patch is to be installed. This is being ground out in preparation for welding to make good small areas of damage that have been detected. Once this is done the surface will be prepared for fitting the new material of the patch.
Nigel
Comments
Sun, 05-19-2013 22:13
Hello again. I had an idea that was (somewhat rudely, mid-sentence) dismissed in talking to a museum volunteer a few years back, but here it goes [...]
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!