It was a low turnout at the Steam Department today, in part because several of the team were at Harper staffing the stand at the High Wheeler show. The weather may have deterred some and it certainly was not kind to the shop!. The ice brought down a large section of guttering and the machine shop furnace failed, which lead to some time spent investigating the gas leak.
Glenn and Mike made great progress on the super heater flues. 7 of 16 are now cut and ready for safe ending.
Sand blasting was on hold as Collin was away. Jason tried but found it difficult to work in the boiler due to the accumulation of blasting sand. This made for an unstable base on which to stand in the confined space of the barrel.
We therefore brought forward the task of clearing sand from the boiler. The technique may not look pretty but it works. The material is so dense that suction is not effective. It is not easy to sweep or push in the confined space of the boiler but pushing it to the main drain plug and setting up a chute there proved to be the most effective method.
In this way we have now removed several hundred pounds of the material from the boiler.
Several key additional pieces of equipment arrived that should allow us to move forward next week. We now have the angled tips for the sand blaster that will allow the corners of the firebox to be cleaned. A dust collector was installed that improves the extraction of dust from the boiler during sand blasting.
With the arrival of a new and more powerful vacuum, substantial progress was made in removing residual lagging material. This tends to accumulate everywhere as the material fragments as it is removed. Cleaning this up to enable inspection and refitting is one of many mundane but essential steps in the overhaul.
Mike was working on the mud ring where the patch is to be installed. This is being ground out in preparation for welding to make good small areas of damage that have been detected. Once this is done the surface will be prepared for fitting the new material of the patch.
Nigel
Comments
Mon, 06-17-2013 09:50
Wish I could be there to help.
Fri, 06-14-2013 16:50
Matthew, Any special event is the decision of the museum Board. My personal opinion is that it is likely that there would be a special event to [...]
Thu, 06-13-2013 18:33
Hi, I have a question, if or when she is restored and back up and running this or next year. Will their be a special event set up for the return of [...]
Tue, 06-11-2013 22:36
The whistle 1630 wore for a while that you're thinking of was a Frisco 6 chime donated by a former member of the steam shop. It was on it a few times [...]
Tue, 06-11-2013 18:03
You are talking here about something well before my time !. I have not seen her with anything other than the whistle she now carries. If she [...]
Mon, 06-10-2013 16:17
i'm curious here. Will 1630 ever wear the ATSF 6 chime she had on for a while? Better defines her, I love the deep whistle she has now but the higher [...]
Sat, 06-08-2013 15:15
Many many many many many thanks for getting the Spaulding webcam working!!!!!
Fri, 06-07-2013 16:55
The donation was to the museum as a whole. How it is used and whether any comes to steam department projects will be the decision of the museum [...]
Fri, 06-07-2013 16:53
Basically the plan is "ONLY" reassembly. As far as we know she is is reasonable mechanical shape. The big mechanical problem that stopped her (slack [...]
Fri, 06-07-2013 16:28
Nigel I read you guys got a one million dollar check donation!!! Will this be used to finish 1630 ,428, 5 and get started on the others next in line?
Fri, 06-07-2013 16:16
So does 1630 basically only need reassembly? With the boiler in particular. Does her tender or running gear need any work before she's ready for the [...]
Fri, 06-07-2013 12:00
Hello.. The voltage we are using and presumed the RR also used is 120 vac. The system is a little unique because the lite bulbs are each 60 volts. [...]