A very strange day at the steam department. The temperatures were more like May than March but one of the "isolated thunderstorms" seemed to take aim at Union. I have rarely seen rain and hail like it and a significant part of the morning was spent clearing drainage as water building up between the shop and barn 9 started to flood into the shop.
However, when the storm had passed it became a beautiful day and we were able to carry out the shunt to move the Shay truck out of the shop for steam cleaning. This was rather a "rush job" as no one had expected conditions to be good enough for this so soon.
All the equipment started well after the winter so it proved possible to get everything shunted by 1:30.
So several hours of steam cleaning were done, removing probably 30 lbs of caked grease and muck.
This area of the truck frame was previously completely filled with hardened grease and muck.
This had to be done using the old steam department machine as the more powerful car shop one was not yet serviced. Hopefully we can borrow that next time the weather is favorable. Now that all the equipment is set up it should be much quicker to shunt the truck outside next time.
Nothing is ever as easy as you hope. The roof of the wheel drop is a bear to remove and replace, requiring use of the Bay City crane. As darkness falls, Phil and Cameron demonstrate the gentle art of removing the lifting hook that became wedged in the hoisting eye of the roof !!
Also on the Shay, Dennis completed welding the crack on the front surface of the cross beam so that repair should now be complete.
Unfortunately the weather was much less kind to work on 1630.
The target was to complete the interior sand blasting. Eric and others managed to completely clear the blast medium from the boiler and work was started on cleaning the belly section. However the humidity after the storm proved disastrous. Moisture in the compressed air caused the equipment to clog repeatedly and only about a third of the work was done before the equipment became completely useless. The rest of the day was spent removing the buildup of damp medium from the equipment and adding additional moisture collection points to the air feed. With these in place it should be possible to complete next weekend even if we do have similar conditions.
Bob and Paul prepared the cab for sand blasting the back head. To allow this, we needed to seal all open pipes and valves. This sandblasting should be a quick job once we can pull the locomotive into the open. There is no way of containing the medium when we do this so it must be done outside the shop. At the same time we will plan to lift out the throttle body for inspection.
Glenn and others finished painting the remaining super heater flues so they are now all ready for safe ending.
Work continued on machining various parts of 428 including the axle box plates, connecting rod ends and bushes.
Nigel
Comments
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!
Sun, 05-05-2013 18:53
Ah yes, I have made such Jibs myself. If it were me, I would add in each corner an angled piece from the base to the Jib to act as sway bracing. [...]