A good deal of progress was achieved on 1630 today despite a low turnout that was to be expected at Easter weekend.
The main effort was heavy duty cleaning. The objective was to clear the abrasive and associated dust from the locomotive top down so as to minimize the amount above the wheels and motion before the sheeting could be removed. This was achieved and she now looks recognizable again with the wheels and rods uncovered ready to shunt next weekend.
Matt spend several hours inside the boiler sweeping, shoveling and finally vacuuming the sand from the boiler barrel. There is still some more to remove from the sides and top of the firebox but the barrel itself is now clear and open again at both ends.
Looking in from the front the view is open thru to the firebox again. The tubes are clear of the sand that could be seen in the views last week. The strange rod running between the tube sheets was being used to measure lengths for the super heater flues.
The scale of the effort over recent weeks can be judged from the medium removed. Each of these tubs is about 80 pounds and there are several more that did not fit on the pallet!. Paul, Ed and I were kept busy shifting the material that Matt pushed out while also cleaning the outside of the locomotive, tender and surrounding areas of the shop.
The decision was taken not to use sandblasting on the footplate. We will needle chip the back head as the effort of removing the medium would outweigh the gains of quicker cleaning. The diesel department moved the rotary snow plough from in front of the shop so, weather permitting, we are now ready to shunt outside next Saturday. The objectives then will be steam cleaning to remove any remaining residue and prepare for painting as well as lifting out the throttle valve body for lapping.
We were also able to start work on preparing the super heater flues for refitting (safe ending). The preparation is complex because there are small but significant length differences between different areas of the tube sheets so the final length of individual flues will vary by about 1/2 inch. The length of each flue is currently different depending upon how much was lost in cutting each one out of the boiler. There is a limit to how long the narrow section can be so each flue must be measured to determine if it can be fitted by attaching a safe end just at the narrow end or if it must be extended at both ends. Once this is done work will begin on cutting the required extension pieces matched to each flue.
After we had removed the sand blast material from the area, Mike was able to restart work on the firebox patch. Progress here will depend upon availability of our welding expert to build up the mud ring.
In other areas:
· Steve, Bob and Ed were working on the hydraulics that will drive the planer. This machine will significantly increase our capability to machine axle boxes and wedges, which is currently a very slow process.
· Cameron was using the shaper to prepare the sections that will be used to build up the axle boxes for 428.
Nigel
Comments
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!
Sun, 05-05-2013 18:53
Ah yes, I have made such Jibs myself. If it were me, I would add in each corner an angled piece from the base to the Jib to act as sway bracing. [...]