| BLOG | DIRECTIONS | SCHEDULE | STORE | |
Sunday, April 29. 2012Steam Department Update 4-28-2012A rather brief update this week, not because of lack of progress but because I spent most of the day in the rules and safety sessions so was not directly involved in the work in the shop. While this was a day away from the shop for a number of us it is essential that we have a team able to control movement of equipment and these sessions are critical to ensure that this is done safely. Work progressed steadily on 1630: · Collin, Eric and Jason made good progress on cleaning and preparing the tube sheets. Both front and back tube sheets have now been extensively cleaned and checked. The good news is that no signs of cracking have been found. Work is progressing on smoothing and preparing the holes to take the new tubes. This will take several weeks to complete but good progress was made today. · Dennis, Bob and Mike continued building up of the mud ring ready to for fitting of the corner patch. Over the next couple of weekends this will move out of sight as the section inside the firebox is built up and the rivet holes on that face are rebuilt. · Plans are in place to do the thickness testing next Saturday. This weekend we were marking out the points at which measurements will be taken. Each section of the boiler plate work must be measured to assess its minimum thickness which then forms the basis of the calculation for the form 4. Clearly each part of the boiler is only as strong as its weakest point so the calculation is based upon the thinnest point found in each section. Measurement points are identified in a random pattern across each plate with a focus on the areas likely to be weakest such as the belly. Here the guys are cleaning off and marking measurement points ready for next weekend. Nigel Sunday, April 22. 2012Steam Department Update 4-21-2012A successful day at the steam shop. We now expect the ultrasonic testing to be done weekend of May 5th so yesterday was an opportunity to progress other activities in preparation. 1630 saw the light of day for the first time in nearly a year when we pulled her out to remove the throttle valve and allow cleaning of both the locomotive and the shop area where she has been sitting. Eric and his father made good progress in testing the tell tale holes in the firebox stays. The engineer's side is now largely complete. By midday Jeff had the BrownHoist de-winterized and running and we were ready to shunt 1630 out of the shop. Once outside we worked on the removal of the throttle body, which will be lapped to ensure a good seal when reassembled. This is an awkward piece that sits in the dome. However, with some help removing cotter pins from inside the boiler, it was removed and taken to the shop. It has apparently been removed and refitted in the past with all the tubes in place. I have a lot of respect for the guys who achieved that !!. It was good to see 1630 in steam again !!. Seriously though, it was an opportunity to do some steam cleaning and the locomotive now looks a good deal better and easier to inspect. The opportunity was also taken to clear the area around and under the locomotive, that had accumulated the most amazing collection of insulation debris and other muck as well as odd items that had fallen while working. By end of day she was back in the shop and ready for ultrasonic testing. In other areas, Paul and the lads made good progress on needle chipping and wire brushing the Shay truck. Glenn over came a problem, that has developed in recent weeks, of the fork lift battery failing to hold a charge. Far from the suspected defective battery he found that a loose terminal and blown fuse in the line from the alternator meant the battery had not been connected to the charging system at all for the last few weeks!!. Next weekend will probably be quiet as many of us need to attend the rules exam. Nigel Sunday, April 15. 2012Steam Department Update 4-14-2012A very productive day thanks to a good turnout. We did not move 1630 as Dennis was available to do welding on the mud ring for the firebox patch. Good progress was made on this. The metal has now been made good around all the rivet holes from the outside. Once the last of the holes is re-drilled accurately from the inside the metal can be made good on the inside. (One side must be done at a time so that there is always a pilot hole to ensure that the finished rivet holes are accurately aligned). Now that the sand blasting and associated dust are finished several other jobs could be progressed. · Collin and Jeff C thoroughly needle chipped and wire brushed the back head so that is now ready for inspection and ultrasonic testing; · Eric and Jason cleared and checked the tell tale hole in the stays on the engineer's side. This is a dirty and tedious but essential task as we must prove that these holes, which would leak water and provide an indication should the stay break, are all clear to the required depth; · Matt finished removing the blasting medium from the firebox crown and Bob cleared it from the sides of the firebox so it is now clear in most areas; · We continued the detail measurement of the super heater flues and should soon be ready to start preparing the material for safe ending; · Jason and Eric moved on to cleaning up the inside of the tube sheet for final inspection and preparation to refit the tubes. The sheet must be closely examined for any cracking between the tube holes then the edges of each hole must be made good where necessary and smoothed to ensure a snug fit when we use the rollers to expand the new tubes into place. We are now scheduling the long awaited ultrasound testing that will provide the basis for the critical form 4 calculations in support of the new certification. Work continued in a number of other areas progressed in previous weeks such as the planer and the boxes for 428. In addition, Rick and Ed cast the firebrick for the riveting furnace that we need to complete 428's cab. That is an important mid-term objective as refitting the cab to 428 would free up a very useful area of the shop for other fabrication work. Jeff worked on lubrication of the Brown Hoist crane in preparation to pull 1630 out. We will do this as soon as weather and other jobs, such as the welding and the ultrasound testing, permit. We also managed to largely clear the area between the shop approach and barn 9. B & G are planning to grade this once it is clear, reducing the risk of flooding and hopefully providing a more stable surface. This area is a long standing problem as parts of it are no more than fine sand or dust not far removed from quicksand. It proved its capability again yesterday when the forklift became bogged and we spent an hour extracting it!!. Nigel Sunday, April 8. 2012Steam Department Update 4-7-2012A good deal of progress was achieved on 1630 today despite a low turnout that was to be expected at Easter weekend. The main effort was heavy duty cleaning. The objective was to clear the abrasive and associated dust from the locomotive top down so as to minimize the amount above the wheels and motion before the sheeting could be removed. This was achieved and she now looks recognizable again with the wheels and rods uncovered ready to shunt next weekend. Matt spend several hours inside the boiler sweeping, shoveling and finally vacuuming the sand from the boiler barrel. There is still some more to remove from the sides and top of the firebox but the barrel itself is now clear and open again at both ends. Looking in from the front the view is open thru to the firebox again. The tubes are clear of the sand that could be seen in the views last week. The strange rod running between the tube sheets was being used to measure lengths for the super heater flues. The scale of the effort over recent weeks can be judged from the medium removed. Each of these tubs is about 80 pounds and there are several more that did not fit on the pallet!. Paul, Ed and I were kept busy shifting the material that Matt pushed out while also cleaning the outside of the locomotive, tender and surrounding areas of the shop. The decision was taken not to use sandblasting on the footplate. We will needle chip the back head as the effort of removing the medium would outweigh the gains of quicker cleaning. The diesel department moved the rotary snow plough from in front of the shop so, weather permitting, we are now ready to shunt outside next Saturday. The objectives then will be steam cleaning to remove any remaining residue and prepare for painting as well as lifting out the throttle valve body for lapping. We were also able to start work on preparing the super heater flues for refitting (safe ending). The preparation is complex because there are small but significant length differences between different areas of the tube sheets so the final length of individual flues will vary by about 1/2 inch. The length of each flue is currently different depending upon how much was lost in cutting each one out of the boiler. There is a limit to how long the narrow section can be so each flue must be measured to determine if it can be fitted by attaching a safe end just at the narrow end or if it must be extended at both ends. Once this is done work will begin on cutting the required extension pieces matched to each flue. After we had removed the sand blast material from the area, Mike was able to restart work on the firebox patch. Progress here will depend upon availability of our welding expert to build up the mud ring. In other areas: · Steve, Bob and Ed were working on the hydraulics that will drive the planer. This machine will significantly increase our capability to machine axle boxes and wedges, which is currently a very slow process. · Cameron was using the shaper to prepare the sections that will be used to build up the axle boxes for 428. Nigel Sunday, April 1. 2012Steam Department Update 3-31-2012A rather limited turn out at the shop this Saturday with several people helping at the book store to catalog and prepare a large collection of model locomotives recently received thru a donation. However the key target on 1630 was achieved. The sand blasting of the boiler interior is now complete and a few of us were able to start removing all the ply that sealed the boiler and cleaning the dust and sand from the locomotive. Despite all the sealing the process creates a vast amount of dust and some escape of the abrasive. We now need to remove as much as possible of this from areas close to bearings etc. before we can move her outside to sand blast the back head. At that time we will aim to give her a thorough cleaning. The interior of the boiler shows the progress that has been made and also provides some unusual views of the inside of a locomotive boiler. Here you can see the top and part of the side seam of the firebox. The many long vertical and shorter horizontal stays hold the inner and outer fireboxes together. In use the inner firebox must always be completely covered by water but most of the height above the firebox crown would be steam. The water and steam are all at a pressure of 180 psi. The extensive stay system is required to hold the inner and outer firebox together against that pressure. On the left you can see one of the super heater flues and two of the smaller fire tubes that have been left in place. On the right are the holes from which other flues and fire tubes were removed to allow access to the boiler for cleaning and inspection. In this picture they are still blocked by the ply sheet used to contain the blasting abrasive but soon they will again be open to the fire space. In this shot we are looking forward toward the front tube sheet. Here you can clearly see where the majority of the tubes had to be removed to allow access to the sides and bottom of the boiler and only a few remain in the center. At this point the holes were still blocked by ply sheets but, by end of day, they were again open to the smoke box. Above you can see the long braces that secure the top section of the tube sheet to the boiler barrel. Again the whole structure is built to resist a pressure of 180 psi. The tubes themselves brace the lower part of the tube sheet but above the level of the tubes (an area that would be full of steam, when in operation) the braces are required to prevent the tube sheet being pushed forward by the pressure.
This view shows the top of the front tube sheet more closely. Here you can see the heavy attachment of the braces to the tube sheet. To understand why they are so heavy do a quick calculation. At 180psi the load on an area about 10 inches square is around one ton!!. In the center can be seen the dry pipe. This carries steam from the throttle (high in the dome) forward to the super heater header (in the smoke box on the other side of the tube sheet) and then on to the cylinders. It is called the dry pipe as the steam that it carries is now separated from the water in the main space of the boiler. This view also shows the work still to be done in removing the abrasive that still sits on top of the tubes and other surfaces within the boiler.
Meanwhile Paul made good progress on needle chipping and wire brushing the truck of the Shay. With the thick crud removed it can now be taken down to clean metal for final inspection and then repainting. The bolster now looks pristine after Paul's efforts.
This makes an interesting comparison to the shot of the same part 11/26 last year. Nigel |
Blog AdministrationFind us on FacebookCategory TreeCalendarQuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Sun, 05-19-2013 22:13
Hello again. I had an idea that was (somewhat rudely, mid-sentence) dismissed in talking to a museum volunteer a few years back, but here it goes [...]
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!