| BLOG | DIRECTIONS | SCHEDULE | STORE | |
Sunday, December 30. 2012
Steam Department Update 12-29-2012 Posted by Nigel Bennett
in Steam Department at
18:36
Comments (2) Steam Department Update 12-29-2012It is a "second-hand" update this weekend, courtesy of Phil Cwikowski. I did not make it to Union this Saturday as we had family visiting. Unfortunately, absent anyone who had experience with the tube roller, we were not able to roll more tubes into 1630 but a good deal of other progress was made. On 1630: · measurements were taken to fit the ferrules for the super heater flues. It looks as if we have enough for the firebox but will need to find or make some more for the smokebox; · the flues are now alongside the locomotive ready for refitting when the fire tubes have been secured; · the scaffolding and spare tubes have now been cleared so that we have free access to the front of the locomotive again; · needle chipping of the cylinder covers was completed and primer was applied to protect the cleaned surfaces; · the valve chambers were checked for sand blast material that could have been carried over from the boiler cleaning. The good news is that they appear clean and free of debris. In other areas: · Major progress was made on the wheel lathe. Air pressure was applied for the first time in decades to release the lock holding the back head. With this done, attempts were made to move the back bead on its slides ........... and it moved!!. This is critical as the back head weighs several thousand pounds and, were it jammed, it would require very heavy equipment to free it. After this the gear for turning the shaft of the back head was investigated and this was also turned. All of this checking is critical as these parts are normally moved under the power of substantial geared motors. Since it has not operated in many years it is critical to ensure that these huge parts are free to move before we apply power as major damage could occur if they are jammed when power is applied. The tricky part is judging the difference between jammed and normal resistance when it is normally moved by a large motor thru substantial gearing !!. · Stu and Bob returned to work on the planer and further progressed the cleaning and reassembly of this machine; · We gathered the information to calculate the total weight of the new air compressor and motor assembly so that Rick can now identify the vibration isolators that we will need to mount it. So progress on a number of fronts. Hopefully next week we can continue with the tube rolling. Nigel Wednesday, December 26. 2012
Steam Department Update 12-22-2012 Posted by Nigel Bennett
in Steam Department at
18:03
Comments (0) Steam Department Update 12-22-2012With Christmas close it was a small but active team at the steam shop this weekend. The next major milestone on 1630 was achieved as planned. The last 17 fire tubes were loaded so all except for the 9 that will be installed along with the super heater flues are now in place. Then we moved on to rolling the fire box ends. As with each step, this was initially slow. It is critical that we fully understand the technique and can do it right each time before we start to do it on a large scale. However we made a good start, got more confident as the day progressed, and by end of day the first 15 were rolled. Looking closely at the view below you can see the effect. Comparing columns K, L and M to the adjacent columns, these are now tight in the tube sheet and set at a consistent 1/4 inch projection beyond the sheet. Once we have proved that everything is watertight the projection will be beaded over. All tube ends in the fire box are beaded to protect the joint from the direct effects of the fire. The rolling requires a team of three and is achieved by first setting the tube accurately with a 1/4 inch extension beyond the tube sheet. The team member in the smoke box then clamps that end of the tube to prevent movement. The roller is then inserted into the tube. Here you can see the construction of the roller. Three small hardened rollers are turned by the rotation of the tapered pin that is inserted thru the center. The air motor is attached and rotates the central tapered pin. The rotating pin is slowly drawn into the roller forcing the three hardened rollers out into the wall of the tube slowly increasing its diameter. When the tube is fully expanded against the ferrule and tube sheet the taper pin has been largely drawn into the roller. The motor is then reversed to free the pin and the process continues with the next tube. In addition to the work on the fire tubes: · annealing was completed on the 16 super heater flues, so these are now ready to load once the fire tubes are secured; · drilling continued on the fire box patch. The holes are now complete on the front face. Once holes are made in the side face it will be finally formed to the mud ring along its whole length. We also took advantage of reasonable, if cold, weather to jack the end of the KCS tender to remove the wood packing that was left between the rubbing plates when it was delivered. This should now be in a condition which will allow it to be shunted so that the box cars of parts can be relocated back by the road to allow access. Nigel Sunday, December 16. 2012
Steam Department Update 12-15-2012 Posted by Nigel Bennett
in Steam Department at
12:14
Comments (4) Steam Department Update 12-15-2012I suspect that a number of steam shop volunteers are, like me, feeling rather stiff, aching and bruised this morning. However, that is an indication of a very productive day yesterday. On 1630 the re-tubing is almost at the next key milestone. All but 17 of the tubes below and around the super heater flues are now loaded into the boiler and, by end of day those 17 are all cut to length. So it should not take more than an hour to load these next week. Those following the progress chart will notice a discrepancy between the full total of 180 and the target (171) that we are currently working toward. These are the 9 fire tubes that lie in between the super heater flues that have been removed. These will not be loaded at this time but slotted in as the super heater flues are fitted. This will not be done until the 171 are secured by expanding. After a couple of hours hammering ferrules into the remaining holes in both tube sheets, loading started in earnest. Here Phil stands on top of the large pile of tubes on the staging.
Phil selects a tube of the correct length and passes it to the team who feed it into the next hole in the front tube sheet. Slowly it gets more and more restricted in the barrel. Matt (believe me this is Matt !!)guided the tubes thru the barrel at the sides and here at the bottom under the super heater flues. By this stage he was looking rather uneasily at the space left for him to make his exit !.
Shortly after this, Matt squeezed his way out thru the remaining gap leading to the access hatch, having finally checked that no rogue objects remained in the boiler. Hopefully this is the last time that anyone will be able to get to the bottom of the barrel for the next 16 or so years !!. Squeezed in between the siphons in the firebox I was guiding the ends of the tubes into the rear tube sheet. Once Matt was out, we continued loading tubes by sliding them in on top of the ones below. The trick to this is the guy in the firebox (normally me !) who has to catch the end of the tube with a hammer handle, lift and then guide the end into the rear tube sheet. By the end of day you can see the 17 remaining gaps in the front sheet and the large number of tubes now in place can be seen thru the super heater flue holes.
Inside the boiler is a very different picture when compared to where Matt was lying a few hours earlier The rear tube sheet now is now largely full with the small area of projecting ferrules indicating where the remaining tubes will be fitted.
Comparing this to the shot at start of day shows just how many tubes have been moved into the boiler. The staging area beside the locomotive is now empty. We are starting to get space back into the shop. It is amazing the sheer volume of tube that fits into the boiler. The one thing that slowed us towards the end was that you can no longer keep a stock of cut tubes ready to load. With only a few to go, they have to be exactly the sizes required for the remaining holes. So we stopped loading in mid evening, having loaded all the precut tubes. We then cut the exact sizes needed for those 17 holes ready for next Saturday. Work also started on annealing the super heater flues ready for loading and expanding. This will be a different technique from the fire tubes as they are too large in diameter to fit the furnace and will need to be heated using the acetylene torches. The first of these was annealed yesterday (1 down 15 to go). Meanwhile work continues on fitting the corner patch to the firebox. Here Mike and Jerry are drilling the patch using the pillar drill. Much to our relief, Dennis our welding expert who has been away for a number of weeks, made it in yesterday. This was critical as the team fitting the patch need to work closely to his requirements in shaping and fitting the patch. Dennis was also able to start on welding the gear for the wheel lathe while Mark started work on freeing the back head on its slides so that it should move when the gear is attached. Overall a very successful day. Nigel Sunday, December 9. 2012
Covered space for steam collection Posted by Nigel Bennett
in Steam Department at
16:12
Comments (0) Covered space for steam collectionIn parallel with bringing #1630 back into operation we urgently need to improve the storage of our non operating steam locomotives. Many of our locomotives are currently stored outside where they are deteriorating. As detailed on the Illinois Railway Museum main website, the museum is currently planning an additional covered storage area. Space in this building will be provided based upon the cost of the building, which works out at about $215 per foot length. This is a substantial cost for a large steam locomotive which can be about 100 feet in length. Some of our best examples, notably the Burlington Hudson #3007, do not have dedicated covered track space. (While it is currently under cover it is occupying general department space and would potentially have to be put outside again when we have locomotives in operation). Other items that we would dearly like to get under cover, where they could be cosmetically restored for better display, are the Rock Island 4-6-2 #938 and C&O 2-8-4 #2707. Please consider donating to the fund raising for barn #14 nominating the steam department. As an added incentive, we have a number of the "Burlington Bulletin" books on the S-4 Hudsons including #3007, which we will provide to anyone who can donate $25 or more to the steam department for covered space. Nigel Sunday, December 9. 2012
Steam Department Update 12-08-2012 Posted by Nigel Bennett
in Steam Department at
15:17
Comments (10) Steam Department Update 12-08-2012There were two very separate activities at the steam shop this weekend. Outside, the Kansas City Southern tender from Galt arrived and had to be unloaded and put back on its trucks (which had arrived separately during the week). Here the rather unusual trucks of this tender await the arrival of the tender itself. The tender is a fairly substantial items as can be seen from comparison to the B&G building as it enters IRM for the first time. A good deal of careful back and fore was required to position the tender (still on the trailer) centrally over the track so that the mounting points would be in the correct position to fit into the trucks. Once in place steel beams were located under the body. The trailer had then to be raised, blocks placed under the beams, and then lowered a number of times until there was sufficient height to set jacks under the beams. Finally the jacks were all placed and the tender could be raised off the trailer. The trailer is free and starts to move out from under the tender. The trucks are chained to the trailer and each other so that they are pulled under the tender, at the correct spacing, as the trailer pulls out. The job of lowering the tender back onto its trucks so that the pins aligned and the pivot points located into the sockets in the trucks proved to be a long and tricky exercise. It was well past dark by the time this was completed so pictures of the completed tender are for next week !. On 1630, things looked bleak in the morning. We are absolutely dependent for tube loading on those of the team who can fit into the boiler. Having arranged a morning and afternoon shift, as it is more than one person can do to work in these conditions all day, Collin's car failed and he was not able to get to Union in the morning. However, while we lost the morning shift, Jason did sterling work in the afternoon. Here we see him "relaxing" between loading tubes. It is not a environment in which you can work for more than a few hours at a time. We have now completed loading of the tubes down both sides of the super heaters. The fireman's side, looking forward, now looks pretty full compared to earlier views when we were sand blasting. Looking toward the firebox on the engineer's side also shows the boiler filling rapidly. This also shows the positioning of the copper ferrules, which are set slightly below the surface of the tube sheet in the firebox, where the end of the tube will be beaded, but projecting into the boiler barrel, where the copper can be seen around each of the new tubes. Mike continued work on drilling the rivet holes in the patch. The accurate alignment of these holes is proving to be a significant challenge. Nigel Sunday, December 2. 2012
Steam Department Update 12-01-2012 Posted by Nigel Bennett
in Steam Department at
12:17
Comments (0) Steam Department Update 12-01-2012It was a productive day at the steam shop again very largely focused on 1630. On 1630: · Matt and Stu stripped and cleaned the check valves. These critical valves are where the water is fed into the boiler (from the injectors). These will be essential to even the earliest hydro tests. Since these valves are directly attached to the boiler they must be fully pressure tight to allow any testing. (The first tests will be done when the tubes have been rolled into place to identify any that require further rolling to make a perfect seal. At this point no accessories will be connected to keep the test very simple). It was inevitable that sand blast material got into the valves. In addition, one suffered from occasional leakage when last in use. Both were cleaned and lapped. The seat was replaced on the engineer's valve so these should now be in good shape for testing and service. · The firebox patch is now ground to shape and fits well onto the mud ring. Mike and Jerry were starting to drill the first hole. Initially a bolt will be fitted. Once the patch is rigidly bolted into place the bolts will be replaced, one at a time, by rivets. This requires considerable care as the holes in the mud ring are at different angles so each must be drilled thru the patch using guides to ensure that each is an exact match to the ring. Once the bolts are in place the patch can be rigidly secured and finally adjusted to form a perfect match to the sheets. · The last (hopefully) of the tubes were swaged and annealed. We have a few extra tubes that will be held in case of need should any be damaged in fitting but, on current calculation, we now have enough prepared to fully tube the boiler. In the next few weeks, when we have sufficient people available, we will swage the tubes for Shay #5. Having all the equipment set up and people now familiar with it will make it a lot more efficient to do these now. · As mentioned last week, the decision was taken to fit copper ferrules to the front tube sheet. Although the front sheet is often not ferruled, fitting ferrules will give greater assurance of a leak free seal. Unfortunately this means removing the tubes that were previously loaded. During the day the tubes were removed from the engineers side and the first 30 were reloaded with ferrules fitted. The process was, as always, somewhat tentative at first. However, once the method was established it moved a lot faster so we should be able to have all the tubes, that were previously loaded, refitted with ferrules in place and move on to new ones next weekend. After final cleaning the valve block for the planer was painted so that should be available for reassembly in the near future. Nigel |
Blog AdministrationFind us on FacebookCategory TreeCalendarQuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Sun, 05-19-2013 22:13
Hello again. I had an idea that was (somewhat rudely, mid-sentence) dismissed in talking to a museum volunteer a few years back, but here it goes [...]
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!