It was a productive day at the steam shop although the weather was rather unkind, given our priorities.
On 1630 the whole focus was upon continuing the fitting of fire tubes. As noted last week, our first priority was on trying to make the smaller air motor work with sufficient power to drive the tube rollers and so avoid trying to handle to the large motor in confined spaces.
Moving the Sullair to the North end and rigging a holding reservoir to assure minimal pressure drop as the motor works should have been simple. It took Phil and me rather longer with a few challenges such as melting the wheels out of huge blocks of ice that had frozen it to the ground !. However, Glenn's good work over the summer paid off. The compressor starts well even at 15 degrees.
The effort was a success. The smaller air motor with this enhanced air supply will successfully drive both the straight and flaring tube rollers. This unimpressive looking reservoir, close to the locomotive, proves invaluable in maintaining pressure as the tube is rolled.
The results were impressive. We were able to both largely complete expanding the tubes in the firebox and reach about 25% completion of rolling at the smokebox end.
We now have just two tubes in the main area to refit. We decided to expand all tubes before addressing the ones where the ferrule "popped" during expansion. Only one did so this week. So we have that and the one from last week to refit before we have all fitted (aside from those between the super heater flues).
Rolling the tube ends is now a rapid process but is driven by preparation for the next step, which is flaring those tubes that are to be beaded after the first hydro test. These need to be fairly accurate to 1/4 inch projection at each end and the flaring is more effective if the length is adjusted before this is done. So, next week, a number of tubes that have excess length will need to be cut back to 1/4 inch with the angle grinder before flaring. This was expected. The tube sheets are not flat so each tube length is unique and must not provide less than the required projection, so you cannot hope to get each tube correct to 1/16th as they are fitted.
Here you can see some of the tubes (for example the two just left of the lowest super heater flue) that project further and will need to be trimmed before flaring.
Hopefully in the coming weeks we can get two teams working. Once the smokebox end of a tube is rolled, the firebox end can be flared. So it should be possible to have teams working in both firebox and smokebox at the same time. The developing number of tubes with blue paint marks is an indication of substantial progress
In other areas:
· The move of the McCabe was completed. This location will allow it to be used without further movement but keeps it out of the way.
· Jeff managed to get the scissor lift moved to the shop despite the icy conditions. This will allow work to start next week on installing the new air system into the South shop.
A demonstration ride on the lift provided a rare opportunity for a look at work in the shop from above. Looking the length of the shop, Jerry is relocating material to make way for the McCabe and, at the far end, work continues rolling tubes into 1630.
Looking toward the West wall, the team is working on the shaper.
· Stu and Mike worked on reassembly of the planer. Sorting out how the levers should link to the hydraulic control block appears to be a challenge judging by Stu's expression!
So, overall another week of good progress.
Nigel
Comments
Mon, 06-17-2013 09:50
Wish I could be there to help.
Fri, 06-14-2013 16:50
Matthew, Any special event is the decision of the museum Board. My personal opinion is that it is likely that there would be a special event to [...]
Thu, 06-13-2013 18:33
Hi, I have a question, if or when she is restored and back up and running this or next year. Will their be a special event set up for the return of [...]
Tue, 06-11-2013 22:36
The whistle 1630 wore for a while that you're thinking of was a Frisco 6 chime donated by a former member of the steam shop. It was on it a few times [...]
Tue, 06-11-2013 18:03
You are talking here about something well before my time !. I have not seen her with anything other than the whistle she now carries. If she [...]
Mon, 06-10-2013 16:17
i'm curious here. Will 1630 ever wear the ATSF 6 chime she had on for a while? Better defines her, I love the deep whistle she has now but the higher [...]
Sat, 06-08-2013 15:15
Many many many many many thanks for getting the Spaulding webcam working!!!!!
Fri, 06-07-2013 16:55
The donation was to the museum as a whole. How it is used and whether any comes to steam department projects will be the decision of the museum [...]
Fri, 06-07-2013 16:53
Basically the plan is "ONLY" reassembly. As far as we know she is is reasonable mechanical shape. The big mechanical problem that stopped her (slack [...]
Fri, 06-07-2013 16:28
Nigel I read you guys got a one million dollar check donation!!! Will this be used to finish 1630 ,428, 5 and get started on the others next in line?
Fri, 06-07-2013 16:16
So does 1630 basically only need reassembly? With the boiler in particular. Does her tender or running gear need any work before she's ready for the [...]
Fri, 06-07-2013 12:00
Hello.. The voltage we are using and presumed the RR also used is 120 vac. The system is a little unique because the lite bulbs are each 60 volts. [...]