And in the wood shop area, as is our custom, we produced a lot of sawdust and chips. Production is at such a high level, the collection barrel needs to be emptied more than once every day the machines are running.
Victor Humphreys is our 'go to guy' for painting and he does a fine job. Here are the new cupola cab windows for Chicago Great Western X 38 getting the first coat of maroon.
Dave Rogan does careful work in fine tuning the mortise and tenon joints for the second CGW X 38 door. We make it a practice to completely assemble and dry fit the door before gluing, and on occasion, fine adjustments need to be made.
And at the end of the day it is worth it. The second door is in the glue press curing as Dave makes a final check. The first door is done to this stage and can be seen in the background.
John Faulhaber and Rich Witt are trimming a new roof board for the Lake Shore Electric 810. The new boards are being installed from the top down towards the tack molding.
John is on the belt sander now making the final fit fpr this piece. Nothing ever comes out exactly perfect when working on an eighty year old car body, so the last piece is a custom work of art.
And here is the car, outside in Barn 4. Three or four rows of roof boards are done, and the new tack molding has been installed. Wednesday morning it was about plus 7 F and these guys were on the scaffold first thing. At least they were out of the wind!
Henry Vincent has completed the new pieces for the repair on this door for Chicago Aurora & Elgin 36. He has moved forward and is sanding old paint off, and preparing the mating surfaces for new finish before final assembly.
Well, more properly, speaking OF tongues. A good sized crew worked again throughout the day on new roof boards for Michigan Electric 28. I think the goal is for something in excess of 1200 linear feet to be made. That is not a trivial effort. Here are the first boards off the shaper showing the new tongues.
Paul Cronin is acting as catcher getting the stock as it comes off the shaper, and Buzz Morisette is feeding the machine. Not the only two working this project, others helped, but were not in this image. Jeff Brady and Norm Krentel were outside in the barn, working on the top roof sheathing.
Progress was also made with the new Boston & Maine windows - beading, planing, and ripping.
Comments
Mon, 06-17-2013 09:50
Wish I could be there to help.
Fri, 06-14-2013 16:50
Matthew, Any special event is the decision of the museum Board. My personal opinion is that it is likely that there would be a special event to [...]
Thu, 06-13-2013 18:33
Hi, I have a question, if or when she is restored and back up and running this or next year. Will their be a special event set up for the return of [...]
Tue, 06-11-2013 22:36
The whistle 1630 wore for a while that you're thinking of was a Frisco 6 chime donated by a former member of the steam shop. It was on it a few times [...]
Tue, 06-11-2013 18:03
You are talking here about something well before my time !. I have not seen her with anything other than the whistle she now carries. If she [...]
Mon, 06-10-2013 16:17
i'm curious here. Will 1630 ever wear the ATSF 6 chime she had on for a while? Better defines her, I love the deep whistle she has now but the higher [...]
Sat, 06-08-2013 15:15
Many many many many many thanks for getting the Spaulding webcam working!!!!!
Fri, 06-07-2013 16:55
The donation was to the museum as a whole. How it is used and whether any comes to steam department projects will be the decision of the museum [...]
Fri, 06-07-2013 16:53
Basically the plan is "ONLY" reassembly. As far as we know she is is reasonable mechanical shape. The big mechanical problem that stopped her (slack [...]
Fri, 06-07-2013 16:28
Nigel I read you guys got a one million dollar check donation!!! Will this be used to finish 1630 ,428, 5 and get started on the others next in line?
Fri, 06-07-2013 16:16
So does 1630 basically only need reassembly? With the boiler in particular. Does her tender or running gear need any work before she's ready for the [...]
Fri, 06-07-2013 12:00
Hello.. The voltage we are using and presumed the RR also used is 120 vac. The system is a little unique because the lite bulbs are each 60 volts. [...]