There's always something to do. Outside work on the yards project has slowed to a crawl but the parts that came down in the fall are ready to go up in the spring. It's nice and warm inside the B&G Building, no wind eather. A good place to recondition parts for the yards and build up stock.
I fixed up the media blaster with a new air supply hose from the compressor. The 75 foot run was too much for the 3/8" air hose. Too much pressure loss. I doubled the size to 3/4" and that works Great! Now I can actually adjust the pressure at the blaster's regulator. It now makes quick work of rusty woodstrains. A new window and supply of window film means I could see what I'm blasting. When the weather is tolerable I work on accessible outside projects.
Work continues on moving equipment to the steel pole from the rotted wood pole by the pavilion. I set the pole extension and transferred the signal and phone cables. I finally got power into the second ART TRAIN car. That initiated a new project. Replacing the old transformers by the office which are now overloaded by the addition of the 2nd ART TRAIN car and additional lighting in the car shop. In order to facilitate that future transformer replacement without an extended power outage, I need to install a secondary tie between two transformer banks. This tie will also serve as an emergency backup in the event of a transformer failure involving the office or diner annex. I had planned such a tie for years but now it's installation is necessary.
Other winter work involves getting ready to do other projects. Like a new display sign near the admission booth. I want to get the platform lights on 50th ave station working this year. These will be D/C cluster lights operating off the 600v railroad traction power but with new wire. Circuits will be rewired to a safety switch on a pole outside. The old open blade 600volt fuse box will remain undisturbed as a display but will be disconnected and not functional for obvious safety reasons.
There are issues with the R33 rectifier which must be repaired when the weather warms. Spring maintenance must be done on the railroad, there are several broken insulator pins and dozens of catenary hangers to replace. Jole Ahrendt (car dept.) has been busy fabricating replacement catenary hangers. I understand these are ready waiting for a warmer day.
Comments
Sun, 05-19-2013 22:13
Hello again. I had an idea that was (somewhat rudely, mid-sentence) dismissed in talking to a museum volunteer a few years back, but here it goes [...]
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!