| BLOG | DIRECTIONS | SCHEDULE | STORE | |
Tuesday, March 2. 2010
Track Dept Weekend Report. Feb 27, 28 Posted by Adam Robillard
in Track Department at
06:00
Comments (0) Track Dept Weekend Report. Feb 27, 28
This weekend was all about track machines-
Saturday I was out along with Frank DeVries and our plan was to get our heavily used machines serviced and ready to go. We started early with a trip to Behr Recycling in Woodstock to cash in eight old machine batteries we've been collecting over time. Most places will give you a $5 or $7 credit toward a new battery but since we currently don't have a need for new batteries we brought ours in for cash. We picked up $39.30 for the batteries and that money was put into the EJ&E 529 caboose fund. When we got back we started by replacing the four large high pressure hydraulic oil filters on the 6000 tamper. It was a messy job and my legs and arms were soaked with hydraulic oil by the time we finished but got the job done. These don't have to be replaced very often but we've never replaced them since owning the tamper; they were certainly due for replacement. We also heated the engine room to thaw out the throttle cable which often freezes solid. After a trip to Napa for some parts and oil, Frank did some re-plumbing on one of the air tanks which was leaking. The next task was to get the Model 50 Burro crane over the the Pit on 41 Track and give it its annual service. After warming up the crane, Frank ran it over from Yard 11 to the pit and started with an engine oil/ filter change. This time Frank was the one draining the oil and ended up getting drenched. Say goodbye to that coat! We tackled our leaking transmission as well. While I added engine oil, Frank drained the transmission oil and made a new liquid gasket for the leaking filter plug. The car shop was kind enough to let us leave the crane overnight on the pit for the gasket to cure properly. We oiled the drive shafts, inspected the wiring and cleaned up a bit before calling it a day. ------------------ Sunday the gang was myself, Frank DeVries and Tom Hunter. We began on the pit by refilling the transmission oil in the Model 50 Burro to find that the new seal appears to be working without leaking. We attempted to start the crane without any luck. After a few attempts we put the battery charger on it and headed to Tk24. The big project for the day was to pull ALL of our machines from Tk24 to switch the heated portion of the diesel shop. We started by getting the 6000 tamper, the ballast regulator and the EJ&E 585 motorcar all fired up. Without diving into the details of the switch list, we were able to pull everything out of the barn and onto the Carline without much difficulty. In a rare move, the old SOO line brush cutter that was in the heated portion of Barn 2 was also pulled out for the first time in years. We will find it a new home soon but it will no longer be in the heated shop. After the big switch and getting everything put back inside, we took the Burro Crane back to Yard 11 and brought the 6000 tamper onto the pit and gave it its annual service. The three of us did an engine oil/ filter change, lube and once over while on the pit. Tom and Frank did some electrical work as well. We made quick work of it, got it back to Tk24, cleaned up and called it a day. The 6000 tamper and Model 50 Burro Crane are ready to earn their keep this spring. The first projects we intend to start will be tamping on the Carline and Mainline in April with the 6000 tamper. We will begin track inspection this coming weekend and dive into mainline repairs during March in anticipation for service in a month. Thanks to the Electric Car dept for use of the pit and everyone who helped out this weekend. We got A LOT done. Franks photos from the weekend are on his Member's Pages here: http://www.irm.org/gallery/album238 http://www.irm.org/gallery/album239 Thanks, Adam Robillard IRM Track Dept. Tuesday, February 2. 2010Track Dept Weekend Report
Toms report from Saturday and my report from Sunday-
Saturday- Yesterday Frank and I got there so that we could help with the Electric Car folks with the first moves into Barn 11 - as no one was about in the morning, we dug into the list of stuff to do in Barn 2 - starting with the starter of course. As I noted below - Frank dug out that one from the 585, we did the switch with the 580 and got the 585 running. We let it run a while to warm up and starter in on the 6000. We changed out the broken pin on the right work head, and on the good advice of Frank decided to change the left one too since I bought two new pins... good thing as that one was broken too, hanging on but less the a 1/4 inch...yikes... So it goes to show - inspect your machine as much as you can... Both are now new. After all that was done, Adam showed for the 2nd trick. We headed to Yard 11, to wake up the 50. It took a while with the normal trans oil and warm up, we had to thaw out the transmission air lines too - but it fired up fairly well for having sat for a month... In the end it was not needed - so that ended a good day (Seems the EJ&E folks installed the wrong starter in the 585 - one with too small teeth on its gear - that DID grind away some on the fly wheel, but after Frank removed the 585 starter and we went into the barn to see what was on the 580 (how cool to have spare motor cars huh?) and saw it was a lot bigger motor on the 580... sooo..switcho we did -) Tom Hunter -------------- Sunday- Tom and I made up the gang and chose to clean off the CNW flatcar of 'stuff' gathered from along the RoW with the Burro crane we serviced Saturday. Tom fired up the Model 50 in Yard 11 and I went to retrieve wreck knuckes and such. The CNW flat was buried in the middle of a string of cars on Station Tk 2 so we had to move a bunch of cars to get it out. I do believe the Model 50 moved more tonnage that day than ever before! We moved a very heavy six axle flat, eight axle flat and Rock Island coach uphill in one pull! With a full transmission and full throttle it crept the cars upto the main at a brisk 1-2MPH... It was amazing. After making the switch we headed to yard 14 to unload a slew of line poles we had picked up from Schmidt Siding and then went to the diamond at South Jct to unload three old signal foundations from the old 151/ 152 signals. Tom reported how heavy the things were to pick up. 6000lbs is not light. We finished the heavy lifts and ran the flat back to station 2 and put away all of the other cars. We tied up the crane and called it a day. I bought three sheets of 3/4" plywood for a little shelf project in Tk24. I hope to start that soon. On another note it, the diesel guys plan on switching the shop on Track 24... That means we'll have to clear out ALL of the track machines from the Barn. Included is the old brush cutter in the heated portion of the shop. If anyone is working on it, please let me know as it may be moved permanently out of the shop due to track space issues. Take Care, Adam Robillard IRM Track Dept Tuesday, November 17. 2009
Track Dept Weekend Report - November ... Posted by Adam Robillard
in Track Department at
18:38
Comments (0) Track Dept Weekend Report - November 14/15
Saturday's gang began with Greg Frech, JD Marzec and Adam Robillard.
We received 100tons of ballast this past week and it was time once
again to load ballast cars and continue working on surfacing yard 11
(outside of the barn) as well as the tail track lead at the Yard 13
diamond. Greg and JD were on the Model 50 Burro crane crew and sorted
material throughout the yard. We had lots of scrap, rails, timbers,
etc scattered all over the yard and they spent all morning loading the
gondola and stacking material. In the meantime,
Adam loaded our green CNW ballast car with the Model 30 Burro crane.
Joel Ahrendt received his first lesson on the Model 30 as well and now
has a good taste at what it takes to load a ballast car. Typically
each full car takes roughly a day (8hrs) to load with the clam shell
bucket.
By lunchtime, Adam had nearly 3/4 of the ballast car full and asked to use the diesel dept switch crew to help dump ballast. Jim West and Warren Lloyd as the crew of the ComEd 15 switched Yard 11 and dumped 1/2 of the car on the tail track lead. Jim West ran the engine while Warren, JD, Greg and Adam ran the doors. Finished with that Greg, JD and Adam got out the Amtrak regulator and regulated the freshly dumped ballast in prep for tamping. Dark took hold soon after and we called it a day. Sunday's gang was made up of Steve Lewkowycz, Jim West, Joel Ahrendt, Warren Lloyd and Adam Robillard. The day's priority - Tamp and Regulate. Steve L and Adam R started the day out by checking fluids and starting up the Amtrak 6000 tamper in Yard 11. We took it to the Yard 11 tail track and set up the machine. Steve L took to the controls for his first time and made the first pass with only a minor 'cord' problem which continued to short out and trip the circuit breaker.. A quick crop of the light buggy extension cord was in order but remedied quickly. After the first pass was through we got the Amtrak regulator out and plowed stone to prep for the next pass. By this time we were joined by Jim W and Warren L who helped finish the next few passes with the tamper. Jim ran the tamper for the rest of the evening and did a fine job as this was only his second time at the controls. We made three passes on the track now it no longer resembles a roller coaster. Warren ducked out about the time Joel A showed up to help out. The next steps were to tamp 11-4 and 11-2 tracks from the Barn to the switches. We split into two gangs: Steve and Joel ran the ballast regulator while Jim and Adam ran the tamper. We did our final passes on both tracks and the crew on the regulator had them both broomed and looking like mainline track by dark! The 6000 ran great with no mechanical problems all day long.... Looks like the hard work over the past few months is paying off. Thanks to all who helped this weekend, especially Joel Ahrendt, Jim West and Warren Lloyd visiting from the other departments, as we get ready to open up Barn 11! Adam Robillard IRM Track Dept lzeje657@msn.com Wednesday, November 11. 2009Midweek Track ReportWell it turns out Veteran's Day is an Amtrak holiday... know knew? Well the weather cooperated today so I head out with a list of one man jobs to accomplish. To my surprise, JD Marzec and Greg Frech both showed up willing to do track work! Turns out they had the day off as well. So with three people the job quickly turned to Yard 11. The job was to get 11-4 track ready for another pass with the tamper so the first task was to regulate the stone that was dropped a few weeks ago. After getting the regulator fired up, Greg and JD made a few quick passes with the plow and broom. After they finished the 6000 tamper and regulator were moved to Yard 10 to clear 11-4 track. We made our way to Track 24 to fire up the tie crane and motorcar/ powerpack combo. We had to replace a ~12ft stick of rail on 11-4 track to close a 3" gap in the curve. So Greg and JD both got a walkthrough on the machines and ran them over to yard 11 while I acted as the U-man on the ground. The three of us made quick work of removing the old rail and cutting/ installing the new rail. After the last spike was through we headed for lunch at Joe's. Monday, October 12. 2009Track Dept Updates Oct 12, 2009
SEPTEMBER 26-27, 2009
Last weekend was a big weekend in Yard 11. Our dept was joined by three volunteers from the Minnesota Transportation Museum, Andy Inserra, Phil Wellman and Eric Hopp in addition to our IRM gang Frank D, Tom H, Adam R and our most recent addition, Mike Weber. The task was to do as much work in Yard 11 as possible with two full days and a good group of guys ready to work. In previous weeks we have been actively loading ballast into our two C&NW ballast cars and dumping them on yard tracks as needed as well as repairing the 6000 tamper. Saturday we split into numerous gangs throughout the day while we ran our "production surfacing gang" in the Barn. While tracks were being tamped with the 6000 tamper, other crews were busy loading ballast cars with the Model 30 Burro crane, regulating stone on the yard tracks and dumping stone with the Model 50 Burro crane. At one point it was truly an impressive scene with three work gangs working on seperate tracks at once! The crew from Minnesota did a great job learning the machines and jumping into the jobs. (Some of them have backgrounds in track and signals and are also the MTM's track dept...) Saturday night we all worked well past dark which was possible due to the ceiling lights inside of the Barn. We called it quits for the night and made it to the Truck Stop for dinner a bit after midnight. Sunday most of us returned for another day of tamping and regulating in the Barn. Like all track machines a few problems came up with the 6000 tamper later in the day shutting down the operation. A few parts failed 'inside' of the machine and for anyone who knows the machine also knows how dirty it is to get under, in between and 'inside' of the it for any reason... We had a few spare parts which we reinstalled and helped us get through the evening but more parts are on order which will complete this round of repairs and get us rolling again. The work didn't stop there as another track was regulated and the west end of 11-4 track was lined with the assistance of Nick K in the Bobcat. By the end of the weekend we had finished tamping 11-4 track, nearly finished 11-3 and made the first lift on 11-2 track. Each track requires 3-5 lifts with the tamper for their entire lengths to get the track upto the proper height and alignment. Ballast was dumped on 11-3 and 11-4 tracks and both tracks regulated. It was a VERY successful weekend and proves how much we can accomplish when the machines work properly and most importantly when we have many hands helping out. Track work is not an easy activity to say the least... Thanks to the gang from Minnesota again, we really apprectiate your help! Adam Robillard lzeje657@msn.com -------------------- OCTOBER 3-4, 2009 This past weekend, Tom H, Frank D and Adam R were out Sunday to continue repairs on the tamper, load ballast and pick up material on the mainline. An urgent request was made to clean up some Track and Line Dept material near the interchange track for the unloading the the new Santa Fe loco in the coming weeks. Frank was the first one out this morning and fired up the Model 50 Burro crane. I arrived shortly after and we picked up the C&NW flatcar and headed West toward the interchange. There we met up with Tom H and John N and the four of us loaded a complete track diamond, misc rails and OTM and good number of old line poles and wooden planks which have all been in the weeds for well over a year. The Burro crane made quick work of the job and impressively lifted the 8000lb diamond onto the car with little trouble. We made our way back to Yard 11, tied down the train and went to lunch. After lunch and a quick stop to Napa, I split from Tom and Frank and went back to the interchange with the tie crane and flat carts to finish the clean up job. In the meantime Tom and Frank worked on the tamper in Yard 11. They made significant progress but there is still more work to be done on the tamper and a few bugs to work out during the week. Throughout the day Frank also spent time loading the next ballast car with the X-17. It turned out to be another late day for us all. I can't remember the last time we've gone home before dark but the Barn is important to us and we're committed to finishing the track portion as soon as possible. Next weekend we're planning to continue work in Barn 11. Help is needed to load and dump more ballast on the finished track, 11-4. There is a lot of hand work at the West end of all four tracks to finish raising and leveling the tracks where the tamper cannot reach. Shoot me an email or talk to any of the Track Dept volunteers if you'd like to come out and help us complete Barn 11.Adam Robillard lzeje657@msn.com ----------------------------- OCTOBER 10-11, 2009 Saturday's crew consisted of Frank D, Tom H, Steve L, Steve's friend Josh Gould, and Adam R. As in previous weeks the big project is finishing Yard 11. The day started early for Frank who was able to get the tamper temporarily fixed making it operable once again. With things looking positive we fired up the tamper and got to work... Thankfully Nick showed up shortly after and gave us a little pep talk. My favorite quote from the conversation- "Get as much done before the tamper breaks again, it's already past due for a break down..." Mind you we hadn't been tamping for more than 15 minutes at this point. More on that later... We all focused the next few hours tamping 11-2 track and 11-3 track. By 12:30 we had 2 track and 3 tracks completely raised and ready for stone. But as expected the tamper failed just as we were finishing 3 track. The pin which holds the entire workhead assembly to the hydraulic cylinder snapped, the workhead fell to the ground and busted the hydraulic cylinder and hoses.... Sigh. Well all hope wasn't lost and the next few hours were spent working on the current failure and replacing parts from last weekend's failures... Needless to say we got a lot done on the machine and we'll be up and running this weekend.I left early but the rest of the gang stayed late Saturday dumping another round of ballast on the finished tracks. The majority of the work inside of the barn is done. Three passes with the tamper on one track and the tamping will be done. We need to manually lift the last 20' on each of the yard tracks, finish ballasting (including loading one more car of stone), regulating, and we will be finished with the track portion of the project indoors. IF all goes well next weekend I can see us being out of the Barn within the next 2-3 weeks. Sunday was very low key in comparison. I was the only one out and spent a few hours sorting the recently arrived switch timbers near the connector track. Next month Volkmann, our track contractor, will be out replacing switch ties on a number of mainline and carline switches. Our obligation in the dept is to distribute all of the ties and pick up the old ties afterward. This cuts costs dramatically and helps speed up the process. All of the switch ties are laid out along side of the connector track and marked for length. With the tie crane we'll pick up the ties we need for each switch and lay them out along the tracks. This is another time consuming project but also very important in maintaining our railroad and keeping it safe to use. The cold weather is upon us so it's important to keep the block heaters in the machines plugged in at the end of the day. The Model 50 is plugged in at Yard 11. The tie crane is too far from the door at Tk24 to get a cord to right now, so we'll need to switch out and clean up the tie carts to make room. More photos from the Track Dept can be found in Frank DeVries' photo album here: http://www.irm.org/gallery/icemancne and my photo album here: http://www.irm.org/gallery/lzeje657 Adam Robillard Roadmaster - Track Wednesday, August 19. 2009Track Update - Yard 11Our task this past weekend was to
construct the new 11-4 track inside of the Barn in yard 11. We had a
really good group out Saturday to work taking time from their normal tasks to
help us out. The crew was the regular track gang, Frank D, Tom H, Steve L
and Adam R and we were joined by Jamie K, Pete P, Warren L from the diesel dept
and Erik M, a long distance volunteer from Nebraska. After lunch we regained our strength and finished up building the entire track to the west end of the Barn! Bob Olson and myself ran into the material yard for a quick trip to locate more joint bars while the Erik ran our hydraulic rail saw cropping the ends of the rails and getting the last short panel set. The next step before ballast was to finish up the Quality Control work and spiked up all of the joint ties with the air compressor suspended from the Burro crane and spiking gun. Steve L did a great job nipping the ties while Frank D and Jamie K preset the spikes. Adam R ran the spiking gun and Tom H kept the air compressor moving along in the Burro Crane. Once we cleaned up our mess from the construction it was time to do a rough alignment of the track to make surfacing easier later on. We hooked a chain to the Burro and at an angle and tugged on the track to drag it into place, 15’ from 11-3 track. With a motivated crew, we figured the next reasonable step would be to dump ballast on our new track. Jamie K and Pete P grabbed the USA 8537 to dump the ballast. An attempt to move the cars with the Model 50 burro proved to be too much on the tough grade into the barn. Adam R, Pete P, Tom H and Steve L ran the four ballast doors while Frank D and Jamie K ran the move. We dumped the entire track with a car and a half of stone in a matter of minutes. Our last task, due to the dwindling light, was to plow out the ballast with our new Amtrak Ballast regulator to prep for the tamper. This was the first time we’ve used this machine and I think we can all say it was an amazing success. A few minor tweaks and lack of use issues came up, but we did manage to run the machine down the entire track without any real problems. It will be a good machine once we get it through ‘our shop.’
With this said, 11-4 track is completely built! This Saturday we will begin the process of getting the Amtrak Jackson 6000 tamper adjusted, lubed and running and hopefully continue to reload our ballast cars. Until the electrical portions of the building are complete, we will work on raising 11-4 track inside the barn and tamping the approaches to the doors outside of the barn. This will be a process of raising, dumping stone, regulating, raising…and so on. We need to raise the track up nearly a foot in some places and that will take time. Congrats to everyone so far who’s helped on this project. The help from within the museum really makes things easier for everyone working and shows the commitment they have toward the museum. To find more pics on the Yard 11 project Frank D regularly updates his page here: http://www.irm.org/gallery/album182 Check ‘em out. Thanks,
Adam Robillard IRM Roadmaster Saturday, August 8. 2009Barn 11 news
Today we took a large step toward the completion of Barn 11. The gang today was Frank, Trackbolt, Steve and myself. The goal today was to build off the newly constructed switch and extend the track into the Barn and begin setting track panels inside the building on the new 11-4 track.
Frank and Trackbolt (Frank's daughter) were the first ones out and had the yard sorted and tools prepped for the days work. When I showed up Frank and I hooked up the first short track panel. We made a few cuts, drilled a few holes and installed a few ties. By lunch the first panel was in place! After lunch Steve joined us and we started by installing the first long track panel which extends through the door sills. The Model 50 Burro crane made quick work of the actual install process and the rest of the sweat was getting everything in line and bolted together. Once the panel through the door was in place we brought in the next two panels, laid them in place and bolted them up as well. Nick joined us with the bobcat and backhoe and helped place some stone on the new track to make it safe to travel across. Dave D. helped us engineer the tracks through the door sill and find our eventual rail height. There is a lot of QC work to be done on this new stretch of track but nothing our own track dept isn't capable of handling. We will need to finish spiking up a couple of ties, tamp the barn approaches and insert ties under the joints between panels. From here on out the rest of the track will be built 'relatively easily' with the remaining track panels and Model 50 Burro crane. We have the air compressor and hydraulic power tools to assist us in the construction. The entire process works best with 3-4 people. Anyone is free to join in during this process. We always appreciate the help!Next Saturday we will again spend the day working on Barn 11 out of the Thomas spotlight. We will attempt to complete the work on the new portion and place more track panels. Our two ballast cars have been loaded by our Model 30 Burro crane and bucket and are ready to be dumped on the track soon. Frank was the "official" photographer for the day and he'll be posting pics in his Member's Photo page on the IRM site soon. Thanks, Adam Robillard, Roadmaster |
Blog AdministrationFind us on FacebookCategory TreeCalendarQuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!
Sun, 05-05-2013 18:53
Ah yes, I have made such Jibs myself. If it were me, I would add in each corner an angled piece from the base to the Jib to act as sway bracing. [...]