| BLOG | DIRECTIONS | SCHEDULE | STORE | |
Sunday, March 31. 2013
Steam Department Update 03-30-2013 Posted by Nigel Bennett
in Steam Department at
11:12
Comments (5) Steam Department Update 03-30-2013The number of people in the shop was a bit reduced at Easter weekend and it was unfortunately one of those days when a lot of hard work did not achieve as much as was hoped. On 1630: · The main focus was on loading the super heater flues. Unfortunately this proved a great deal more tricky than had been hoped. When the tubes were safe ended each was carefully measured with the objective that it was matched to a specific location with a certain amount of excess length to be ground off after fitting. When the first few were fitted it became clear that there is a significant variation from the intended lengths with some shorter and some longer. Clearly, where there is excess length it can be cut off. But if we have any that are too short to be fitted we would need to get more welding done. The key objective became to ensure that the shorter ones can all be used without the need to get a welder in again to lengthen any. So, instead of simply slotting each tube into its numbered hole, it became an exercise in loading and unloading tubes multiple times to ensure that the shortest tube that provides the required projection at each end is used in each hole. As each tube is 17 feet long and 5 1/2 inch in diameter, they are heavy beasts to fit and refit so it was a hard day's work made worse by the fact that it was unexpected. The first part is easy. The fork lift raises the tube to height and in this shot, Phil and Sean slide the tube into the hole in the tube sheet.
The next bit is more tricky. Once the tube is off the forks it becomes a giant lever pivoted in the tube sheet. Here Dave is assisting by controlling the end of the tube to ensure that is slides smoothly thru the hole and can be located in the rear sheet without dislodging the ferrule at that end.
Once it is in place there is a careful process of gauging the projection at each end to ensure we have the required 1/4 inch minimum. Given the length issue, a number were then removed and the process repeated to ensure that the shortest suitable tube was used in each hole. Anyway, by end of day we had all 8 on the engineer's side in place and the first on the fireman's side and have managed to place the shortest tubes.. · With Vince's assistance, Mike finished the tapping for the patch screw on the firebox corner. When I left sparks were flying from inside the firebox as Mike did the final grinding of surfaces inside the firebox ahead of riveting. We are waiting on the return of the air bucker from overhaul and can then set up for the riveting.
· Ed and Richard substantially completed the pipe runs along the boiler sides and started work on the cab pipe work. · During the last couple of weeks Kevin has done more needle chipping to prepare for painting both on 1630 and on the planer. Elsewhere: · Bob continued work on wiring the control system for the planer; and · Dennis finished building up the grease keep for the truck axle box on 428. So next week we target fitting of the remaining flues and then we can set up to roll them into place. Nigel Sunday, March 24. 2013
Steam Department Update 03-23-2013 Posted by Nigel Bennett
in Steam Department at
10:18
Comments (7) Steam Department Update 03-23-2013Not too much visible progress in the steam shop this weekend but actually a good deal that is not very apparent. On 1630 · The first two super heater flues are now loaded. This involved identifying and learning how best to use a whole array of new equipment.
o Jason successfully expanded ferrules into all 16 holes in the rear tube sheet last Sunday. These were chosen from two alternate thicknesses to provide a close fit on the flue as it is inserted from the front of the boiler. o For the large flues the loading process is, of necessity, more complex. Ferrules will be fitted in the front sheet only where the hole is enlarged beyond 5 1/2 inches in diameter. From measurements made yesterday this will be 10 of the 16 flues. o Fitting the front ferrule is very much part of the loading process. Given the size and weight of a 5 1/2 inch tube 17 feet in length, there is no possibility of expanding the ferrule into the sheet in a way that would allow the flue to passed thru the ferrule without displacing it. So the flue must be passed thru the front sheet, into the back sheet and pushed several inches beyond its final position into the boiler, clear of the front tube sheet. The ferrule can then be fitted and the flue drawn back into the front sheet. So fitting the front ferrules is an integral part of loading the flues. o Initial progress was slow as the ferrules must be expanded to the absolute limit of our largest rollers, which meant that they were not very secure. During the day we made a spacing ring that overcomes the problem so, based upon experience with the two now in place, we believe the rest should be much quicker. · Jane continued priming the inside of the cladding sheets so that these will all be ready to install over the lagging. She has now completed the batch we have in the shop so we will need to store these again and get another batch for cleaning and painting. The cladding will not look good at this stage as the outer face will not be prepared and painted until it is in place. However, priming the inside where it is subject to heat and damp from the lagging, is essential to preserve the sheet on the locomotive. · Eric and his Dad worked from pictures of the backhead, that we took before stripping, to locate all the valves and controls, lay them out in the machine shop and start work on servicing, cleaning and painting them. · Dennis weld filled the hole for the one patch screw that must be replaced. Mike and Tom then produced a guide and started to drill out the hole for threading. · Dennis weld repaired the two super heater elements that failed under pressure test last Fall. (Actually Dennis did this a couple of weeks ago and Nigel did not notice !!). Anyway, these are now ready for hydro testing once we get above freezing outside.
On 428 · The first of the two guides for machining the shoes and wedges was competed and Tom is starting to finish the ends of the cast iron shows on the shaper. The second, which will enable the machining of the angle on the wedges is approaching completion. · Dennis was brazing the grease cellars for the truck axle boxes. In other areas: · We moved the turret covers for #265 up on to the top of the locomotive. Time is moving on and the museum opens to visitors soon. We would be deeply unpopular with Buildings and Grounds if large lumps of metal are in the walkways of barn #9 as opening day approaches ! · We had hoped to get some tubes for the Shay out of the boxcar but investigation proved that this can only be done with fork lift access to the car as other heavy material must be moved to get at the tubes. (For efficiency we want to swage the Shay tubes when we do a few extra required for 1630. It takes several hours to set up and test the swager so we want to do a full batch rather than 5 tubes when we do so). However, we will now need assistance to shunt the KCS tender and re-spot the boxcars before we can do this. · Glenn and Richard worked on the safety covers for the new compressor. · Glenn assisted the track department in trying to start their crane. Unfortunately this proved "non trivial" as it seems the fuel lines are blocked. So it did not start today. · Jeff was finalizing the air supply in the new shop. - Yes this is Jeff. The extent of the hair cut led many to question if we had a new volunteer this weekend !. Most of the new outlets are now in place. These are all being structured with a drain on each down pipe to avoid water carry over. · Bob carried on from last week, positioning the planer. It is now not only in position but pretty much level. So a good day's progress and hopefully we are now set up to move forward quickly next weekend. Nigel Sunday, March 17. 2013Steam Department Update 3-16-2013After a hard day at the shop it is always good to be able to say that we achieved what we set out to do. Having a major target in sight certainly encourages you to keep going! On 1630: All the small tubes below the super heaters are now completely installed to the point at which we will first test them. (As mentioned previously, they should be water tight after expanding and flaring. So we aim to do an initial hydro test to identify any that need to be tightened before we roll over (bead) the ends of those that need to be so treated). · A number of us took turns to expand the firebox tube ends with the air hammer. The technique developed last week worked well. Brian rolled any tubes that showed signs of moving during expansion a little more to ensure they were tight. He has become our expert with the tube roller, having expanded almost all the ends into the front tube sheet. The expansion is a tough job. It takes a lot of effort to control the large air hammer and ensure that a smooth flare is produced. All this must be done while squeezed in above the arch tubes where the heat builds up nicely. However, we found that you could do 6 to 8 before running out of steam. As you weaken, you are able to apply less force to the hammer and the flaring becomes less effective. So the time to stop is pretty clear!!. Anyway, by constantly switching operator, we achieved the objective and flared more than 130 tubes in the day. Here you see Phil and Brian at the end of the job. In this case Phil operates the hammer while Brian watches the tube end closely for any sign of movement. This is critical as the guy on the hammer cannot easily see if the tube starts to move;
Meanwhile Mike and Ralph worked on the holes thru which the patch will be riveted to the mud ring. The preparation is everything. The hot rivet is hammered into its hole in maybe 25 seconds. However the shape it will take is determined by forming the hole and the design specifies that the rivets are not all the same. Some have conical heads with a small countersink into the sheet, while others are countersunk almost flush. Here Mike is cutting the countersink into which the rivet will be formed.
So, as is the way with this work, we now move on from techniques with which we have become familiar to new ones. The next step on the tubing is to fit the 16 large super heater flues (and the remaining 9 small tubes that lie between them). While the general principles are the same, the tools are distinctly different. You certainly cannot use an expander on a tube this size. Both ends and the ferrules at the firebox end will need to be rolled into place and these rollers are on a whole different scale from those we have been using. On 428: · Dennis continued with building up the truck axles boxes. The focus this week was on building up the ledges on which the grease cellar rests to provide lubrication to the journal from below; · While Dave and Phil continued building the machining guide to mount the axle box wedges in the shaper. Elsehwere in the shop: · A big visible step was made on the wheel lathe. The large gear, that was cracked and has been repaired, was finally fitted into place along with the clutch mechanism. The mechanism was broken, either when the lathe was acquired or in transit, and has been rebuilt with some missing and broken parts reconstructed from drawings. The gear is driven by an electric motor (behind the gear itself) and free wheels on the shaft unless the clutch is engaged (from a lever at the operator's station. The control linkage was also reinstalled and can be seen running across the end of the lathe to the clutch mechanism. Much to the relief of all involved, this now operates correctly when the control lever is moved!. · Stu, Bob and Eric positioned the planer. This may not look much but is a big step in activating this machine. This a very substantial weight that has, to this point, been resting on rollers. It has now to be finally positioned and leveled after which the rebuilt hydraulics can be reconnected. During the afternoon and evening the machine was positioned. Then the leveling screws were all cleaned up and located on steel plates. The machine was the raised off the rollers and slowly lowered so that it sits only on the leveling screws. Next it will need to be accurately leveled (it currently demonstrates that the floor is not accurately level!) and locked into place. Here you can see the early stages as Stu screws down one of the leveling screws to lift the main body of the planer and release the rollers that are still seen projecting from under the machine So next week we can start the next phase of the tubing. Nigel Sunday, March 10. 2013Travels to UK steam railwaysA little off the normal topic. During my trip to the UK I managed to spring a few hours away from the office to visit a couple of preserved steam railways. So attached are a few notes and photographs from these visits. On the Saturday I visited the Severn Valley Railway near Birmingham. This line is about 15 miles long running thru beautiful scenery along the river Severn. The train and its locomotive certainly provided pause for thought. I have often looked with amusement at the Thomas locomotive dwarfed by the train of heavyweights that it is "pulling" out of the yard. However 1501, an 0-6-0 pannier tank of Great Western heritage was here preparing to take its 7 car train over the hilly 15 mile line, which it was well able to do. In retrospect, these locomotives used to take the stock for express trains from Paddington terminus to and from the yards so were regularly moving 450 ton trains so this was no great load. Last week I visited the Mid Hants Railway at Ropley in Hampshire. I follow the blog of the Wednesday volunteer gang there and was pleased to meet them. They made me very welcome and showed me around the workshop and yard. Most impressive what can be achieved when you have the operation to support some full time staff with volunteer support. Mid week the only locomotive in steam was the visiting T9 4-4-0, which was working a photographic charter. A range of locomotives were in the yard serviceable. In the foreground are 4-6-0 #850 Lord Nelson and schools class 4-4-0 #925 Cheltenham while in the background is 34007 Wadebridge, a Bulleid light Pacific. Another good looking locomotive was this Stanier "Black 5" 4-6-0 #45379. Now two years in service, Dave tells me she was rebuilt on site from scrap yard condition. Another locomotive is in course of rebuild from scrap yard condition while others are undergoing periodic general overhaul. If we think the 15 year boiler requirement is bad, in the UK it is only 10 years between required boiler strip downs !. The difference between US and UK locomotive construction and therefore overhaul technique is very obvious. UK locomotive fireboxes usually fit between the fabricated frames so no major boiler overhaul can be carried out without removing the boiler from the frames. So it is common to have a separate boiler shop as they do at Ropley. Here a number of boilers are in various stages of overhaul. In the background you can see a boiler rotated thru 180 degrees allowing ready access to the base of the firebox and mud ring. If you can do that, riveting the mud ring is less of a challenge than we face with #1630 ! Attached to the main shop they have a nicely laid out machine room and they even have a planer. One big difference is that theirs works !!. Hopefully ours will soon. Many thanks to Dave, Colin and the Wednesday gang for your hospitality, Nigel Sunday, March 10. 2013
Steam Department Update 03-09-2013 Posted by Nigel Bennett
in Steam Department at
12:45
Comments (6) Steam Department Update 03-09-2013Thanks to Roger for the update in my absence last week. Having arrived back from the UK Friday, the jet lag made Saturday at the steam shop harder than usual for me !. However the team made good progress in a number of areas despite my preoccupation with what time of the day or night it was. On 1630: · Another milestone in fitting the small tubes. Brian finished rolling the front ends into the smokebox tubes sheet. In the view below you can see all the tubes now fitted and the 16 vacant holes into which we will start fitting the super heater flues; · After grinding most of the firebox ends to the final length for beading, we made a good start on flaring the ends in the firebox. We have to watch carefully to ensure that there is no movement as the tube end is flared and expand the front end a little more if there is any tendency to move but, having worked that out, progress is quite rapid; Here you can see the difference between those higher up, that are now flared, and the ones at the bottom still to be done. The comparison between adjacent tubes E6 and D2 provides a good example. Once this is complete, we can move on to fit the 16 super heater flues and the 9 small tubes that fit between them. · Last week Dennis finished welding the patch into place. A clear demonstration of my limited knowledge of the finer details of welding. It looked pretty complete to me two weeks ago but a further finishing pass and tidying up around some of the rivet holes was still required last week. · The holes have now been reamed for riveting and focus is now on cleaning and servicing the air tools that will be used for forming the rivets. The riveting will be a considerable job as these are substantially the largest rivets we have driven in the shop in many years. · Dave and Phil worked on cleaning and servicing the various control valves from the cab; · Ed continued with the pipe work, which is now getting close to completion There was quite a lot of activity on 428 focused on the leading truck and axle boxes; · Having finished the welding on 1630, Dennis moved on to building up the truck axle boxes. Once built up these will need to be machined and the bearings fitted; · Dave and Phil worked on producing a guide to mount the axle box wedges in the shaper. The wedges must be machined to provide an accurate and consistent angle between the faces. One part of the guide is this tapered block. Here it is being drilled in preparation for mounting on the plate below. The tapered block will be attached to this plate so that the wedge can be locked in position with the angled face on the block. The outer face, against which the axle box will bear, will then be positioned so that is can be planed flat to provide the required angle versus the face within the channel (which bears against the frame). · Mike was working on another mount to hold the shoes in position for mounting on the shaper. In the shop in general, there was a big step forward in the project, funded by the Benefit, to provide piped air supply to the new shop (South end). Jerry had put in several days work during the week and yesterday he and Jeff completed the major parts of the system. After blowing out the debris, valves were fitted on several of the outlets and the system tested for leaks. The system proved air tight and, when I left, Dennis was, for the first time ever !!, working in the fabrication area without 100 feet of hose stretching back into the main shop. This is a substantial improvement as long runs of hose and substantial distance from the operator to the shut off valve have been a safety concern. The next step will be to finish the connection thru the South wall of the shop. This will serve the dual function of providing air for work in the wheel drop area as well as allowing the Sullair to be connected to provide additional capacity without long hose runs. The final step will be to connect in the large compressor. A good day's progress. Hopefully next week I can be there in mind as well as body !! Nigel Sunday, February 24. 2013
Steam Department Update 02-23-2013 Posted by Nigel Bennett
in Steam Department at
09:27
Comments (10) Steam Department Update 02-23-2013It was a day of great progress and one very significant milestone in the steam shop yesterday. The activity was largely on 1630: · Fitting of the small tubes progressed very well using the methods established last week, with teams working both ends at the same time. o Collin and Eric ground the projecting ends in the firebox and all of these are now ready to flare once they are sealed into the front sheet. As noted below, work on tubes in the firebox ceased for very good reasons in the afternoon; o Phil cut replacements for the two tubes that had hit problems and these were fitted and expanded. So all the small tubes, other than the few that are in between the super heater flues and must be fitted as part of installing the flues, are now in place; o Most of the ends that are to be beaded in the smokebox were also ground to length. At times Brian and Eric were working simultaneously on this with an impressive rate of progress. Just a few on the fireman's side remain to be ground to length. o Brian is rapidly becoming our expert on the tube roller. Once the grinding of the engineer's side was complete he started again with the tube roller and worked steadily to the point that we are now substantially more than 50% complete in rolling tubes in the smokebox. Everything on the engineer's side and much of the lower area is now done. · With installation of the small tubes nearing completion, Phil made good the paint (actually a specialized boiler treatment) on the 16 super heater flues to ensure that these are ready for installation. · Phil also spent a couple of hours on the sand blast cabinet in the car shop cleaning up some of the rivets needed for the patch. ........... which brings us to the major landmark of the week; · Dennis returned after a couple of weeks absence, due to illness in the family, and work restarted in earnest on the firebox patch. The tube fitting team moved out to allow full access to fit the patch. o The patch was bolted into place, the last two rivet holes were drilled and bolts fitted thru them. o After more cleaning, degreasing and tightening, the patch was finally secured in place and Dennis was preparing to weld when I left for the Soiree. o I later received pictures from Phil. By the end of day the patch was fully welded into the inner firebox sheet !!. o This is a huge step forward in correcting the problem that caused the locomotive to be pulled from service. It mean that we now have one more really tricky job to do before the repair is complete. All the bolts currently holding the patch must be replaced by rivets, which are 7/8 diameter and about 6 inches long. This will be a "fun" exercise but, once this is done, we will be close to the point where this part of the boiler is ready for hydro testing. In other areas: · Dennis completed welding the gear for the back head mechanism on the wheel lathe. Once the holes are drilled out and bolts fitted we should be able to assemble this part of the lathe and test it. · Bob continued work on the planer; · Dave machined new parts for the spring hangers on 428; and · Jeff was able to install the first sections of the new compressed air supply to the South shop. So, overall a very significant day for the steam shop. No update next week as I am going to the UK on business. However, a lot is now in progress so I hope that there will be a lot more to report in two weeks time. I am hoping that there may be the opportunity to see some steam activity in the UK while I am there. Nigel Sunday, February 17. 2013
Steam Department Update 02-16-2013 Posted by Nigel Bennett
in Steam Department at
12:33
Comments (5) Steam Department Update 02-16-2013It was a productive day at the steam shop although the weather was rather unkind, given our priorities. On 1630 the whole focus was upon continuing the fitting of fire tubes. As noted last week, our first priority was on trying to make the smaller air motor work with sufficient power to drive the tube rollers and so avoid trying to handle to the large motor in confined spaces. Moving the Sullair to the North end and rigging a holding reservoir to assure minimal pressure drop as the motor works should have been simple. It took Phil and me rather longer with a few challenges such as melting the wheels out of huge blocks of ice that had frozen it to the ground !. However, Glenn's good work over the summer paid off. The compressor starts well even at 15 degrees. The effort was a success. The smaller air motor with this enhanced air supply will successfully drive both the straight and flaring tube rollers. This unimpressive looking reservoir, close to the locomotive, proves invaluable in maintaining pressure as the tube is rolled. The results were impressive. We were able to both largely complete expanding the tubes in the firebox and reach about 25% completion of rolling at the smokebox end.
We now have just two tubes in the main area to refit. We decided to expand all tubes before addressing the ones where the ferrule "popped" during expansion. Only one did so this week. So we have that and the one from last week to refit before we have all fitted (aside from those between the super heater flues). Rolling the tube ends is now a rapid process but is driven by preparation for the next step, which is flaring those tubes that are to be beaded after the first hydro test. These need to be fairly accurate to 1/4 inch projection at each end and the flaring is more effective if the length is adjusted before this is done. So, next week, a number of tubes that have excess length will need to be cut back to 1/4 inch with the angle grinder before flaring. This was expected. The tube sheets are not flat so each tube length is unique and must not provide less than the required projection, so you cannot hope to get each tube correct to 1/16th as they are fitted. Here you can see some of the tubes (for example the two just left of the lowest super heater flue) that project further and will need to be trimmed before flaring. Hopefully in the coming weeks we can get two teams working. Once the smokebox end of a tube is rolled, the firebox end can be flared. So it should be possible to have teams working in both firebox and smokebox at the same time. The developing number of tubes with blue paint marks is an indication of substantial progress In other areas: · The move of the McCabe was completed. This location will allow it to be used without further movement but keeps it out of the way. · Jeff managed to get the scissor lift moved to the shop despite the icy conditions. This will allow work to start next week on installing the new air system into the South shop. A demonstration ride on the lift provided a rare opportunity for a look at work in the shop from above. Looking the length of the shop, Jerry is relocating material to make way for the McCabe and, at the far end, work continues rolling tubes into 1630. Looking toward the West wall, the team is working on the shaper. · Stu and Mike worked on reassembly of the planer. Sorting out how the levers should link to the hydraulic control block appears to be a challenge judging by Stu's expression! So, overall another week of good progress. Nigel |
Blog AdministrationFind us on FacebookCategory TreeCalendarQuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!
Sun, 05-05-2013 18:53
Ah yes, I have made such Jibs myself. If it were me, I would add in each corner an angled piece from the base to the Jib to act as sway bracing. [...]