Monday, April 13. 2020
The John Mcloughlin Mens Bathroom ... Posted by Roger Kramer
in Great Northern John McLoughlin at
11:00
Comments (0) The John Mcloughlin Mens Bathroom Gets a MakeoverContinuing the restoration news on the John McLoughlin is the repainting of the Men's bathroom. Mark Hoffmann started by abrading two walls in late 2018. They were primed to preserve the surface from rusting but we never top coated them. 2019 brought an increase in activity in the entire sleeper. That is when the work in the men's bathroom resumed. You will see, in these pictures, our renewed efforts. Now we have started the hardest job. Working on the ceiling and using a sander and electric wire wheel to remove the old paint. Thats Tim Fennell inspecting Sandis fine work. Not shown in any of these pictures is the actual painting of the ceiling. As we found out in the Mt Harvard, working over your head on the ceiling is no easy task. The ceiling did get painted! Many thanks to Mark, Andrew, Tim, Bob, our volunteers. Here we just finished painting the last two walls. A corner sink gets reinstalled underneath the mirror. With much of the work completed we moved on to the stripping the old paint from the steam and water pipes below the sinks. They are now also painted. That almost finishes the job. Removing the clutter will make it even better! After reinstalling all of the wall light fixtures, brass shelves and two sinks we moved on to the more difficult job! The team was to begin the most labor intensive work yet, the repainting of all four sections. Removing old paint from ceilings and walls was going to be a major, major job! We first had to remove the four seat cushions that made up each Pullman seat. No easy task. The seat cushion themselves are very heavy. Made up of metal coil springs, straps and wood, each weighted about 40 pounds. Yes, That's one reason why these sleepers were called heavyweights. Everything about these Pullman sleepers is super heavy. They were made to last a long time. My back can attest to that. Anyway, the next blog on the John Mcloughlin will focus on our repaint of the four sections. Donations to continue this project can be sent to: https://www.irm.org/donations/category/passenger-car-department/ Thanks, Roger. Sunday, April 5. 2020Repainting CB&Q RPO 1923A job that was long on the wish list of coach department projects was finally completed June, 2019. Thanks to the energy and determination of Nick Dey, who spearheaded the project, our RPO again is in beautiful shape and should be kept that way for many years. Nick started the project in mid August, 2018. Working in barn 3 by himself his goal was to repainted the 1923 for the Museum Showcase Weekend but because of the lack of volunteers that date was missed. In early September saw the RPO moved into barn 14 and the work there was continued. With more volunteers helping in the Fall, 2018, and Spring of 2019, the 1923 finally was repainted and re-lettered and placed back in service for RPO days in June of 2019. Unfortunately, the team just ran out of time to complete the job in the Fall of 2018. The next year was sure to bring a renewed emphasis to complete the job. In the spring of 2019 Gregg Wolfersheim entered the picture and thus completed the project. The goal was to demonstrate how the railroads use Railroad Post Offices in bygone service years. We met that goal when the freshly painted car was used again on RPO Days 2019! I didn't take any pictures of it in operation last year but I sure heard many favorable comments from members and visitors alike. Thanks to Nick Dey, Gregg Wolfersheim and the many volunteers who spent countless hours working on the CB&Q 1923. Again, it takes a team effort. If you wish to see more painting projects like this in the passenger coach dept PLEASE contribute to https://www.irm.org/donations/category/passenger-car-department/ Thanks, Roger. Thursday, April 2. 2020
Painting the Union Pacific Rotary ... Posted by James Kolanowski
in Steam Department at
11:30
Comments (2) Painting the Union Pacific Rotary SnowplowHere are some of the behind the scenes photos during the priming and painting of the UP rotary snowplow after it had been sand blasted. The main rotary unit was painted in barn 14 as it was the only building tall enough for it to fit in to. The tender was painted in the Diesel Shop as it would be winter by the time we were ready to start working on it. Quite some time ago I had bought a quart sample of the the PPG paint in the color that we thought was right. It wasn't until September 15th when we sprayed a cover to see how it would look. Everyone appeared pretty happy, so we bought the rest in bulk. On September 23rd, we started priming the rotary unit. It was done in 5 sections. We started with priming and painting the roof, then the sides one at a time, priming and painting the round rotary section minus the red, and lastly spraying the red. The roof was the most difficult section to paint. First, this thing is tall. There was only inches of clearance between the hatch and walk treads over the cab and the bottom of the trusses in the building. Then there was so much equipment on the roof... valves and vents and hatches and ladders and brackets, it never ended. It started with one coat of PPG Corrosion Resistant Epoxy primer and was best to be followed up within 24 hours with the first topcoat of PPG AUE-370 paint. The paint could have its second coat not more than 7 days later. The rood was finished on the 26th of September. The masking was done on October 3rd. Since barn 14 is a storage building, there is no equipment or source of compressed air. Two portable air compressors were just enough to keep up with the production HVLP spray gun I like to use. One of the compressors died, so I was quick to grab the nearest locomotive, which was 1605, so keep the project going. The larger sullair is far to wet on its air output. 1605 right off the main reservoir MU was perfect and very dry. The sides were started on October 8th and finished on the 9th. Some primer was done on the front section on the 9th, with the leftover mixed for the sides. The remainder was primed on October 18th and the outside that was aluminum color was painted the same evening. By this time the temperatures were getting a little cool, so all the steel was preheated with the propane heaters the steam guys dropped off. The minimum temp was 50 degrees to spray, we brought it up more than that so it was dry some before getting below 50. On October 27th, Buzz started applying the stencils for the lettering and numbers, and on the 28th, Gregg and Blake masked all the areas around the stencils. I sprayed a couple coats of black and we stuck around long enough to remove all the stencils while the paint was still a little tacky. The right side of the rotary still needs all the lettering applied. Buzz ran out of time applying them, and then ran out of weather. This will be completed later this spring when the weather is consistently warm again. The last step was to paint the blades and chute red. That was done the next night on October 29th. Everything was heated up again and two coats done that evening. It had to get done as the forecast was calling for cold temperature later in the week and this was going to be the last chance for any work like this. Aside from lettering on the right side, and painting the trucks black, the main rotary unit is done. The tender was sand blasted and then moved into the heated Diesel Shop on November 5th. It wouldn't be worked on until January 2020 as we were all focused on getting the train ready for the Happy Holiday Railway Christmas event. The roof of the tender was primed and painted January 4th and 5th. Then the painter went on vacation for three weeks. On January 31st, the right side was primed and painted over the next two days. The left side, front and rear were primed and painted starting on February 8th and were completed on 9th. The week after, Kym, Gregg, and a number of others wire wheeled the trucks and completed all the prep on those so they could be primed and painted. On the 15th, Roger and I applied all the stencils for the lettering and we all masked off all the areas around so the black could be sprayed over the lettering. This was completed on the 16th and 17th, with all the masking being removed the same day. The tender was moved out of the Diesel Shop on the 22nd and moved back to barn 14 with the main rotary unit. All that remains is the roof walk platforms, a bunch of things that connect the tender to the main unit, safety chains and such. All of which will be done as time permits through the remainder of the winter and spring. There are many more photos during the painting process. You are welcome to view a slideshow of them all by following this link in our photo gallery. The slide show will advance automatically at 3 seconds per photo and you can change some of the available options. Enjoy! |
Blog AdministrationCategory TreeCalendar
QuicksearchSyndicate This Blog |
|||||||||||||||||||||||||||||||||||||||||||||||||
Powered by s9y.
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...