Thursday, April 28. 2016Turntable Update April 28th 2016
It has been a couple of weeks of good progress but everything taking that little bit longer than we might have hoped.
We waited a full week before UP could deliver the flatcar to the site for loading. Once that arrived, there was a surge of activity.
Securing plates were welded to the flatcar and then, within 24 hours, the turntable deck and all remaining parts were removed from the pit and loaded last Thursday. The pictures show what was involved. The move was done by Hulcher using two of their side lifters, which was a very efficient way of doing this job as compared to crane lifting
The large central bearing was secured to the table and lifted with the main beam to avoid a separate crane lift.
The trucks, center bearing and all remaining wiring, rails etc. were loaded on a flatbed truck and were safely unloaded and stored at Union by Monday of this week.
At Burnham, with the table now on the flatcar, work progressed in securing this to ensure its safety during the move. This involved the attachment of substantial steel cables, attached to mounting points welded to the flatcar. The arrangement and implementation of the attachment must all be reviewed and approved by the specialist group in UP responsible for these large loads.
After a couple of iterations involving the addition of some additional reinforcing plates to strengthen the mounting points on the flatcar, we received confirmation today that table is now satisfactorily secured.
We now await the switching of the idler cars to be connected at each end of the flatcar to protect the overhanging ends. Once these are coupled, the couplings between these are the flatcar must be disabled (the load consists of all 3 cars so the couplings must be disabled to prevent any possibility of accidental separation enroute).
So, after 75 years, the table is just about ready to leave Burnham and make its way to it new home at Union.
Nigel
Sunday, April 10. 2016Turntable update April 10th, 2016
After a week of planning, great progress was made on the turntable in the last ten days. This is critical as site clearing will start this month and we must have the table out before this happens.
JD and Phil travelled to Denver in a truck loaded with tools and equipment and have been working with Dennis and track contractors based locally.
The stages of the removal are:
1. Remove and ship the rails, deck, railings, circle rail and everything else that can be taken from the top of the main bridge beam;
2. Lift the main bridge beam from the pit and lay it on the railroad flat car that will carry it to Union;
3. Take the trucks and center bearing, along with the remaining ring rails that lie under the beam and load these for transport to Union.
A surge of activity early last week saw everything on top of the bridge beam removed, stacked and then loaded onto 3 flatbed trailers. By Thursday, all 3 were unloaded at Union. Many thanks to Dave and Carl for their efforts in unloading. Each trailer was unloaded in 45 minutes, which was an indication both of their efforts and the good work of the team in Denver ensuring that everything was carefully strapped and loaded.
Unfortunately, the weather meant that we have a future job. Heavy rain Wednesday night meant that we could not use the long term laydown areas for rail, ties, etc. and had to locate everything for outside storage on gravel surfaces. So there will be lot of relocating once the weather improves. However, the electrical boxes and other sensitive items are now all in covered storage.
After this rush of activity, the guys in Denver have been preparing the oak timbers that will be used to mount the bridge onto the flatcar but have now run out of work and are returning home.
Everything is prepared with heavy lift equipment lined up to lift the bridge from the pit and onto the flatcar. However, we must now wait for the flatcar to arrive on site, along with the idler cars that will travel under the overhanging ends of the beam. All this is ordered and in-transit via Union Pacific to the Burnham yard but it is currently expected to be late this week before they arrive. Once they do, there will be another rush of activity but, until then, there is nothing more that can be done.
Congratulations to Dennis and the team on a very successful job so far. Now we all wait in anticipation of the lifting and loading operation.
Nigel
Thursday, April 7. 2016
More from the Silver Pony Crew Posted by Roger Kramer
in California Zephyr Silver Pony at
20:19
Comments (24) More from the Silver Pony Crew
Here's more developments on the Silver Pony restoration.
Last Sunday, April 3rd, Jeron Glander and Cody Ziarko met up in barn 11 to continue working on the Silver Pony. All pictures in this post are provided by Jeron.
They were testing parts of the 110 volt system and then began removing some seat frames to prepare for the replacement of the broken lower body windows later this year.
They were later joined by Brian Paterson of the Coach department and Ben M. from the Steam Department. When the Silver Pony was originally built, it used a motor generator system to supply 110 volt A/C to power the ceiling fluorescent light fixtures in both the passenger and bathroom areas. There are also 110 volt outlets located throughout the car for be used for the vacuum cleaner appliances. Remember, this was a first class car and cleaning standards were top notch. Cleanliness was the order of the day. Passengers expected that kind of service on these trains. Nonetheless, sometime
during its career with the DRG&W RR, the motor alternator was removed and replaced by a solid state inverter. This converts 32vDC into 110vAC. This solved a number of mechanical and electrical issues with the car. Jeron and Cody are in the process of locating a set of batteries to install under the car in the battery box so that the inverter will be able to function properly.
During the previous week Jeron removed all the old Alaska Railroad heralds and the GCRX reporting marks from both sides of the car. These were all vinyl decals, so a heat gun and plastic scraper made quick work of the removal process. Even this little change greatly improves the exterior appearance of the dome.
Another view shows the emptiness of the barn 11 after removing equipment. These is part of the BIG SWITCH This view was taken April 6th after Jeron and Cody had removed all the seats and bases. What a difference |
Blog AdministrationCategory TreeCalendar
QuicksearchArchivesSyndicate This Blog |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Powered by s9y.
Comments
Wed, 04-01-2026 09:01
Good job on the barn 15
Wed, 03-25-2026 18:21
Exciting to see a new barn going up! What's next, after the RAIL project is complete?
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?