Sunday, June 10. 2012Steam Department Update 6-9-2012The high temperature and the number of visitors associated with the Union Pacific family day meant that work was a little more subdued than usual this weekend. However some significant progress was made. On 1630 the main focus was on investigating the back head braces. As discussed last week, the drawings, which have been the basis for previous calculations, suggest that this is the most highly stressed area of the boiler and potentially limits the pressure at which we can operate. For this reason we worked on ways of measuring how big the braces really are. This is no easy task as the critical braces are above the inner firebox 6 to 8 feet back between rows of stays that are only 4 inches apart. The picture shows the area braced. The position of the attachment bars is marked in chalk and, within these, the circles show the attachment points of the braces. The method developed relies upon using a rigid steel "fork" that is strong enough to break scale off the brace and marginally less that 1 3/8 inches across. This will just fail to pass over a 1 3/8 brace but would easily pass over the smaller 1 1/4 or 1 1/8 (the 3 sizes shown in the design). This was proved and tested on the front tube sheet braces, which are very similar but easily accessible. Most of the team supported Jeff and Phil to develop a rig of webcam and lighting that could be fitted between the stays to observe and record the fork being applied to braces hidden above the firebox. Whilst painfully slow and hard work for the guys, particularly given the heat, the results were very encouraging. The first two of the hidden braces we have reached are definitely NOT the smaller 1 1/4 size shown on the drawing but 1 3/8. So we can already say the bracing is stronger than drawings would suggest. The bad news is that the remaining six braces are even more tricky to get to!!. Phil made a second test fork shaped to give us the best chance of reaching these and we will continue next week. The shot above is the result of this process. This is about 7 feet along the length of the firebox but clearly shows the brace and the measuring fork. The fork would be an easy fit on a 1 1/4 bar and just fails to pass over a 1 3/8 rod, so this is clearly larger than the drawing shows. (In case anyone is wondering why a difference of 1/8th inch is so significant, the stress is related to the cross sectional area of the braces so the difference in area and reduction in stress between a 1 1/4 and 1 3/8 brace is a full 20%). Mike, Bob, Ed, Stu and others continued drilling out the rivet holes for the firebox patch. This is now approaching completion. All the holes are now pilot drilled and are being steadily increased in size to create the exact size required for the rivets. We received the steel bar needed to produce the piston rod for the McCabe and Bob set that up in the lathe to start the machining to produce the piston rod. Once the McCabe is repaired we can start work on the patch itself. Glenn repaired the Sullair so we are now ready to sand blast the tube and start work on the safe ending the super heater flues. Stu and Bob worked on assembling the hydraulic pump for the planer. This will be a powerful tool if we can bring it into service. The table moves back and forth thru the cutting head allowing several large items such as axle boxes to the machined consistently and simultaneously. Phil and I collected the new cab windows for 2050 that have been made in the woodwork shop. These are beautifully made and will really improve the look of this impressive locomotive. .............. Don't forget the Steam department benefit at Sanfillipo on July 1st tickets are available on the main web site. Nigel Sunday, June 3. 2012Steam Department Update 6-2-2012At least I was able to get back to Union this weekend although mainly as a nuisance to others as I cannot lift anything much!!. Some key milestones were achieved. On 1630 we reached the important milestone that has been our objective for several weeks · All the measurements of boiler sheet thickness for the form 4 have now been completed. We owe an enormous thank you to Tom Huber of ECE Global who spent a second day crawling in and over the boiler with the UT testing equipment to complete a comprehensive set of measurements of every part of the pressure vessel. Collin, Phil and several others from the team supported him in locating points, cleaning and recording. We now just have to plot all the final measurements on diagrams of the sheets to complete a major part of the form 4. · Dennis cut back and welded a small crack we found in the dome lid securing ring. We had been wondering how a crack this shape could form and now we know. It resulted from a small inclusion (defect) in the casting when it was made 95 years ago !. So it is now better than it has ever been. · The flexible stays where the caps have been removed were thoroughly cleaned and are now ready for hammer testing; · A lot of progress has been made toward safe ending the super heater flues. A rigid measuring bar was made from used boiler tube to allow exact lengths to be confirmed; Glenn Traced the problem with the Sullair to a broken fuel pump so we can hope to sand blast the material needed for the safe ends once the replacement fuel pump arrives next week; Phil and Cameron have made substantial progress on chamfering the ends of the flues to accept the safe ends; One flues that was found on inspection to have an existing weld was shortened to allow a new end to be fitted. · We will probably do some work over the next couple of weekends in an attempt to clarify one anomaly. 1630 has been restricted in recent years to a 160 psi boiler pressure as opposed to the 180 at which it ran during its service with the Frisco and Eagle Pitcher. The reason for this is not wear but an apparent anomaly in the design. Drawings of the boiler consistently show the back head braced by a mixture of 1 3/8 and smaller diameter 1 1/4 diameter braces. The reason for this is unclear as, even by the standards when built, inclusion of the smaller braces brought stresses at 180 psi close to the limit in this one area when all other areas of the boiler show substantial reserve. As shown a couple of weeks ago, these braces, particularly the ones shown in the drawing as 1 1/4, are extremely difficult to access. However, yesterday for the first time we did manage to get a measuring tool to one shown in the drawing as 1 1/4. The strange thing is that it does not appear to be smaller. So the big question we will try to answer is whether the braces are actually bigger than the drawing shows. Paul reached a milestone on the truck for the Shay. This has now been needle chipped to the point at which we should be able to give it a final application of degreaser then a final steam clean and be ready to inspect and repaint. Given the large number of visitors to be expected next weekend for the UP event, steam cleaning will be scheduled two weeks out. This is not something you would want to be doing with many visitors passing by!. Nigel Sunday, May 27. 2012Steam Department Update 5-26-2012A second hand update this week as I was not there. It sounds like a good day's progress despite (or probably because of .. !!) my absence. Thanks to Phil for the input. Steady progress on 1630: · Bob and Phil worked around the UT measurement points to ensure that those where we could not get a clear signal last time are ready for retesting. We have confirmation that Tom will be back next Saturday to do this; · Bob now has the measurement packages for several of the sheets to allow work to progress on the form 4; · Eric was able to depth check most of the stays on the Fireman's side except for a small number where heavy lifting to remove grates will be required; · Bob needle chipped the wrapper sheet around the turbo generator and removed the last of the insulation in that area; · Phil cleaned off the top to the tender. Next we will need a spell of needle chipping to prepare it for painting. This is not an area that is visible to the onlooker but, being flat, it gathers water and needs to be well primed and painted to avoid rust; · Cameron and Phil started work on preparing the ends of the super heater flues for safe ending. These have to be ground to provide a taper into which the tapered end of the extension tube is fitted and welded. (These are not simply butt welded as it is important that, should the weld fail, the flue would not simply drop into two pieces); · Unfortunately the Sullair developed a problem which prevented sandblasting of the tube section that we need for the safe ending.. In other areas: · Paul continued needle chipping the truck of the Shay; · Ralph machined the last of the bull rings for 428; · A large team worked on the rivet furnace and the fire brick for the base has now been poured in situ. It looks as if this is now getting close to ready once the concrete has dried and will then need to be carefully fired to prevent cracking. Nigel |
Blog AdministrationCategory TreeCalendar
QuicksearchSyndicate This Blog |
|||||||||||||||||||||||||||||||||||||||||||||||||
Powered by s9y.
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...