Monday, April 13. 2009DC Line Department updateWe had a great turnout Saturday! Charlie Strong, Stan Wdowikowski, Warren Lloyd, Joel Ahrendt, Roger Smessaert, Rod Turner and "the new guy" Mike Sorenson. All under my supervision Dug out and straightened the seven remaining poles. That completed the worst section that had to be fixed. Sunday, March 22. 2009An overview of the line dept.Let me explain to you what the A/C-D/C Line Dept. does. The Line Dept. is the electric utility part of IRM. We design, install and maintain the museum's overhead and underground electrical systems. Both A/C power & lighting and D/C traction power. We also install and maintain signal & telephone lines above 7 ft. for those respective departments. We also design, install and maintain the building wiring systems for the Buildings & Grounds Dept. Our system is quite elaborate. Com Ed, our local electric utility, maintains a 34kv to 4kv substation on our property. Everything on the 4kv side of the transformer is owned and maintained by IRM. Our system consists of 7 miles of 2400/4160 volt line, single & three phase transformer banks from 1kva to 750kva, voltage regulators, two 800kw rectifiers, a traction power substation with 2 -2500amp feeders and electronic relays, many poles, underground ducts and manholes. We're like a small town. We own a digger derrick and a bucket truck. We maintain a stock of protective rubber goods: hose, blankets,gloves and sleeves- all up to date. We have hot sticks, hot arms and lots of other "tools of the trade". We always work safely. The best part: it was all built and is maintained by unpaid VOLUNTEERS! If you love this trade like I do or just interested in linework. Come out and help! The line dept is Fun! THERE's MORE TO IRM THAN JUST TRAINS. Max Tyms 815-923-4391 Sunday, March 22. 20093-22 line dept updateWith all our protective rubber back from the lab we're ready to work safely for another year. This warm weather feels great. The frost is just about out of the ground making digging by hand possible. Things have dried enough to allow access to work locations again. This week was spent finishing up some old projects. Monday, was telephone day. A new cable was run from the terminal box on the East wye to barn 3. This will replace the underground cable that got an "oops" with a trenching machine a couple of years ago. This new 12 pair cable was installed in existing ring run then ty-rapped to a #6 copper wire to drop to the barn. Tuesday, I replaced the rusty spanwire and finished transferring equipment on the poles in front of the depot. A new down guy was installed and everything was pulled up tight and served permanent. All the old wire was removed and old poles cut up. All that remains is to pull the pole butt and clean up. Wednesday, the forecast rain never fell. So, Roger and I did some more telephone work. A 6 pair cable was fished through existing ring run from the terminal box at the east end of Central Ave. along the tracks and over the diamond. This is a particularly congested area. With the tail track, yard tracks and carline converging, there is literally a spiderweb of trolley wire, span wire, pull-offs and feeder at that location. Setting up and maneuvering the bucket through all that wire, to reach the telephone messenger, was time consuming. We eventually got that cable in the 3 spans of existing ring run. Next, we had to turn a 90 and head to our destination-The Hoffman Bus Garage. That would involve installing new ring run for two spans over hot trolley wire and the trolley bus line to a steel pole near the building. Then, a drop to the building. We began by rubbering up the yard track trolley wire. Then proceeded to string a 1/4" EHS galvanized messenger across the yard track. After pulling enough slack in the 6 pair cable to reach the building, we strung that across the yard track. The messenger was permanently deadended on one side and temporarily clamped on the other. The 6 pair was clipped in a couple of rings to clear the trolley wire and the rubber was removed. We coiled up the excess wires and called it a day! Most of Thursday and Friday were spent in the office getting quotes on materials for other projects and chasing down an operating coil to fix the Depot St. street lights. Although I did spend some time in the material yard looking for a 6" pole clamp. I was also able to fix a damaged down guy and get the trolley bus wye back in service. Saturday found me at IRM before the sun. Picking up the telephone job where I left it. The safest way to continue, after giving things a good look, was to deenergize the trolley bus line. There was too much hot wire and special work to cross over with a bare steel messenger. The line was switched out and grounds were applied. I then proceeded to string the messenger and 6 pair cable to the steel pole near the building. With the messenger pulled tight and deadended I began to snap the 6 pair in rings. Working back cable rings were installed every 18 inches. Johnney balls were installed in the messenger on ether side of the trolley wire where they crossed. Bonding around the insulated sections was also installed. The johnney balls create an insulated section of messenger over hot trolley wire. This prevents a short circuit and the resulting damage in the event a trolley pole dewires and contacts both the trolley wire and the grounded telephone messenger. The bonding maintains continuity of ground around the insulated section. With rings installed I worked on the drop to the building. A #6 solid, hard drawn, insulated copper wire was strung from the steel pole to the building and the 6 pair cable was ty-rapped to it every 9". The cable was run into the building and awaits termination by our phone guys Les and Wally. That ended a busy week for me at IRM's A/C-D/C Line DEPT. |
Blog AdministrationCategory TreeCalendar
QuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]