Comments
Thanks to Jim and Jerry for all their work lagging this week. We could not have made as much progress on the sheet cladding without their efforts!
#1 Eric Wahlmark on 2013-10-13 19:03
Thank you Eric. My bad. I was thinking thru what was done Saturday and omitted Jim and Jerry's efforts during the week. Nigel
#1.1 Nigel Bennett on 2013-10-13 21:39
What is left to do on 1630?
#2 Andrew Ossler on 2013-10-20 15:31
Broadly, make sure the superheater elements do not leak at the joints into the header, fit the accessories and steam test. The steam tets will tell us what we have to do to fix any minor faults over winter then, in addition to any fault fixing, obviously the lagging and painting are to be done. Nigel
#2.1 Nigel Bennett on 2013-10-21 01:06
Add Comment

E-Mail addresses will not be displayed and will only be used for E-Mail notifications

To prevent automated Bots from commentspamming, please enter the string you see in the image below in the appropriate input box. Your comment will only be submitted if the strings match. Please ensure that your browser supports and accepts cookies, or your comment cannot be verified correctly.
CAPTCHA

 
Submitted comments will be subject to moderation before being displayed.