| BLOG | DIRECTIONS | SCHEDULE | STORE | |
Sunday, September 30. 2012
Steam Department Update 09-29-2012 Posted by Nigel Bennett
in Steam Department at
13:09
Comments (5) Steam Department Update 09-29-2012Well I'm glad to say that after the problems last Saturday we were able to move forward very well this weekend. Glenn did a great job during the week in getting the starter of the Sullair rebuilt and refitted. It may be overkill but we added a battery isolator on Saturday !. On 1630 work on rebuilding the boiler proceeded well: · Collin and Jeff made great progress on painting the boiler shell. After final cleaning, almost all the interior of the boiler barrel was painted. If all works to plan, Jason and Eric will be in Sunday to deal with the tube sheets, dry pipe and the last area around the exit. · After a few tests, swaging of the new boiler tubes started in earnest. My initial intent had been to do 5 that we could test fit them to the boiler. Having done the first couple, Tom checked them and confirmed they were good so we went straight into production. We now have 24 swaged at one end and annealed at the other, so ready to test fit to the boiler, cut to final length and then start expanding into place. Only another 150 to go !. The swaging area now shows a good quantity of finished tubes on the "output" side. No photographs of the process as I seemed to be the prime candidate for working the furnace and swager, which made photography a little tricky!. · Tom and Stu worked on methods for cutting ferrules from copper tubes now we know that we cannot buy them. A series of approaches using band saws, pipe cutters or a lathe failed as the result tended to be egg shaped or had ridges that it would make fitting difficult. However plan D worked. Using the large band saw with a stop set at the required 5/8 inch length, two people can cut them reliably in less than a minute each. A little work is required to take off the rough edges with emery cloth but we now have the means of mass production and produced the first ten. · Ed continued the boiler pipe work. We now have the first of the new pipe runs largely in place. · Mike continued forming the second test patch. This is now pretty much formed and ground to size and the next step will be drilling the rivet holes and fitting. So far so good. If the next stage works, we will be able to start on the patch itself. Dennis was back after a busy summer and was able to progress some of the welding tasks: · On the Shay, the new retainers for the springs were fitted to the bolster so we can now start planning the reassembly of the truck; · Jeff worked with Dennis on the design for the a boom and lift cage for the fork lift that will enable us to use it for lifting large parts such as the throttle and dome cover on to the top of the locomotive; · Bob worked with Dennis on fitting the reinforcing sections to the gear of the wheel lathe. These are now complete so when Dennis is next available in a couple of weeks, we can hopefully finish this gear and reassemble this part of the wheel lathe. Also on the Shay, Tom and Stu drilled the tell tale holes on new stays and test fitted these to the firebox. A number of tasks were progressed in preparing for the winter: · Rick, Bob and Glenn worked on clearing the area around the new large compressor in preparation for set up and testing; · Bob cleared the area around the cab of #428. One of the cold weather tasks will be to complete the riveting of the cab so that it can be refitted to the locomotive. Not only will this be a big step on #428 but it will free up a big and useful area of the shop for fabrication work; · Bill and Stu worked on the water supply in the boxcar. This will need to be winterized soon but we wanted to ensure that it was operating since it was reported as inoperative when Leviathan visited. In the event it proved to be fully functional. However it takes an inordinate time to clear the air from the pipes and draw water from the underground tanks. Hopefully we can make some modifications to install a non return valve and avoid this issue. Once the air locks are cleared it certainly moves a lot of water quickly. Nigel Sunday, September 30. 2012
CGW X 38 Update - September 29, 2012 Posted by Robert Kutella
in Chicago Great Western X 38 Russell Snow Plow at
05:20
Comments (0) CGW X 38 Update - September 29, 2012
A good day, an energetic crew, and two unexpected volunteers showing up to help on the project. All in all a very good day!
My personal goal for the day was to see about applying the first lettering to the north side. During the week, I pored over photographs, worked hours at the computer using a drafting program, and resolved font and sizing issues. I printed out the needed art patchwork on my small home printer and proceeded to tape and stitch it together. This paper 'stencil' merely serves to transfer the pattern to the side of the equipment. After tracing on to the car side, the stencil is removed and we use a fairly small brush to apply special white lettering enamel. We are halfway there and you can see it taking shape. I do this very slowly, slower with each passing year. I am sure a professional sign painter would have long completed these three characters by now. But we muddled through it and now the plow carries its proper CGW number after an absence of such identification of over 40 years. Work began on the south side of the plow with Jim Leonard placing a half dozen new carriage bolts to anchor internal timbers to the steel sides. This included removal of the old bolts, cleaning and priming the areas around the bolts, and then installing the new ones and tightening everything up. Jim made some more progress on the south door threshhold and fit issues are resolved, with the cast plate in for machine shop work. Jim moved on the new framing for the north window. Each piece had to be squared, adjusted to fit, and bolted firmly in place. It looks good, now we better get some maroon paint on those shiny boltheads and new wood. Long time volunteers Ray Pollice and Gerry McGonigal were on hand and pitched in. They are removing the old paint and rust from areas of the front nose and plow faces. Little by little, a patch at a time, a substantial amount of the surfaces have been cleaned and primed. Sunday, September 30. 2012
B&O Boxcar Update - September ... Posted by Robert Kutella
in Baltimore & Ohio 374065 Wagon Top Boxcar at
05:06
Comments (0) B&O Boxcar Update - September 29, 2012SEE THE MAGIC HAPPEN!! After a summer of brutally hot weather the temperatures seem to have become more moderate. The past few months the car work has continued although the order of certain tasks had to change to protect the health of the volunteers. Body repairs continued in the form of removing rust, cleaning old paint, repairing dents and dings, repairing the interior car floor, emptying the car of much stored equipment, cutting away rust outs, fabricating new steel panel plugs, welding them in, grinding, installing new rivets, and prime painting. If you were to walk by the car, much of this progress might not be noticed except by a very detailed look by a trained observer. But the day dawned clear and Victor Humphreys was on hand early in the day, cleaned and wiped down sides, and in short order the first finish paint was being applied to the south side of the car. It was an almost instant transformation from an ugly duckling to a swan of princely stature. Three of the panels on that side were painted with the correct finished color and the effect is spectacular, and gratifying to see the work. Thank you Victor for being the champion on this project and doing much of the work yourself. Thursday, September 27. 2012
CGW X 38 Update - September 26, 2012 Posted by Robert Kutella
in Chicago Great Western X 38 Russell Snow Plow at
08:41
Comments (2) CGW X 38 Update - September 26, 2012As mentioned previously, the weather was good, and we had a good sized crew for the project. Dave Rogan and Jim Leonard started the day by setting up the scaffold and sanding down the maroon paint applied two weeks ago. Just one of the necessary steps before applying the second coat of the finish paint. Victor Humphreys took over and we now have smoother shiny maroon on all that area. The new rear window sill was installed, and new molding added for stop jambs on the top and each side of the opening. Jim Leonard is adding the last one here. The temporary plywood blank was cut down and installed and for now this opening will live that way through the winter. Dave Rogan needlechipped below the south door opening. It got primed and then they moved on to fitting the steel threshold. That may involve a little more than we first thought. Dave did some more neddlechipping on the rear wall and Fred Ash also helped out there for awhile. Jim Leonard is fitting into place and bolting in new framing timber for the window on the north side. The rough timbers had been planed and sized previously, now to make them conform to the exact needs. Rich Witt helped manning the shop drill presses and boring and counterboring the needed holes 'on demand'. All four were installed at the end of the day. As soon as one task was done, the volunteers were ready and eager to move to the next. Soon, we hope to finish cleaning the rear wall and some work got done on that today. But as soon as the finish paint was being applied to the north side, we did not think it was a good idea to work right next to that operation. So, the crew moved forward to the nose and began more needlechipping and wire brushing on the wedge face and knife metal. It also helped reduce the noise in the rear areas where other work was being done on the plow.
Thursday, September 27. 2012
B&O Boxcar Update - September ... Posted by Robert Kutella
in Baltimore & Ohio 374065 Wagon Top Boxcar at
08:32
Comments (0) B&O Boxcar Update - September 26, 2012Progress continues with the pleasant weather, although heavy ground fog early today made one question how it could turn out so nice. The first two panels are finally ready for finish paint. The welding, rivets and priming are done, and Victor Humphreys is sanding and touching up the primer. This is the last patch to be done along this half side of the car. One more day of work and priming, and then it is off to the races with more paint. The car is looking really nice with the rust outs gone and sides smooth and intact, bulges gone. The large area of filler to the right and above the new steel is an area that had severe pitting in the original steel side, some sort of badge or board having resided there at some date in the car's past. Thursday, September 27. 2012News and Views - September 26, 2012The exceptional weather on this fall day energized everyone and a lot went on, as usual for a Wednesday which is becoming a very popular day for volunteer work. Work has continued on the TMER&T D 13, which is work car dump motor. In recent weeks most of the roof structure over one of the 'telephone booth' cabs has been replaced and restored. New saddles have been made and are fitted, ready to install. Today, Gerry Dettloff, John Faulhaber, and Henry Vincent applied a new canvas fabric to the roof. As they work their way along the side, it almost seems that democracy is in action. "What should we do next on this side?" Note that the car is in one of our storage barns and access is difficult, the crew resorting to creative staging and ladders. Except for Gerry who quickly scampered up on top. In the shop Pete Galayda (shown) and John Nelligan continue work on the Charles City Western steeple cab locomotive. Here, a 'box' of resistance grids has been disassembled, a myriad of rusty and sometimes damaged parts in array on the work table. Each is carefully cleaned or replaced and the parts reassembled into a box arrangement. This is Number 3 of seven to be done. In recent weeks the Wednesday Special Projects Team have also been working on baggage car MILW 1309. Some ten (or more?) years ago this was completely restored but years outdoors in the weather have resulted in a shabby and worn appearance. That should not come as a surprise to any of your readers, but points out that the long term preservation of equipment, and best use of volunteer resources is NOT to do work over again, but work to fund and build the next Barn. But it is looking very nice indeed. Tuesday, September 25. 2012News and Views - September 22-23, 2012As I mentioned previously in these entries, my time this weekend was almost totally consumed by IRM hosting a meet of folks interested in old wood working machines. Over 85 attended on Saturday and I would like to thank all the volunteers that contributed their time and effort to make it a success, led various tours, and to those who cooperated indirectly in deferring their work, or scheduling it around the clinics and demos in the wood shop area. That said, I managed to pick away at machining a new window sill for the X 38 snowplow and there was other work going on. We thought the brutally hot summer would never end, but mother nature knows differently. Nearby Sugar Grove registered a 32 F reading Sunday AM. Now the race is on to use remaining good weather days on our projects before Jack Frost settles in for the winter. Victor Humphreys continues at warp speed on the repairs to the sides of our B&O wagon top boxcar. Here is the first panel with new steel welded in, the welds ground down, and body filler applied and sanded. Also you will note the new 'rivets' in place and the area ready to be prime painted. The Electric Car department managed to execute a long and complicated switch move to reassign space of many cars now that the Zephyr repairs are complete and the trips have been run. (Remember that the Zephyr occupied most of Track 41 to allow repairs to take advantage of the repair pit.) So the big news is that TMER&T 972 is back in Barn 4. Watch for developments on this project in the coming weeks. |
Blog AdministrationFind us on FacebookCategory TreeCalendarQuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Mon, 06-17-2013 09:50
Wish I could be there to help.
Fri, 06-14-2013 16:50
Matthew, Any special event is the decision of the museum Board. My personal opinion is that it is likely that there would be a special event to [...]
Thu, 06-13-2013 18:33
Hi, I have a question, if or when she is restored and back up and running this or next year. Will their be a special event set up for the return of [...]
Tue, 06-11-2013 22:36
The whistle 1630 wore for a while that you're thinking of was a Frisco 6 chime donated by a former member of the steam shop. It was on it a few times [...]
Tue, 06-11-2013 18:03
You are talking here about something well before my time !. I have not seen her with anything other than the whistle she now carries. If she [...]
Mon, 06-10-2013 16:17
i'm curious here. Will 1630 ever wear the ATSF 6 chime she had on for a while? Better defines her, I love the deep whistle she has now but the higher [...]
Sat, 06-08-2013 15:15
Many many many many many thanks for getting the Spaulding webcam working!!!!!
Fri, 06-07-2013 16:55
The donation was to the museum as a whole. How it is used and whether any comes to steam department projects will be the decision of the museum [...]
Fri, 06-07-2013 16:53
Basically the plan is "ONLY" reassembly. As far as we know she is is reasonable mechanical shape. The big mechanical problem that stopped her (slack [...]
Fri, 06-07-2013 16:28
Nigel I read you guys got a one million dollar check donation!!! Will this be used to finish 1630 ,428, 5 and get started on the others next in line?
Fri, 06-07-2013 16:16
So does 1630 basically only need reassembly? With the boiler in particular. Does her tender or running gear need any work before she's ready for the [...]
Fri, 06-07-2013 12:00
Hello.. The voltage we are using and presumed the RR also used is 120 vac. The system is a little unique because the lite bulbs are each 60 volts. [...]