There were two very separate activities at the steam shop this weekend.
Outside, the Kansas City Southern tender from Galt arrived and had to be unloaded and put back on its trucks (which had arrived separately during the week). Here the rather unusual trucks of this tender await the arrival of the tender itself.
The tender is a fairly substantial items as can be seen from comparison to the B&G building as it enters IRM for the first time.
A good deal of careful back and fore was required to position the tender (still on the trailer) centrally over the track so that the mounting points would be in the correct position to fit into the trucks.
Once in place steel beams were located under the body. The trailer had then to be raised, blocks placed under the beams, and then lowered a number of times until there was sufficient height to set jacks under the beams.
Finally the jacks were all placed and the tender could be raised off the trailer.
The trailer is free and starts to move out from under the tender.
The trucks are chained to the trailer and each other so that they are pulled under the tender, at the correct spacing, as the trailer pulls out.
The job of lowering the tender back onto its trucks so that the pins aligned and the pivot points located into the sockets in the trucks proved to be a long and tricky exercise. It was well past dark by the time this was completed so pictures of the completed tender are for next week !.
On 1630, things looked bleak in the morning. We are absolutely dependent for tube loading on those of the team who can fit into the boiler. Having arranged a morning and afternoon shift, as it is more than one person can do to work in these conditions all day, Collin's car failed and he was not able to get to Union in the morning. However, while we lost the morning shift, Jason did sterling work in the afternoon. Here we see him "relaxing" between loading tubes. It is not a environment in which you can work for more than a few hours at a time.
We have now completed loading of the tubes down both sides of the super heaters. The fireman's side, looking forward, now looks pretty full compared to earlier views when we were sand blasting.
Looking toward the firebox on the engineer's side also shows the boiler filling rapidly. This also shows the positioning of the copper ferrules, which are set slightly below the surface of the tube sheet in the firebox, where the end of the tube will be beaded, but projecting into the boiler barrel, where the copper can be seen around each of the new tubes.
Mike continued work on drilling the rivet holes in the patch. The accurate alignment of these holes is proving to be a significant challenge.
Nigel
Comments
Mon, 06-17-2013 09:50
Wish I could be there to help.
Fri, 06-14-2013 16:50
Matthew, Any special event is the decision of the museum Board. My personal opinion is that it is likely that there would be a special event to [...]
Thu, 06-13-2013 18:33
Hi, I have a question, if or when she is restored and back up and running this or next year. Will their be a special event set up for the return of [...]
Tue, 06-11-2013 22:36
The whistle 1630 wore for a while that you're thinking of was a Frisco 6 chime donated by a former member of the steam shop. It was on it a few times [...]
Tue, 06-11-2013 18:03
You are talking here about something well before my time !. I have not seen her with anything other than the whistle she now carries. If she [...]
Mon, 06-10-2013 16:17
i'm curious here. Will 1630 ever wear the ATSF 6 chime she had on for a while? Better defines her, I love the deep whistle she has now but the higher [...]
Sat, 06-08-2013 15:15
Many many many many many thanks for getting the Spaulding webcam working!!!!!
Fri, 06-07-2013 16:55
The donation was to the museum as a whole. How it is used and whether any comes to steam department projects will be the decision of the museum [...]
Fri, 06-07-2013 16:53
Basically the plan is "ONLY" reassembly. As far as we know she is is reasonable mechanical shape. The big mechanical problem that stopped her (slack [...]
Fri, 06-07-2013 16:28
Nigel I read you guys got a one million dollar check donation!!! Will this be used to finish 1630 ,428, 5 and get started on the others next in line?
Fri, 06-07-2013 16:16
So does 1630 basically only need reassembly? With the boiler in particular. Does her tender or running gear need any work before she's ready for the [...]
Fri, 06-07-2013 12:00
Hello.. The voltage we are using and presumed the RR also used is 120 vac. The system is a little unique because the lite bulbs are each 60 volts. [...]