| BLOG | DIRECTIONS | SCHEDULE | STORE | |
Sunday, May 22. 20112011 Mainline Tie Project
This
year, like most years, the museum’s Track Department undertakes a large
tie renewal job. This is a necessity to properly maintain our railroad
and allow for a high quality ride all of our visitors and volunteers
have come to expect. This year, it was decided to undertake one of the
largest tie renewal projects to date, nearly 750. Typical years may see
500 ties replaced anywhere on the property where they’re most needed.
This places a huge strain on us to complete the bulk of the work before
operations ramp up in April and May. Whether it’s the Mainline, Carline
or little used yard track the importance of maintaining our track for
the safety of the public, our volunteers, and the fragile equipment we
operate is always the top priority of the Track Department. Always…
So what does it take to get the job done? This process began last year with the purchase of the 750 brand new ties to be installed. All of which were delivered by truck and unloaded on the property. During this year’s detailed track inspection beginning in the cool month of March we walked up and down the railroad not only inspecting the track, but also marked bad ties to be replaced. Once a majority of the ties were marked for replacement we had to figure out the best way to get the new ties on site. This year, because of the huge quantity of ties, we found it best to load all of them onto a flatcar and roll them out to the site. With our Burro crane we unloaded all of the bundles in the general locations that would be needed. This is not an easy process and most of this work happened during the last half of February and into March. Needless to say there was plenty of ice and snow on the ground to make the job difficult. With the ties all on the ground, the lengthy process of placing each tie in the exact location where it was to be installed began. Mostly, this involved the tie crane and an operator working eight or nine hour days over the weekends. This step took many weekends throughout March and April to complete. While that was happening, we also moved new spikes in locations they could be accessed and continually worked on machine maintenance. Things break, machines wear out, and we spend a lot of time and elbow grease keeping the machines in running condition. With only our small core group of volunteers, and without the necessary equipment to do the actual replacement ourselves, we hired a railroad contractor to truck in their own equipment and swap the bad ties for the new ones. This took a solid week for the contractor to finish the job and then the cleanup of all the material was left to us. As with most tie projects, the work typically disturbs the track severe enough to require a slow order. The problem of support under the ties becomes an issue without being properly tamped. Until that happens, the ties may not have enough ballast underneath which could create an unsafe condition. At this point the race was on to clean up the railroad before the operating season gets into full swing. During this time all of the old ties were collected with the tie crane and placed in one large pile near Johnson Siding where they will eventually be picked up taken away by another railroad contractor. Just like when they were all set out, the job meant the tie crane and operator must spend long days peddling ties back and forth. This year it took us five or six full working days and detailed cleanup still isn’t finished. In addition to all of the ties, other material had to be picked up, such as old line poles and tree limbs. This adds considerable time and energy but needs to be done. With the wood picked up we focused on gathering all of the steel scrap which took the form of 2,800 spikes from the tie job, hundreds of old tie plates and other track material left on the line from years past. This could only have been done quickly and efficiently with our Burro crane and its electromagnet. We took one of our flatcars and ran up and down the line until the flatcar was full of steel and brought it back to the property to be sorted. That brings us to today. The next steps will be to get rid of our huge tie pile at Johnson Siding, and surface the railroad. Surfacing the railroad will be done in house using our ex Amtrak production tamper purchased a few years ago. Contracting an operation such as this would cost the museum another $40,000 and that does not include regulating the railroad afterward to finish the project! All of the work done in house by the Track Dept. easily cuts the total cost of the project in half and in this season alone has already saved the museum roughly $50,000. The alternative to any of what we do in house involves renting and trucking in equivalent machinery and paying contract wages. Work will continue throughout the season to tamp and dress the line working between operations and special events. Follow up maintenance on all of our machines and sorting materials from the line will take many more weekends of work. Without the equipment we have, most of this wouldn’t have been possible. While most of this work goes unseen to a majority of our volunteers and visitors, it is this work that is required for our museum to function as a world class operation. None of this could be done without the dedication of our Track Department working odd hours in all sorts of conditions. Thanks to all who have helped on this project including Frank DeVries, Tom Hunter, Bill Lygiros, Patrick Shea, Jeron Glander, Mitch O'Brien, Bob Olson and Adam Robillard. Also we must thank everyone who supported the work including, but not limited to, the Operating Department granting us track time, Dave Diamond in the Buildings & Grounds Department, and anyone I may have missed. …and that’s what it takes to get the job done More Track Dept. photos from Frank Devries and Adam Robillard can be found in the Member's Photo Site here- http://www.irm.org/gallery/Members-Photos Monday, March 14. 2011Sunday's Track ReportRiding on the success of yesterday's progress today our two goals for the day were to clean a few machines with the pressure washer, and unload the ties loaded onto the flatcar yesterday along the mainline. The short version of the story is that both jobs were completed but not without a little excitement in between. The crew today was myself, Tom Hunter, Jeron Glander, and a new volunteer, Patrick Shea. We started right away with the rented 3000psi heated pressure washer and cleaned up the tie crane, regulator and Model 50 Burro crane. After cleaning the radiators on the burro it ran significantly better now that it has proper air flow drastically minimizing the possibility of overheating the engine. We picked up our loaded flat car of ties and the EJ&E 529 caboose and headed out onto the carline. The rest of the day was spent unloading around 400 ties along the mainline. Tom expertly ran the crane while Jeron, Patrick and myself hooked and unhooked the bundles along the line, mostly between Seeman Rd and Four Mile Siding. We'll come back out with the tie crane sometime soon and distribute the ties where they'll be installed. It was an incredibly productive day and called it quits after tying up shortly before sunset in Yard 11. This week the rest of the ties (~250) should get loaded onto the flatcar which should allow us to repeat the job again next weekend. Thanks again to Patrick for joining us for a second day in a row. Hope we didn't scare him away. Adam RobillardIRM Track Dept Saturday, March 5. 2011Saturday's Track Report
Today unofficially marked the beginning of 'the busy season' by inspecting the first portions of the mainline for its return to revenue service in the coming weeks.
Food started off the morning in Marengo with Frank Devries and myself. After arriving to the property we were joined by Bob Olson and began walking track from Seeman Rd working East. The priority was to walk and mark ties to be replaced this year as well as inspect for the usual defects; joint bars, bolts, breaks, culverts and anything else that isn't quite right. We walked a few hours before calling it lunch at Subway. Tom Hunter met us there and we were off for a few more hours of inspection. We officially walked from Signal 201/202 all the way to the east end of the line. A few hard miles in full winter gear. Totals from the day include 387 ties marked for renewal between West Switch Johnson to Four Mile Siding (+ a few more not yet marked), one center broken joint bar and two pull aparts. At least another 100 ties will be marked once we clear ballast off the track between Poles 39-46ish. The goal is 700 ties on the mainline this year which we will begin to distribute next weekend. Slow orders and O.O.S. bulletins ARE posted and will stay in place until repaired. We called it a day with dinner at Joe's and wrapped up a lot of loose ends. Frank will be out tomorrow and next weekend we'll begin loading flat cars with ties for distribution and probably working on repairs as well as continued inspection. Come out and join the fun! ***If you're interested in helping out give me a shout at lzeje657@msn.com or find any one of us on most weekend and we'll get you hooked up! Adam Robillard IRM Roadmaster lzeje657@msn.com Monday, April 19. 2010Track Department report April 19Sunday's gang consisted of myself and Tom Hunter. Jeron Glander joined later in the day. Riding off the success at Four Mile Siding last weekend Tom and I prepped tools and material on the crane, flat and caboose combo and headed East to finish building the siding. We didn't waste any time when we got there pulling the storage cars from the siding and using the crane to connect the last two track panels. I realized we had forgotten lock washers to finish bolting them together but all of the joints have a bolt on each side until we can pop a few more in. After finishing off the second panel an investigation into a low oil pressure issue was found to be a hot engine... A little Too hot. It looks like the water pump has failed or the radiator is severely clogged. But with no coolant flow on the top of the radiator it brought our crane use to a severe halt. With the crane shut down Tom and I moved on to spiking up all the remaining ties in the section we had installed the rail in last week. Using track jacks, air compressor and spiking gun we had one entire side spiked up in no time. Prepacked lunch followed in the 529 and then onto spiking the other side.... After restarting the air compressor, without fail, it sputtered off and wouldn't restart. Upon investigation of this issue we figure a bad fuel pump. Fuel in, no fuel out... How about some hand spiking to ease the frustration? Of course! We spiked up the entire other side by hand just in time for Jeron to arrive with the Ballast Regulator. We set the panels in a rough line and Jeron, who reinstalled the rebuilt hydraulic cylinder earlier in the day, plowed stone from the siding into the new track. Getting late in the day we called up for a 'tow' back to the property not risking an engine failure without coolant..and were grateful to see Joel Ahrendt, Warren Lloyd and Kyle Merkel arrive with the ComEd 4 electric steeplecab to help us back. While waiting, Jeron managed to drag nearly enough stone for a first lift on the new track to the very end of track. The end will need somewhere around 12-18" raise but it's very close to complete as is. The 'in service' trackage was officially extended roughly 80' and the last of it will be extended another 80' once we make a good raise and tamp. Sunday, April 11. 2010Track Department report April 11The day started with Brian Harp and Tom Hunter refilling the hydraulic tank in the Amtrak Regulator. It drank roughly 40 gallons of fluid severely depleting our 55gal drum of oil. We'll have to get more soon.. After I arrived and met up with Steve L. we prepped for a day at Four Mile Siding. Tom ran the crane with work train with Brian as the conductor and headed east to switch out the siding, while Steve and I switched Barn 2 to retrieve the Hydraulic power pack and motorcar. We followed east and began by moving trees with the crane. BIG trees. The biggest tree we had to slide down the track on two ties and teeter it off with the crane into a wide clearing. The tree maxed out the crane's capacity at near 10,000 lbs but Tom managed to set it off very nicely. A few more large limbs were moved out of the way as well before we had the room to begin building track. We cut, drilled and installed a stick of 112lb rail and gaged the track to set everything up for the first panel to be hooked up. We gage spiked a few ties under the new rail for the crane to roll onto to hook up the first panel Jeron Glander arrived via the North Shore 714 with a gift of bottled water and helped us out for the rest of the day. We lifted the first track panel out of the way first to clear the ground of limbs and sticks to get a relatively smooth foundation for the new track. Tom then set the new panel in place and we bolted it all up with relatively little difficulty. We cleaned up and headed back to the property around 4 o'clock. All that is left is the hookup of the next two panels and finish spiking 12 or so ties. One more day and we'll be ready for the regulator and brush cutter to begin their work. Thanks to Brian Harp for joining us this weekend. I hope he can join us again in all of the festivities before next year's annual meeting. On a bad note- the J585 refuses to start now. The starter problem has gotten much worse and it no longer spins the engine over to crank.. Flywheel replacement time? Looks like a return of the 580 is imminent. Sunday, March 28. 2010
Track Dept Weekend Report Mar 27, 28 Posted by Adam Robillard
in Track Department at
23:02
Comments (0) Track Dept Weekend Report Mar 27, 28Saturday Report --- The day's primary project was the joint effort with the Signal Dept to get the very large Corwith Tower lever machine into our Spaulding Tower. This proved to be no easy task. The entire lever machine is roughly 20 ft in length and weighs nearly 9000lbs... The signal dept can report further on its future but our part was the heavy lifting with the Model 50 Burro crane to get it into the lower level- through the doorway. Tom Hunter ran the crane and after a few test lifts near Barn 9, we lifted the machine near the station and ran it into the Tower very slowly and carefully. We were successful in getting it in the building around 2PM and hit lunch. Lets hope that machine never has to leave the tower again! After lunch, the crew of Tom Hunter, Tyler Hunter, Frank Devries, Jeron Glander and myself, Adam Robillard split into a few groups. Jeron and Tyler ran to Napa and picked up new fuel filters for the Burro crane and along with Tom Hunter replaced the filters in the crane and fueled up the machines in yard 11. Jeron did some wonderful electrical work on the Amtrak regulator and also broomed a yard track in Yard 10 to test the functions. All which appear to be working well. Nice job Jeron! Meanwhile Frank and myself were at Track 24 pulling the bad vibrator motor out of the Switch Tamper and prepping the install of the new one Tom had stored in his garage. We managed to get the new motor in and wired up but it hasn't been tested yet. That's for another day. The next project was to relocate
the brush trimmer that has been stored in one of the electric
carbarns. It cannot be left in the open near the public beginning next
weekend so we needed to switch it back into Track 24. Tom and the gang
took the EJ&E 585 motorcar to retrieve it only to have the entire
machine derail on the Yard 6 lead.... Call in the Model 50! While
Frank, Tom & Tyler took time to rerail the cutter, Jeron and I
headed onto the carline to weld traction bonds. The portion of track
we surfaced over the last few weeks revealed three joints with broken
or non existing bonds. Some quick work with our stick welder resolved
that problem and the two of us went back to Tk24 to clear all the
machines out of the Barn. When the cutter was rerailed, now well after
dark, we shimmied it into the back of Tk24 and switched everything back
in the Barn. We called it a night around 9PM. Wow, what a day. Monday, March 15. 2010
Track Dept Weekend Report. March 14, 15 Posted by Adam Robillard
in Track Department at
15:24
Comments (0) Track Dept Weekend Report. March 14, 15Saturday Report from Adam Robillard and Sunday Report from Frank Devries: --------------- Today was just one of those days things just seemed to go right. It's about time I'd say. The day started early with Frank and myself and the first order of business was to make a run to Farm & Fleet for some hydraulic oil and parts. While we were away, JD Marzec and Greg Frech both showed up willing to work! They did some invaluable work 'derusting' and lubing track bolts in the shop and did a fine job. Upon our return we hit the machine maint. work. Frank filled the hydraulic on the switch tamper and began testing the new pump he had installed previously. Unfortunately it turns out the pump is pumping the wrong direction... a bit more trouble shooting and adjusting will be needed to hopefully get the machine back to 100% soon. JD, Greg and I topped off the hydraulic on the 6000 tamper and about that time Tom Hunter joined the gang. We did some QC bolt work on the 6000 and cleaned up the tool boxes and prepared to tamp.. The original plan was to do a walking inspection of the main line but the hit or miss weather was enough to keep us close to home.During lunch we formulated a plan for the rest of the day. Frank, JD and Greg set to do an oil/ filter change on the Amtrak Ballast regulator which desperately needed it. The air filter is the color of dirt and as Frank put it "hasn't seen daylight since the Carter Administration..." Tom and I ran to Napa for oil and filters and Frank, JD and Greg prepped the machines in Yard 11. While that gang was doing the oil, Tom and I switched out the 6000 tamper and began tamping the Streetcar line between Electric Park and the S-Curves. The initial goal was to test the machine from its winter work and break it back in. Amazingly everything seemed to work well and only a few minor adjustments will have to be made. We spent the next four hours tamping the carline and after the Regulator was finished Frank, JD and Greg ran it around to our work area and began regulating the freshly tamped track. Jeron Glander joined the gang later in the day and did a great job running the regulator after JD and Greg needed to leave. The four of us worked well into the evening hours surfacing the track with our recreation of an Amtrak surfacing gang. The ballast regulator made it through the day but the backlog of work continues to pile up. A few things fell off the machine unexpectedly but nothing to stop the machine from working. By the end of the evening we had the track fully tamped and a majority of the regulating complete. Some more work will have to happen in the daylight but otherwise it is mostly complete. Its amazing how much work can be done with a few good machines and a great crew. Next up we'll begin tamping the mainline... There is plenty of surfacing work there to keep us busy for a while. Thanks to all who helped today. We accomplished an incredible amount of work, far more than any of us expected. Thanks, Adam Robillard -------------------------------- More of the same...... The first task was to determine the electrical short on the regulator. When the lights were knocked off during the barn 11 project, the one light was hanging by the wire. Seems during our work on Saturday, it came in contact with the muffler, burned through the insulation and shorted. Jeron had noticed the high amp readings Saturday night. A quick clip of the wire resolved the short. The light bulb was broken in that light anyway. I noticed most of the lights are burned out on the machine. Next trip out I will pick up some spares from Napa. We fired up the regulator and resumed the plowing and brooming of the carline between Electric park and the S curve. After a short period of time Jeron noticed a hydraulic leak. I sent him back to yard 11 to put the machine away. Jeron found the leak was a loose hydraulic hose, and with quite a bit of trouble, tightened up the loose connection. Apparently like all track machines it was not as easy as putting a wrench on and tightening. From what I understand it involved a hydraulic power pack unit, and a lot of contortionist like moves. Once fixed, it was back to work. Brooming and plowing continued until another leak was noticed. Seems the valve for the oil pan had worked itself loose. When the leak was noticed we shut down quick, and resolved the leak. So that machine had it's second oil change this weekend. I will hit up the hardware store to get a plug for that valve to avoid a similar issue from happening again!!! By the end of the day the track looks really good. There is still a bit of box work to be done, but it is a huge improvement. While Jeron was fixing the hydraulic leak, I went for a walk. Track walking that is... I was able to inspect from East Station switch to Signal 251. During that walk, I found several loose joints, a couple of hanging joints that will get fixed when we tamp, but no breaks, no other defects that will affect opening day. I also marked several piles of OTM and scrap along the main for pick up with the 50. Brush through this stretch looks good. A touch up could be in order around Karsten's, but that's about it. I also marked ties for replacement between E. Station and Karsten's. I think the total was around 140 ties. I marked 5 ties off the bridge to ensure we have good support going into the bridge. Photos have been posted of the Carline results in the gallery below. A few shots of things from barn 10 as well. http://www.irm. Frank D. |
Blog AdministrationFind us on FacebookCategory TreeCalendarQuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Sun, 05-19-2013 22:13
Hello again. I had an idea that was (somewhat rudely, mid-sentence) dismissed in talking to a museum volunteer a few years back, but here it goes [...]
Thu, 05-16-2013 21:52
Looking good Bob! I hope to come out soon once I'm done with school.
Wed, 05-15-2013 21:28
I was not around at the time. General discussion suggests that it was "pretty marginal" in a number of areas. Nigel
Mon, 05-13-2013 11:08
"THUMBS UP!"
Fri, 05-10-2013 02:15
No, it will not be necessary to hold any of the work waiting for the plow to be turned, end for end. Weather will be the major factor, but there will [...]
Thu, 05-09-2013 19:54
The CGW X-38 plow is really coming to life. Bob Kutella and Vic and crew need to be very proud of your collective efforts. I am very appreciative of [...]
Thu, 05-09-2013 15:20
The snowplow looks great! Are you going to apply the door and upper windows befor it is turned to continue work?
Thu, 05-09-2013 09:09
Max, Is there any progress to report yet, in regards to the installation of the poles and overhead wires? Have a good day, sir.
Wed, 05-08-2013 18:40
Thanks for the update! I still don't understand why Commonwealth #5 was removed from service. Do you know why?
Tue, 05-07-2013 09:28
Mr. Kolanowski.....I was just wondering if the Spaulding webcam will be up and running soon for us stay-at-homes. Thanks!2FP
Mon, 05-06-2013 23:04
Max, Has work begun yet on the construction phase of erecting the poles and putting up the wire? Wish I could be there to watch it happen.
Mon, 05-06-2013 23:02
Keep up the good work, Bob. Wish I could be there to help!!!!!!!