Shay update, January 2016:
Happy New Year! My
last report here regarding the Shay was back in September. I had fully intended to do a report following
my three week trip up to IRM in October, but life has a way of
intervening. It also doesn't help
matters that I tend to like machining, painting, and mechanical work better
than putting my thoughts on paper. But,
here we go.
As Nigel has been reporting, great progress has been made
since my last report towards returning the Shay to service. I will try to put some names down here to
thank and acknowledge those who have helped on the Shay for all of their hard
work. I will undoubtedly miss names, and
to those people, I can't thank you enough for all of your continued help on
this project. When you great blog readers
visit IRM, please remember that everything you see running and restored is
thanks to the hard work of our volunteers and the generosity of our
donors. Thank you all!
On to the Shay.
During my three week vacation work was progressing on the Shay on a
daily basis. Many volunteers came in on
weekdays when normally no one is in the shop, and this help really pushed our
project forward. As Nigel has already
given descriptions of much of what has been accomplished on the Shay during my
three week "vacation" and leading up to today, I will attempt to add
what I can to what he has already covered.
As of now all of the work to properly seal and form the ends
of every boiler tube is complete. At
IRM, we use the time honored, traditional methods of installing boiler flues
used almost universally in the steam era.
I can go into this process in further detail in a future blog if people
would like, but suffice it to say for now that the methods we use take a lot of
time, but result in a tube job that should give us a very well-sealed boiler
for all 15 years of service until the next federally mandated boiler
inspection.
One stay bolt was found to be broken the first time we
filled the boiler with water, and a couple of days later it was replaced.
Trevor, with help from Ben, has finished preparing the
inside of the water tender for painting with a protective coating. In the upcoming weeks Cody will be leading
the project of painting the inside of the tender tank.
As Nigel has reported in previous shop reports, the boiler
on the Shay has passed its federally mandated hydrostatic pressure test. This major milestone will now allow us to
proceed with the jobs of adding parts back on the boiler.
The boiler on steam locomotives gets an insulation material
applied to it. This is called
lagging. Surrounding the lagging is a
sheet metal skin called the jacket. We
use a type of block insulation that, while quite messy and itchy to apply,
works quite well and can withstand the pressure of engine crews standing on the
jacket repeatedly while doing maintenance on the locomotive. Jerry has started the process of securing
wires circumferentially and evenly spaced along the boiler which will be used
to secure the lagging to the boiler.
The process of applying the blocks of insulation will begin
shortly. This job consists of wiring
individual blocks of lagging onto the boiler, one at a time, securing them to
the previously mentioned circumferential wires to hold them in place. Once the insulation is applied, the task of
refitting the jacket can begin. To
prepare for this, several volunteers, including Jane, Ben and others, have been
working to remove old primer and rust from the back sides of every piece of
jacketing, and then priming and painting the back side to help prevent rust and
keep the jacket in good condition. We
have thus far held off on doing any cleaning up of the outside surface of the
jacket, other than removing old grease and oil, until we decide whether to
paint the locomotive over this winter or not.
Painting takes a good amount of volunteer time that may otherwise be
needed for other mechanical projects to get the locomotive into operating
condition. If the mechanical side of the
project continues at a good pace, some paint work may start in the next few
months.
Once the lagging and jacketing is installed, work can then
turn to reinstalling all of the piping necessary to make the locomotive
operable. This includes water delivery
pipes, steam pipes to the various appliances, and air piping for the bell, sanders,
and brake system, as well as related brake control stands in the cab.
During the Shay's whole operating life, from the time it was
built to the time it was retired from regular service, it burned oil as its
fuel source. When the Shay was converted
to burn coal by the Chicago and North Western Railway in preparation for its
arrival at IRM in the late 1960's, an industrial grate system was
installed. These grates performed
generally well over the years. However,
as they were not designed for locomotive use, they were at times cantankerous
and hard to rock in order to clean clinker and ashes from them each
morning. Also eventually, due to age and
use over time, the grates would warp or break, necessitating periodic
replacement. Around the time the
locomotive was removed from service at IRM the decision was made to make the
proper grates for this locomotive. To
this end, Steam Curator Tom Schneider, following original Lima Locomotive Works
drawings, made new wood patterns to have all new, proper, grates and side
bearers cast. Phil and I spent time in the Shay's firebox in October measuring
and laying out where the new studs will be welded in the firebox to support the
new grate system. In the next few weeks
the hope is that our welder Dennis, aided by Phil, will weld in these studs. Once this is done installation of the grate
system and its associated linkage can be carried out.
Another large area of the locomotive, the smokebox, has seen
a great amount of work done on it in the past couple of months. All of the holes needed to rivet on the new
bottom portion of the smokebox have been drilled, and the bottom piece was
bolted on, awaiting riveting and welding to the old portion. Several of the rivets that need to be
installed are in an area inconveniently close to the frame of the locomotive. Because of these close confines, normal riveting
practices are quite difficult. To make
it possible to rivet in these areas, Tom and Dennis designed a special fixture
that will allow us to use the frame of the locomotive to our advantage to aid
us in driving the rivets!
Hopefully Nigel can describe this in better detail in a
future blog update. Once the riveting is
done, Dennis will weld the new bottom to the old part of the smokebox. Soon after this is done, installation of the
superheater units and other front end pieces can begin. To prepare for this, our machinist, Eric, has
been busy machining a few newly cast pieces that were made to replace old steam
fittings for use in the smokebox that were very heavily deteriorated from years
of corrosion and use.
There are always many, many small projects among the larger
ones involved with locomotive restoration.
One of these currently is replacement of several wood brackets used to
secure lubrication piping above the motor unit.
Over the years these pieces have rotted out to the point where they do
little to hold the lubrication piping in place.
Phil and John have been working on replicating these pieces,
and they should be reinstalled in the next few weeks.
Being away from the museum as much as I am can not only make
it a challenge to manage a project in a way that moves a project along at a
good pace and keeps everyone happy, but it is also frustrating when I wish I
could physically do more to help while I am not there. Because of this I took on a project for the Shay
that could be done from home. It was
quite common for logging locomotives to have steam driven water pumps on them
to use for firefighting for washing the locomotive, and I am sure for various
other uses. Our Shay has had one of these
duplex steam pumps on it most of its life.
Unfortunately, when the locomotive was retired and before it came to IRM
the pump appears to have been removed from the locomotive. In the early to mid 1970s, volunteers
replaced it with a different pump. While
not the same brand of pump the locomotive carried in service, the pump is an
appropriate stand in. In fact, while
doing research on this pump, I found that the pump is older than the
locomotive! This pump has not been
operable in the time I have been a volunteer at IRM (starting in 1995) and even
Tom Schneider, who has been with IRM since the mid 1970s, doesn't remember the
last time this pump was operable. For
many years I have wanted to rebuild this pump and return it to operation. I started working on it in April of this
year, and I am happy to report that its rebuild was completed on December 23rd;
my Christmas present to IRM, the Shay, and the steam shop.
If there is interest I can write a blog about the
restoration of this pump at a future time.
But for now, I am excited that the pump is again operable, works well,
and will be serviceable on the Shay hopefully for years to come.
Overall, work on the Shay is moving along at a fine
pace. Much has been accomplished since
my last report in September, and the list of things to do is growing ever
shorter. We are still working towards
the goal of seeing the locomotive operate in 2016.
As Nigel and I have both mentioned, we are actively seeking
donations towards the rebuilding of the Shay.
Nigel has informed me that since his last plea for funds several
donations have come in for the Shay.
THANK YOU!! We really, truly
appreciate every donation we receive. I
think perhaps us members don't always express well how much we really
appreciate all of you who donate money to preserve and rebuild our equipment,
but we couldn't do the work we do without your help. So again, thank you very, very much.
I would also like to say a huge THANK YOU to every member of
the Steam Department who has helped on the Shay's restoration to date. Each of you will be to thank for the
locomotive's return to service. This
said, we always welcome new volunteers.
If any of you reading this have thought over time, "Someday I would
really like to go out there and try volunteering in the Steam Shop," well,
why wait? The work is dirty and results
can happen slowly, but there is a lifetime of learning available to those who
are interested, and generally a good amount of fun as well. You don't need to know a thing about steam
locomotives, but just have a willingness to listen, learn, and work. Come out and talk to us in the shop. There is always someone there every Saturday.
Whether you are a donor, a volunteer, or a visitor to IRM,
thank you for your support, and here's hoping that 2016 sees us have two of our
own steam locomotives in operation for the first time since 1999!
Brian Davies