Sunday, August 26. 2012
Steam Department Update 08-25-2012 Posted by Nigel Bennett
in Steam Department at
14:07
Comments (0) Steam Department Update 08-25-2012The second weekend of Thomas and temperatures into the 90's predictably led to a slower work day at the steam shop. However we are now seeing more clearly that work is shifting to the new phase of preparing for reassembly. On 1630: · On Monday I met George, the welding specialist from Curtis Boiler, on site and he carried out the welding on the rear tube sheet. · As mentioned in previous, weeks this was the last critical step to be ready for internal inspection of the boiler by the FRA. With this done, Collin spent Saturday morning cleaning and clearing tools from inside the boiler as well as carefully inspecting all the surfaces for any sign of cracks or damage and polishing any rough edges from the tube holes. We can now advise the inspector that all is ready for inspection and hope that he will be able to fit us into his schedule in the near future. · Glenn and Richard did some rework on the safe ends for the super heater flues. Inspection on Monday indicated that a couple of these had been cut from tube that was more pitted than desirable so new ones were made ready for welding to the flues in the next couple of weeks. · A good start was made on cleaning and preparing the nuts and bolts that secure the super heater elements to the header. This is typical of a lot of work that we will be doing in the next few months. These bolts fit into the header at the top of the smoke box so have a tough life, in the path of the exhaust gases from the fire. To remove them required heating to red heat with the acetylene torch. Now they must be thoroughly cleaned, the threads checked and re-cut as necessary, to ensure that they fit and tighten smoothly when we come to fit the elements. · Vince cleaned and lubricated and number of the flexible stays ends so we are now well on the way thru that process. · Kevin is back for a few days and continued with needle chipping the exterior of the boiler and support brackets so that we will be able to do a thorough re-paint. He is at Union for several days so this activity will continue during the week. · Mike continued with test fitting of the patch. This is a very tricky exercise, a sort of three dimensional jigsaw. It looks as if we are now close with this test. Once this is done, we will run thru a second test to prove that the principles developed can be applied reliably to and then we can hopefully produce the patch proper. · I worked with Tom on preparations for fitting the tubes to the boiler. This is quite a complex, multistage, operation that you will hear a lot more about in the next couple of months!. The first step of the process is to expand the ferrules (copper rings) fitted between the tube and the rear tube sheet into the holes before the swaged tube is fitted. After working with the various sizes of ferrule that we have been sorting and measuring for the last couple of weeks it is clear that we have nowhere near enough of the most commonly required size. We will determine in the next week if we can get ready made ferrules this size in a reasonable time. Otherwise we do have the right size of copper tube and will need to start cutting about 200 of these little rings !!. Good news, it is now clear that, once you know how to match the ferrule size to the hole, the fitting process can be rapid. After all the measuring and testing I was able to fit the first 5 ferrules in no more than 10 minutes. This is likely to be the pattern throughout this operation. We know that years ago re-tubing a boiler was an remarkable fast process. We will have to become familiar with each of the steps and then try to become efficient but accurate at carrying it out. On 428: · Machining is speeding up on the axle box thrust bearings. The first one is complete and the second nearly so. Interesting. The attachment to this box looks quite different from the first. This seems to be a common factor with 428. Each part has been differently repaired at different times. Nigel Sunday, August 19. 2012
Steam Department Update 08-18-2012 Posted by Nigel Bennett
in Steam Department at
14:02
Comments (0) Steam Department Update 08-18-2012The number of volunteers at the Steam shop was lower this weekend as it usually is during Thomas weekends. However some key tasks were completed. On 1630: · The last of the troublesome smoke box bolts was removed. With the bolts out, I was able to clean up all the holes and test fit new "T" bolts into all of them bar one. The new bolts are now being ordered for 10 of the 11 holes. The 11th requires more work. The smoke box has clearly been reinforced since this one was fitted so a rivet is now positioned that prevents setting the bolt into the ring from the rear. Tom will need to make a special stud that we can fit from the front and secure by welding a nut on the back. However, this repair is now largely complete and ready for when we refit the smoke box front sheet. · All the flexible stay caps, that were marked as requiring removal, were successfully freed. This requires heating the socket of the stay with a torch before unscrewing the cap. Applying brute force to the socket wrench without using heat to loosen the thread is absolutely not recommended!. Cracking or otherwise damaging the socket would mean that the whole stay must be removed by drilling it out of the inner firebox then rethreading and fitting a complete new stay - several days of work - so it is a big relief that all are now off with no damaged sockets. One damaged cap was successfully removed and will be replaced with our last spare cap. A few more will be ordered to ensure that we have some spares in hand. The caps must be removed and the stays hammer tested where the stay does not have a full length tell tale hole. Once the cap is removed you normally find rust, scale and debris that must be cleaned out to allow later hammer testing. Once clean you can get a good idea of how the stay operates. In the center is the ball head of the stay, a long steel rod the other end of which is threaded into the inner firebox sheet The slot in the ball would have been used when the stay was installed to turn the rod and so screw it into the inner firebox sheet. The ball sits in the socket, which is welded to the outer firebox sheet. Screwing the rod into the inner sheet tightens the balled end of the rod against the socket. As with rigid stays, the objective of the flexible stays is to hold the inner and outer firebox sheets together against the full pressure of the water and steam that lies between the sheets when the boiler is in service. The difference is that flexis are used where it is calculated that there should be (marginal !) movement between the two plates as they expand This would strain and potentially crack a rigid rod. The movement of the ball in the socket allows this movement. Tightening the ball into the socket provides a significant, but not complete, seal against the boiler pressure so the cap provides the final seal. This is why there is likely to be some debris in the socket when you first remove the cap. · Mike continued with test fitting of the patch. · We also started on the exercise of measuring the holes in the tube sheet and matching these to the ferrules that must be fitted before the tubes can be inserted. · Most importantly, it now looks as if we should have good news on the welding by next weekend. On 428: · Machining is now well under way on the thrust bearing surface of the first axle box. This clearly shows the remains of the old thrust bearing which consisted of mesh (actually old spark arrestor mesh from the smoke box was specified in the UP drawing), which was tack welded to the face of the casting and held in place the babbit which was poured into the recess, allowed to set and then machined smooth. · The overhaul of the pump mechanism for the planer was completed. The next step is to clean and test the hydraulic drive mechanism. Nigel Tuesday, August 14. 2012
Steam Department Update 08-11-2012 Posted by Nigel Bennett
in Steam Department at
08:35
Comments (0) Steam Department Update 08-11-2012A short and late update this weekend as I was in Michigan for my son's wedding on Friday. This did at least mean that we had smaller groups working both Saturday and Sunday. On 1630 work continued on the key tasks: · Between the two days we managed to remove 5 of the fireman's side smoke box bolts so we now have 10 of 11 out and have started to source the replacements. None have shown any sign of moving when hammered. So now we first cut off both the exposed thread and the head of the bolt in the smoke box: Then we have to drill most of the bolt core away with a magnetic drill. Only then can you drive the shell of the bolt out with an air hammer. Heaven knows how these were fitted - but they sure were not intended to come out again !! · Jason completed a full review of the flexible firebox stays and marked those where the caps must be removed for inspection and hammer testing. Most of these have been done leaving about 20 for next weekend. · The pipe to replace the corroded lines down the side of the boiler has arrived and marking up to bend and connect the replacement sections can now begin. · With a family visit on Sunday, my wife spent much of the day sorting our supply of ferrules into sizes and removing those that were damaged. These ferrules are a critical part of the re-tubing process. They are copper rings that are fitted in the rear tube sheet between the sheet and the tube when it is expanded. From initial count it looks as if we may have all we need but will need to match them up to the tube sheet in the next couple of weeks to determine if we need any more. The key objective is to ensure that we have all that we require in hand before we get to tube fitting. · Unfortunately we seem to be having difficulty agreeing a start date with the welding contractor who needs to finish the work on the rear tube sheet before we can schedule the internal inspection of the boiler. On 428 the machining of the axle boxes was started. The first box is now on the Bullard turret lathe and the process of machining off the lateral bearing has begun. The intent is to fit brass wear plates similar to those on 1630 rather than the poured babbit used on these boxes in the past. Bob came by with the newly fabricated collar for the wheel lathe that now needs just final boring to be ready for fitting. With this critical piece in hand we are a major step nearer to being able to bring the wheel lathe into operation. Nigel |
Blog AdministrationCategory TreeCalendar
QuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]