After a week of planning, great progress was made on the turntable
in the last ten days. This is critical
as site clearing will start this month and we must have the table out before
this happens.
JD and Phil travelled to Denver in a truck loaded with tools
and equipment and have been working with Dennis and track contractors based
locally.
The stages of the removal are:
1.
Remove and ship the rails, deck, railings,
circle rail and everything else that can be taken from the top of the main
bridge beam;
2.
Lift the main bridge beam from the pit and lay
it on the railroad flat car that will carry it to Union;
3.
Take the trucks and center bearing, along with the
remaining ring rails that lie under the beam and load these for transport to
Union.
A surge of activity early last week saw everything on top of
the bridge beam removed, stacked and then loaded onto 3 flatbed trailers. By Thursday, all 3 were unloaded at
Union. Many thanks to Dave and Carl for their
efforts in unloading. Each trailer was unloaded
in 45 minutes, which was an indication both of their efforts and the good work
of the team in Denver ensuring that everything was carefully strapped and loaded.
Unfortunately, the weather meant that we have a future job. Heavy rain Wednesday night meant that we
could not use the long term laydown areas for rail, ties, etc. and had to
locate everything for outside storage on gravel surfaces. So there will be lot of relocating once the
weather improves. However, the electrical
boxes and other sensitive items are now all in covered storage.
After this rush of activity, the guys in Denver have been
preparing the oak timbers that will be used to mount the bridge onto the flatcar
but have now run out of work and are returning home.
Everything is prepared with heavy lift equipment lined up to
lift the bridge from the pit and onto the flatcar. However, we must now wait for the flatcar to
arrive on site, along with the idler cars that will travel under the
overhanging ends of the beam. All this
is ordered and in-transit via Union Pacific to the Burnham yard but it is
currently expected to be late this week before they arrive. Once they do, there will be another rush of
activity but, until then, there is nothing more that can be done.
Congratulations to Dennis and the team on a very successful
job so far. Now we all wait in
anticipation of the lifting and loading operation.
Nigel
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...