Sunday, September 30. 2012
Steam Department Update 09-29-2012 Posted by Nigel Bennett
in Steam Department at
13:09
Comments (5) Steam Department Update 09-29-2012Well I'm glad to say that after the problems last Saturday we were able to move forward very well this weekend. Glenn did a great job during the week in getting the starter of the Sullair rebuilt and refitted. It may be overkill but we added a battery isolator on Saturday !. On 1630 work on rebuilding the boiler proceeded well: · Collin and Jeff made great progress on painting the boiler shell. After final cleaning, almost all the interior of the boiler barrel was painted. If all works to plan, Jason and Eric will be in Sunday to deal with the tube sheets, dry pipe and the last area around the exit. · After a few tests, swaging of the new boiler tubes started in earnest. My initial intent had been to do 5 that we could test fit them to the boiler. Having done the first couple, Tom checked them and confirmed they were good so we went straight into production. We now have 24 swaged at one end and annealed at the other, so ready to test fit to the boiler, cut to final length and then start expanding into place. Only another 150 to go !. The swaging area now shows a good quantity of finished tubes on the "output" side. No photographs of the process as I seemed to be the prime candidate for working the furnace and swager, which made photography a little tricky!. · Tom and Stu worked on methods for cutting ferrules from copper tubes now we know that we cannot buy them. A series of approaches using band saws, pipe cutters or a lathe failed as the result tended to be egg shaped or had ridges that it would make fitting difficult. However plan D worked. Using the large band saw with a stop set at the required 5/8 inch length, two people can cut them reliably in less than a minute each. A little work is required to take off the rough edges with emery cloth but we now have the means of mass production and produced the first ten. · Ed continued the boiler pipe work. We now have the first of the new pipe runs largely in place. · Mike continued forming the second test patch. This is now pretty much formed and ground to size and the next step will be drilling the rivet holes and fitting. So far so good. If the next stage works, we will be able to start on the patch itself. Dennis was back after a busy summer and was able to progress some of the welding tasks: · On the Shay, the new retainers for the springs were fitted to the bolster so we can now start planning the reassembly of the truck; · Jeff worked with Dennis on the design for the a boom and lift cage for the fork lift that will enable us to use it for lifting large parts such as the throttle and dome cover on to the top of the locomotive; · Bob worked with Dennis on fitting the reinforcing sections to the gear of the wheel lathe. These are now complete so when Dennis is next available in a couple of weeks, we can hopefully finish this gear and reassemble this part of the wheel lathe. Also on the Shay, Tom and Stu drilled the tell tale holes on new stays and test fitted these to the firebox. A number of tasks were progressed in preparing for the winter: · Rick, Bob and Glenn worked on clearing the area around the new large compressor in preparation for set up and testing; · Bob cleared the area around the cab of #428. One of the cold weather tasks will be to complete the riveting of the cab so that it can be refitted to the locomotive. Not only will this be a big step on #428 but it will free up a big and useful area of the shop for fabrication work; · Bill and Stu worked on the water supply in the boxcar. This will need to be winterized soon but we wanted to ensure that it was operating since it was reported as inoperative when Leviathan visited. In the event it proved to be fully functional. However it takes an inordinate time to clear the air from the pipes and draw water from the underground tanks. Hopefully we can make some modifications to install a non return valve and avoid this issue. Once the air locks are cleared it certainly moves a lot of water quickly. Nigel Sunday, September 30. 2012
CGW X 38 Update - September 29, 2012 Posted by Robert Kutella
in Chicago Great Western X 38 Russell Snow Plow at
05:20
Comments (0) CGW X 38 Update - September 29, 2012
A good day, an energetic crew, and two unexpected volunteers showing up to help on the project. All in all a very good day!
My personal goal for the day was to see about applying the first lettering to the north side. During the week, I pored over photographs, worked hours at the computer using a drafting program, and resolved font and sizing issues. I printed out the needed art patchwork on my small home printer and proceeded to tape and stitch it together. This paper 'stencil' merely serves to transfer the pattern to the side of the equipment. After tracing on to the car side, the stencil is removed and we use a fairly small brush to apply special white lettering enamel. We are halfway there and you can see it taking shape. I do this very slowly, slower with each passing year. I am sure a professional sign painter would have long completed these three characters by now. But we muddled through it and now the plow carries its proper CGW number after an absence of such identification of over 40 years. Work began on the south side of the plow with Jim Leonard placing a half dozen new carriage bolts to anchor internal timbers to the steel sides. This included removal of the old bolts, cleaning and priming the areas around the bolts, and then installing the new ones and tightening everything up. Jim made some more progress on the south door threshhold and fit issues are resolved, with the cast plate in for machine shop work. Jim moved on the new framing for the north window. Each piece had to be squared, adjusted to fit, and bolted firmly in place. It looks good, now we better get some maroon paint on those shiny boltheads and new wood. Long time volunteers Ray Pollice and Gerry McGonigal were on hand and pitched in. They are removing the old paint and rust from areas of the front nose and plow faces. Little by little, a patch at a time, a substantial amount of the surfaces have been cleaned and primed. Sunday, September 30. 2012
B&O Boxcar Update - September ... Posted by Robert Kutella
in Baltimore & Ohio 374065 Wagon Top Boxcar at
05:06
Comments (0) B&O Boxcar Update - September 29, 2012SEE THE MAGIC HAPPEN!! After a summer of brutally hot weather the temperatures seem to have become more moderate. The past few months the car work has continued although the order of certain tasks had to change to protect the health of the volunteers. Body repairs continued in the form of removing rust, cleaning old paint, repairing dents and dings, repairing the interior car floor, emptying the car of much stored equipment, cutting away rust outs, fabricating new steel panel plugs, welding them in, grinding, installing new rivets, and prime painting. If you were to walk by the car, much of this progress might not be noticed except by a very detailed look by a trained observer. But the day dawned clear and Victor Humphreys was on hand early in the day, cleaned and wiped down sides, and in short order the first finish paint was being applied to the south side of the car. It was an almost instant transformation from an ugly duckling to a swan of princely stature. Three of the panels on that side were painted with the correct finished color and the effect is spectacular, and gratifying to see the work. Thank you Victor for being the champion on this project and doing much of the work yourself. |
Blog AdministrationCategory TreeCalendarQuicksearchArchivesSyndicate This Blog |
Powered by s9y.
Comments
Tue, 06-02-2026 19:38
Always a treat when a new diesel comes to IRM! Only wish we'd get more diesel department news from week to week, I always wonder what's going on in [...]
Wed, 04-01-2026 09:01
Good job on the barn 15
Wed, 03-25-2026 18:21
Exciting to see a new barn going up! What's next, after the RAIL project is complete?
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.