Wednesday, November 19. 2008Extending 40 trackThe big project for the weekend was the extension of 40 track near the electric car shop. Saturday's crew was myself, Tom H, Steve L and help from Jeron G. After a trip to Farm & Fleet, Tom continued to tackle the brush cutter in yard 11 replacing more fluids and filters as well as replacing the battery. The machine was almost entirely lubed and ready to use when the starter went out near the end of the day... Sunday Tom managed to get the starter removed and is getting a repair done during the week. Steve, Jeron and myself spent the rest of the day getting material ready for 40 track by locating and loading the rails, tie plates and joint bars. Thanks to Stan from the car shop the Amtrak flatcar was dug from yard 13 and placed with the Model 50 burro while two of us dug out the hydraulic power pack from Track 24. The flatcar was loaded up and by that time it was time to hit the road.Sunday's crew was myself, Tom H and Steve from the track dept as well as MANY more folks from the electric car shop. We had a bunch of help from from other depts including freight car, passenger coach and diesel as well as the day progressed. John B from the freight car dept helped us out from start to finish, thanks for the help and good meeting you John! At the start of the day, 40 track was cleared off by the shop folks using the Milwaukee Electric L7. After laying out the ties and getting our machines to the work area, we torch cut the rail to length, drilled holes in the existing rail, bolted it all together, laid out tie plates, spiked and gaged the track, raised leveled lined, dressed the track and to top it off we spotted the caboose in its final resting spot. In total we built 24' of new track and it took us till dark to finish it all up. The Model 50 burro crane got a good workout as the workhorse crane of the day. We used the forklift to set the ties, burro crane to set the rail, hydraulic power pack to drill the holes, air compressor to spike the ties and tie crane to nip the ties. Incredibly nothing needed to be jump started the entire day... Thanks to everyone for braving the cold including those who could only help out for a little while. It was all appreciated and very enjoyable working together with everyone. It was tiring but I think most of us can agree it was all very rewarding when it was all said and done. The next big project will most likely end up being the yard 11 project. With or without stone there is a lot of work to still get done including the construction of the new 11-4 track and first pass with the tamper on the other 3 tracks. Until that gets underway we will continue to cut brush along the mainline and get more work done of other machines such as the Jackson 6000 tamper, switch tamper and EJ&E 580 & 585 motorcars.I will eventually get some photos up on my Member's Photo page soon from the weekend. http://www.irm.org/gallery/lzeje657 Adam Robillard Sunday, November 9. 2008Track Department UpdateThe team today was myself, Tom H, Frank D and our newest track dept volunteer Steve L. The previously mentioned ex Amtrak brush cutter saw its first day of service today. After a typical jump start, we drove it over to Barn 2 where we had a battery charger running while the rest of us greased the entire machine, cleaned it up and checked fluids. It turns out the alternator which we thought was bad was working fine, but the battery was shot. It wasn't holding a charge so that will be the first thing to be replaced on it soon. Mid morning the car dept brought out the West Towns 141 for a switch move. The car looks great and was the first time i've seen the car outside. Can't wait to ride on it someday soon. Always though blue was a good color for streetcars. The cutter had its fuel topped off and we headed to Central Ave where we set the machine on the tracks and ran it to Karsten's crossing. There Frank and I got a crash course in its operation, which is a beast to get used to, but we managed to cut a couple hundred feet of brush on both sides of the RoW. We found that the line poles for the overhead is going to cause a headache to cut around, but to do a quality cut of the right of way we'll have to spend the extra time to do it right. Steve met us out on the main line around noon and got his first views of the machine as well. The cutter is a two person machine, one driving/ operating one boom and the other person operates the other boom. I think we all agree that it's a pretty powerful machine, enough to cut 5" trees in half... After a late lunch at Wendy's, the four of us met up in Yard 11 to do a few test lifts with the model 50 burro crane. The cold weather made starting the crane very difficult even with the block heater plugged in for most of the day. We did get it to fire and test lifted 3 track panels to measure weights for the new track in yard 11. A few new operators got a chance to run the crane for the first time and all did exceptionally well. All of the track panels are within the capabilities of our crane to handle including the stack furthest away. The 6000 tamper and Model 50 Burro are both on 11-0 track with access to power for the block heaters. We couldn't find a heater on the 6000 tamper (if it even has one) so that is not plugged in. Minus the seasonally cold and crappy weather, today turned out to be a great day. Thanks a lot to Steve for coming out and helping in this subprime weather. Even though it'll get cold and the snow will fly, we'll be working outside a lot taking advantage of the offseason not worrying about revenue trains. If anyone wants to help out there is always something to do. Next weekend will probably be brushcutting, prepping barn 11 or continuing machine maintenance. The switch tamper needs an oil change/ filter and the brush cutter does as well. More to come throughout the week...Adam Robillard Sunday, November 2. 2008Track Department Update
The weather has been far too good lately...we are in for a long winter...
Saturday the track dept was myself, Tom H and Frank D. We had a 30 second reunion to start off the day because both Frank and Tom have been away from IRM for some time and this was a historic momemt...well not really, but ya know. The weather cooperated great. It's certainly fall, but we couldn't ask for better weather. Our original plan was to build track in yard 11 or raise tracks in yard 11 in preparation for the barn. Unfortunately we were not able to touch yard 11 because the contractor was still occupying the building due to some unforeseen issues with the metal siding... Still determined to get something done we spoke with the electric car shop and they allowed us to use the pit in Barn 4 to get some much needed work done on a number of our machines. First for the day was the Model 50 burro crane which we had gotten running last weekend. As in true IRM fashion, we had to jump start the machine early in the day in yard 11. The engine was just too cold to get going but once we got it running it ran great. Over the pit we greased the entire underframe, topped of the transmission with ATF, inspected/ greased the deck rotation gearing, troubleshot a bad hydraulic leak (more to come on that), checked oil levels in the engine, axle gear cases, coolant level and a number of other small tasks. After we were pleased with that, we took the crane outside to test everything and locate the hydraulic leak. It seems the boom extension cylinder inside of the boom is the problem. When the boom is extend and retracted what we believe is the hydraulic seal on the cylinder itself leaks bad and drips oil out the backside of the boom. A repair to this is pretty substantial due to the fact that the cylinder is probably 30ft long and 6'+ in diameter and rests inside of the all welded boom... A few plans are being cooked up now for a remedy, but for now the boom extension is out of service but otherwise the crane itself is not in harm and still in service. The crane is ready for building yard track 11-4 when the time comes. Continue reading "Track Department Update" |
Blog AdministrationCategory TreeCalendar
QuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]