Work progressed steadily around some rather remarkable
events in the steam shop.
I arrived Friday evening, ahead of the Board meeting to
paint the back head ready to fit the fire hole door, to find the middle of the
shop being set up as a left luggage office for a scene in the Transformers
movie. Pity that I had not brought my
camera that evening !.
Around the strange activities, I managed to do the painting
and Dennis worked late, once they had finished, to complete a critical piece of
welding. A few members of the shop team
were around for the filming and, by mid-morning on Saturday, all the cases and
other props were efficiently removed and we were back to normal (or whatever
passes for normal in the steam shop!.
The switching for the film continues to provide views of the
steam collection is unusual places.
Sadly I was not around to see 2903, 2050 and 265 pulled out
into the open. They were back in barn 9,
albeit not permanently as there is still a coach behind them, when I arrived on
Saturday. The feedback from those
involved in the switching suggests that the problem child was not 2050, as we
had expected, but 2903. Despite concerns
about the condition of her springs, the big N&W articulated apparently
handled the curves and switches relatively well. 2903 apparently demonstrated in several
places that the curvature was a good deal tighter than her long rigid wheelbase
was intended to negotiate.
Everything continues
to focus on what is necessary to get 1630 to steam testing.
·
Effort was concentrated on lagging the firebox
in the cab. This seemingly mundane
activity is now recognized as critical.
Even to test assembly of the super heater elements and valve chambers we
need the throttle lever and other controls in place and steam / water tight. Since these are fitted on top of the lagging,
this needs to be in place proto!.
A concerted effort by Rick,
Collin, Ed and Phil achieved what we hope is the worst part of the job. An arch made up of 5 pieces of sheet metal
runs from the footplate either side of the firebox across the top of firebox
around the turret.
The pieces must be wriggled around
pipes and the turret, little blocks of insulation squeezed under the sheet and
the sheet metal joined by threaded rods.
Once the arch is completed in this
way, it is tensioned by tightening threaded rods that attach it to the
footplate. The arch must be completed
first as it secures the sections that are
formed around the corners of the firebox and these in turn secure the flat
sections on the back head itself.
This
was a really nasty job involving squeezing bits of metal, insulation, threaded
rods and small nuts into awkward crevices from confined spaces beside the
firebox and thru the cab roof.
The
guys achieved it and, by end of day the arch is pretty much complete and ready
to tension.
The
only known casualty was one of the cab windows that suffered a break the shape
of Collin's butt and is now in the wood shop for re-glazing!!.
·
Work progressed on the boiler lagging. Eric has been concentrating on this and is
becoming good at stitching the tapered blocks of insulation to the supporting
wires. The first ring is now largely
complete. The blocks are in place. We now need to finally secure them with
banding, fill some to the small holes with insulating mud and then the sheet
metal can be placed.
Jerry put in a lot of time during
the week to ensure that all the sheet metal that was found last weekend is now
painted and ready to fit.
·
Ralph set out into the field to deal with the
Koehring crane, that is used to load coal.
It is really difficult to get coal into the high sided tender of 1630
with anything other than this old machine.
So the fact that it has been unused since 2010 and not in regular use
since 2005 was "a concern".
Much to everyone's (including Ralph's) surprise and relief, it responded
nicely to a well charged battery and some fresh gasoline and, in a few hours, not
only was the motor running but he was able to test the operation of the boom
and grab.
·
Jason and Collin worked on tightening the last
of the tube ends after beading and prossering.
As ever, the last two or three are always the worst. We preheated the water in the milk car so
that we could move quickly to pressure testing as soon as the work was
done. The process required a number of
cycles of bringing the boiler up to operating pressure, identifying the
remaining small leaks, carefully dropping the pressure, working the leaks and
then repeating. However, by late
afternoon the critical point was reached. We determined that the seal was good
enough to go forward to steam testing. So
the long process of refitting tubes is at an end.
·
This, and the excellent members' day BBQ, energized
the team and a lot of changes were apparent in a couple of hours in the late
evening. The gearbox, that has been a
feature of the smokebox for more than a year, is now gone and the smokebox is
wide open again.
Scaffolding was brought in to the
shop to provide the staging from which to install the super heater
elements. Feeling we were "on a
roll" despite the gathering darkness, a small group of us took the B&G
forklift out to the boxcar and fetched the elements for the top row into the
shop and set them onto the staging. We
are ready for a whole new activity next week.
So continued steady progress toward the steam test.
Nigel