It is good to be on the home straight with 1630 but it is
increasingly clear that there is still a lot of work to do!. Also some of it is pretty slow and tedious.
It has been a huge benefit to have Brian Davies on site for
the last three weeks and a great deal has been achieved in that time. Things will move a lot more slowly when he
returns to Florida on Monday.
When I arrived on Saturday it was spectacular to see most of
the steam collection in the open air, having been switched out of barn 9 for the
filming of the Transformers 4.
On 1630 the has been a lot of progress. The two major areas of activity have been finalizing
the fitting of tubes (as a prerequisite to installing the super heater elements)
and fitting lagging to allow installation of controls and air tanks that must
be in place to allow testing.
·
During the week Brian Davies had put in a lot of
hours and had completed the beading of all tubes in the rear tube sheet;
·
On Saturday teams of us took it in turns to
prosser the tube ends in the rear tube sheet.
This process involves expanding the tube slightly on the water side of
the tube sheet, using a multi-segment expander driven by an air hammer. The effect of slightly expanding the tube on
the water side is to firmly lock the tube into the sheet between the bead and
the slight expansion caused by prossering.
Anyway, it is a two man job and, by several teams taking it in turns,
all 200 tubes were completed by late afternoon.
The boiler was then refilled and we started to heat the water. The objective on Sunday will be to test the
tube ends under operating pressure and tighten any that show leaks as a result
of the beading and prossering. As soon
as we are satisfied that the tube ends are dry, the tubing exercise is
complete. The motor can then be removed
from the smoke box and installation of the super heater elements can
begin. So I wait with some trepidation
to see if this can be achieved on Sunday !.
·
Stu and Bob worked with Tom to set up a mounting
that will allow the throttle to be rigidly located for machining and
lapping. The surfaces of the throttle
valve need to be leveled and ground to a tight fit that will provide a good
seal before the throttle is refitted. By
end of day the throttle was mounted and ready for work to be done.
·
Dennis started on the plate work and mesh that
fits around the blast pipe. He has now
assessed all the pieces and identified what new material will need to be fitted
to complete this structure once the blast pipe is in place and the super heater
elements tested.
·
The lagging is proving rather more troublesome.
Two areas are critical for the steam test, the firebox in the cab (to allow
fitting of numerous pipes, valves and gauges that are required both for steam
testing and pressure testing of the super heater elements) and the first couple
of sections of the barrel at the front (to allow refitting of the large air
tanks required to complete the air system).
·
Work started on fitting the barrel lagging at
the front. This is not as simple as it
looks (and it does not even look that simple !). The insulation is rigid blocks that cannot be
conformed to the curvature of the barrel.
So it must be cut into strips about 12 inches wide and the edges cut at
an angle so that adjacent blocks fit tightly together along their length. However the blocks must also be tapered along
their length. The boiler is formed of
3/4 inch plate in overlapping sections.
So, in order to get a smooth taper over which the sheet metal can be
fitted, the 2 1/2 inch insulation must be tapered along its length. (Basically the last section at the rear of
one boiler ring is the full 2 1/2 inches thick while the front section on the
next ring to the rear is 1 3/4 inches thick so that the insulation runs
smoothly over the 3/4 inch transition in the boiler plates). Then, having cut sections of insulation to
the correct taper along its length and sides, each must be cut around any
pipes, hand rails or other projections to fit a specific location. The block is then wired to the wire rings
that were placed around the barrel some weeks ago until a complete circle is
achieved around the boiler. This will then
be strapped into place and the sheet metal fitted over it.
·
The sheet metal provided a bit of a
setback. Jane had done a lot of work to
ensure that all the metal had been cleaned and primed ready for use and had actually been short of
painting work in the last couple of weeks once this was done. When we tried to locate the first major
sheets required for the front ring they could not be found .............. until
we found a whole lot of 1630 sheet metal that had been stored behind a few
sheets belonging to #26 !!. It had been
overlooked for cleaning and painting so Jerry spent much of the evening wire
brushing a lot of sheets and I started painting the ones we need most urgently
..... oh bleep !.
·
However the real nightmare is the cab. The sheets covering the top and sides of the
firebox in the cab overlap and hold down the curved sections that cover the
transition between wrapper and backhead.
These, in turn, secure the sheets covering the backhead. The arch of sheet metal running up the sides
and across the top of the firebox in the cab must first be located so that the
curved sections can be located under its edge.
The critical element of the arch is that two pieces of sheet metal must
be worked up into the maze of pipes and valves around the turret and linked
with 3/8th threaded rods either side of the turret. In addition, insulation
must be set under this area in the form of small cut blocks or mud. Once the link is made the sheets form a
complete arch that is tensioned by other threaded rods secured into the
footplate. All jolly good fun as the
area into which the metal and insulation must be placed can only be reached at
arms' length from the narrow space at the sides of the firebox or by lying on
the cab roof and reaching down several feet into a nest of pipes.
o
Most of the work in this area on Saturday was
planning to determine in which order pieces can best be fitted. This is critical to the project as the
controls essential to testing for leakage in the super heaters cannot be fitted
until this is done.
o
The sheet metal either side of the firebox is in
place to provide protection to the insulation already installed.
o
David finished cleaning the fire hole door and I
chased the threads on the mounting studs so this can be fitted as soon as the
tube ends in the fire box have been proved tight. This is important as much of the backhead
lagging is based upon the fire hole door casting.
In other areas
within the shop:
·
Phil and Cameron
worked with Tom on machining the bolster for the Shay;
·
Dennis started the
long process of building up the axle boxes for 428;
·
Stu and Bob achieved
a major milestone on the planer. The
power is now connected and both motors were tested. The head can now be raised and lowered
correctly and the motor driving the hydraulic pump now operates. The next big challenge is how to remove
decades of muck from the drain area under the bed. Since the lubricant supply to the table is
collected and returned to the pump thru this area, there is a considerable
incentive to get it as clean as possible before we try circulating oil thru the
system.
So, a lot of work
done but still a good deal more needed to get to the steam test.
Nigel