SEE YOU AT THE STEAM DEPARTMENT BENEFIT JUNE 28TH !!
http://www.irm.org/events/steamdeptbenefit.html
What a difference a month can make in the Steam shop.
The South end of the shop now presents a remarkable sight,
wide open in a way that has not been seen in many years.
This is driven by a Buildings & Grounds project to
install sprayed insulation on the roof.
The shop is one of the few heated buildings in the museum and cutting
wastage of heat is a high priority. The
existing panel insulation has been prone to detach and this project is to some
extent an evaluation of a new method to insulate the type of structure used
widely in the museum. Anyway, the
contractors start the first week of June and need clear access to the South
shop. This has driven and been enabled
by some substantial activity on our projects.
First and foremost was #1630. By the end of May, she was routinely located
outside in the preparation area, coaled, watered, greased and ready for another
weekend of operation.
The shine on the paintwork in this picture is no good
things as far as I was concerned!. It
indicates frequent heavy rain while I was doing the preparation. Clearing the firebox and laying a half ton
base of coal for lighting up can be less than fun with 100% humidity and
periods of heavy rain!. For anyone
wondering what is the strange curved object attached to the walkway and
standing well above the top of the boiler, this is the hoist that we use to
lift the fan onto the chimney. So this
is a clear indication that she is ready to fire and awaiting installation of
the fan early the next morning.
Still she ran well again on Saturday despite frequent rain,
rapidly falling temperatures and winds developing to near gale force as the day
progressed. Sadly not too many visitors
to see it!. Those who braved the weather
were rewarded with some spectacular sights of steam trailing across the corn fields.
With #1630 gone from the shop, other big changes were
possible. Shay #5 was linked to its
tender again, albeit temporarily and this allowed her and #428 to be moved
North into the main and North buildings.
So, aside from a big house cleaning, what was achieved in May?.
Obviously the work early in the month focused on
#1630. In recent years May has become a
month of frenetic activity as we prepare for operation and so it was this
year. Many people took days off work and
there was activity in the shop several days each week as we worked thru the
list of tasks to get 1630 into operation.
As was strongly suspected last month, it proved impossible
to be ready for operation May 16th/17th. However steam testing was completed May 21st
and a full weekend of operation was achieved for the 3 day Memorial Day weekend
and we are running the weekend of May 30/31st as a substitute for
the 16/17th. Given the
weather this may not been seen by many visitors!!. Oh well, some you win!.
It is startling how much faster things can move when we can
have teams working several days each week.
In the first two weeks of May:
Dennis finished a great deal of welding including:
building up the mounting for
the tender draft gear;
welding new plate into the
bottom of the tender to provide a solid surface for shoveling;
straightened the tender
footplate on the engineer’s side. This
had a strange “hump” dating back decades to some unknown accident damage and
now provides a level surface for the first time in memory;
attached the tear drops to
the grate shakers.
Phil spent a lot of hours in the cramped space under the
ash pan, assisted by a number of others working outside, to reinstall and
adjust the wedges on #5 axle.
On the first weekend of May, the major task of refitting
the draft gear into the packet under the tender was achieved. This took a lot of brainstorming. The challenge was how to lift this unwieldy
assembly (several hundred pounds and nearly 3 feet long) into a narrow space
under the tender and above the axle. It
is being above the axle that really provided the challenge. The draft gear must be raised into the
pocket. It cannot slide in from the
rear. However the depth of the draft
gear draft gear is such that it barely fits above the axle and below the
pocket. So the whole tender must be
jacked up by the thickness of anything put under the draft gear to support it
on the fork lift.
The eventual solution was to balance the assembly with as
much projection beyond the forks as possible.
It was then secured with a bar below the forks and steel banding around
the assembly. Here JD and Trevor work on
this mounting.
It looked precarious but the acid test (large volunteer
jumps up and down on the projecting end!) proved that it was solid. This way only the thin tips of the forks had
to fit above the axle. With this set up
the fitting went relatively smoothly and the tender was again complete with a
coupler and ready to push forward onto the locomotive. Once it is back in place, it is difficult to
visualize all the effort that has gone into making it look so normal!. JD then completed the operation over the next
few days with a couple of heavy contacts when coupling to break the wood blocks
in the draft gear and release the spring mechanism to its normal operation.
In the second week the footplate welding as completed, the
tender pushed forward to the locomotive and the drawbars fitted to make her a
single unit again. With this done, she
was moved to allow the fitting of the coupling rod on the fireman’s side and
she was again mechanically complete.
Around these major activities, a lot of other people were
working to:
Rebuild the reverser air
cylinder;
Make and fit the new steam
feed line to the air compressor;
Load and fit the brick arch;
Clean and refit the injector
starter valves;
Refit all the connections
between locomotive and tender;
… and numerous other little
tasks.
However, by Wednesday she was ready to switch out to the
steam service lead and load with coal and water. During this came the “ceremonial last task”. With the assistance of Dave Diamond operating
the boom truck, the dome cover was lifted into place.
On Thursday came the acid test. The fire was lit and steam raised. All the essential tests of critical equipment
such as safety valves, injectors and air compressor proved very
successful. Once the steam test was
completed a number of test runs, first light engine and then with train were
completed and we were satisfied that she was again operational.
Having now fired a couple of days it is clear that she is
significantly better than last year (after all the Winter work we would be
pretty disappointed if this were not the case!!). A number of nagging steam leaks are
gone. The work on the rear axle has
significantly reduced knocking that was apparent last year and the rod bearing
that tended to run warm is now cool despite having much less play than last
year. So a very successful outcome to
the Winter work program.
It is on Shay #5 that we have the biggest news. We can now clearly see our way to a second
operating steam locomotive in the near future.
She is currently a single unit again and at the North end
of the shop.
However the real achievements are not obvious.
Phil’s efforts over the last
couple of months have overcome the problem that has sidelined this locomotive
for many years. He successfully cleared
the tell-tale holes on all but 20 firebox stays. So all stays in the boiler are now fully
compliant with current FRA requirements and the 20 had all been removed for
replacement.
Additional thickness testing
was carried out on some parts of the boiler to ensure that we have all the data
to complete the form #4 and this indicates that all parts of the boiler and
firebox shell are suitable for normal operating pressure.
In the last week, with Brian
Davies (who leads this project) up from Florida, all 20 of the stays previously
removed were replaced. (This involves
re-tapping the firebox sheets and machining stays to fit each location). Good progress was also made on peening the
ends of a number of the new stays.
Work has also been
progressing on exact measurement of the tube sheet and tubes to identify
exactly what ferrules are required to fit around the tubes in both front and
rear tube sheets.
The remaining work on this locomotive is clearly defined
and not as big as it might appear. So when will we see her in steam?.
A lot of thought is going into this question at present.
The steam department at IRM has traditionally worked almost
entirely on a volunteer basis. Near
miracles have been achieved this way but it is slow. In practical terms a job that would take 2
men 10 days to complete in a traditional back shop would take us 2 months,
probably more once you consider that both guys may not be available every
weekend and there are inefficiencies in putting a job down and picking it up
again a week later.
In the last few months we have, to a limited extent, used
donated money to employ people on a part time basis to concentrate several days
a week on major jobs and this has allowed us to complete some tasks that had
previously been stalled.
So this is the big question being considered now. The work required to get #5 into steam is now
clearly defined:
Re-tube the boiler and hydro
test;
Fit (weld and rivet) the new
smokebox bottom sheets (inner and outer) and then fit the exhaust assembly into
the new steelwork;
Lag the boiler and fit the
sheet steel cladding;
Produce and fit a new front
beam and walkways;
…………. Plus the various minor
tasks to fit accessories and reconnect the drive mechanism.
Several aspects of this work are of the type that would take
months to do entirely with volunteer effort but a matter of weeks if we “bite
the bullet” and pay people to work full time on them.
On a purely volunteer basis, we should probably be able to
get her into service sometime next year.
If we have the funds to accelerate the key tasks, it could be a lot quicker.
So a lot rests on the level of interest. If you are in favor of accelerating the steaming
of Shay#5 by paying to get key work done quickly, consider a donation to the Shay
#5 fund. My own view is clear!. I will offer to match donations received
during June up to a total of $2,000.
Now we go into a few months of very different activity. There is a lot of work required each week to
address any minor maintenance on #1630 then fuel her and prepare for the next
operating session. In parallel with this
we hope to progress work on #5, the painting of #938 and various shop improvement
projects. But there is always the
contending attraction of taking time out to see #1630 running ……. and you can
hardly deny us that pleasure!.
Nigel