June and July are normally quiet months for project work in
the steam shop with many volunteers on vacation and the demands of operating
and maintaining #1630 taking the time of those who are available. A cursory look into the shop would suggest
2015 is no different. After the
insulation work, #428 and the Shay are now back in their familiar positions and
#938 is back at the North end to continue the cosmetic / evaluation work.
However, the cursory look would miss some radical
progress!!. Read on!.
#1630 has continued to run fairly well but with minor
issues that take a lot of time during the non-running weekends. On the crewing side three trainees )including me!) have now
qualified as firemen, which means that they can now operate with just one of
our qualified engineers, so reducing the demand on our small pool of
engineers. Unfortunately one engineer is
now largely unavailable due to external demands so we are still on the edge for
crew.
Mark got the Kohring crane
back into operation and has subsequently done most of the coaling. This makes it a much quicker and less
demanding operation than last year;
The new water softener
system seems to be a big improvement.
The daily production is much improved, in part due to a better flow rate
and also because it will regenerate immediately the required volume is reached
while the old one regenerated only at night;
At each “off” weekend we
deal with the minor issues noted by crews during the previous weeks but two
issues have proved “niggling” and have been addressed a couple of times.
The steam connection to the
fireman’s injector starter valve has proved very reluctant to seal completely
free of small leaks and will be reworked again this weekend; and
A small leak around the feed
to the fireman’s sight glass reappeared a couple of weeks after it was last
addressed and will be addressed again this weekend.
It all takes time and small groups of volunteers are to be
seen Saturdays and sometimes during the week dealing with issues such as these
as well as helping the crew with start-up and disposal activities. This is a big help as I can assure you that
the full day of grate cleaning, lighting up, ash pan cleaning, greasing, then
firing for the day before taking on water and shutting down is a VERY hard day’s
work, particularly when temperature and humidity are high!.
The new roof insulation in the South shop was completed and
the shop is back in use.
Sudden rapid progress on the new compressor shed, which is
a big development funded from the annual benefit at San Filippo, has been made in the last few weeks:
The concrete slab was laid
with the bolts to secure the large compressor set into it;
In the last week the
building itself has been erected and the old door replaced by a solid wall that
will significantly reduce heat loss in Winter;
The compressors were moved
to the West side door to allow easy pick up by the fork lift when they are
moved into their new location;
We now wait on the fitting
of the roller doors before we can start the insulation;
The pressure will be to get
everything operational before Winter. We
have some significant riveting in prospect and a key expectation of the new
compressor installation is that it will provide sufficient air to support
riveting without the need to use the Sullair (mobile compressor). This will be a big bonus as Winter is ideal
for a hot job like riveting but digging out the Sullair and starting it in
sub-zero temperatures can be “fun”.
Now to the huge progress
…….. Shay #5
On a walk around the shop
she really does not look any different but, look into the smokebox area and, she
is VERY different!. As discussed in the
last blog, there are huge benefits in daily working to move large projects
forward quickly.
Brian Davies, assisted by a
number of the younger volunteers as available on a day by day basis, worked
solidly for two weeks on the boiler. The
effects are remarkable:
The tube and flue holes in
both sheets were prepared (rough edges removed) and profiled;
Ferrules were expanded into
all the holes;
Both small tubes and super
heater flues were cut to length and installed in the tube sheets;
The ends of all tubes and
flues were expanded into the tube sheets;
Work is now progressing on
grinding excess material from the tube ends in preparation for beading.
So the Shay now has a fully tubed boiler and is being
worked towards hydrostatic testing!. We
now have some tasks, such as preparing all the tubes for beading and lapping the
various valves that are required to seal the boiler for hydro, that can efficiently be
carried out by weekend teams.
The tubing was much easier to carry out with the bottom of
the smokebox missing. However
subsequent work will be less affected by the smokebox bottom so the plan is
to pull the front truck out shortly and start fitting the new bottom of
the smokebox. This is actually a smaller
task than the tube fitting but will have a much greater impact on the
appearance of the locomotive.
The last couple of weeks have really confirmed our belief
in the importance of at least periods of full time work to progress a major
steam locomotive project. We attracted
some donations from the appeal last month (final information next month) that
will allow another intensive session later in the year. Having #5 running for 2016 now looks very
realistic if we can continue this way.
On #428 riveting of the cab has continued and this is now
well advanced.
Ed has worked steadily on the pipework including finding
old photographs to help in the complex task of identifying how the various
pipes were routed and what they did.
Really tricky when you start from a pile of pipes of different sizes
bent to follow complex paths but removed years ago by people no longer around ………… and the probability that
some are likely missing and a few from other locos may have been included in
the pile!. However, the cab pipework is
now substantially complete.
A big barrier on #428 will be the availability of
fabrication / welding time. Many hours
of skilled fabrication and welding are required to fit the new cab floor, build
up the axle boxes and rubbing plates on the wheels, etc. Over Winter this will still compete for time
with any work on #1630 and the Shay as that moves toward running condition.
On a side note, I was one of the volunteers missing for a
couple of weeks in June as I visited family in the UK. During that time I did a day of throttle pull
(called footplate experience over there) on the Severn Valley Railway near
Birmingham with my oldest son. They are
a very welcoming group with a whole organization around footplate experience
that is run frequently and includes time both driving and firing on a train running over a 15 mile line with
family / guests riding all day. Anyone
interested in steam throttle pull and recognizing the shortage of opportunities
here might well consider it if you visit the UK.
Amazing how different a steam engine can be in the
detail. We used a GWR Manor class 10
wheeler of 1930’s design.
Only just over half the power of #1630 but with 68 inch
wheels and easily able to accelerate a 6 car train to line speed on a heavily
graded line. Aside from the obvious
attention to appearance the amazing thing was the simplification and
standardization. Historically all
substantial overhaul work was done by major works that also designed and built the
locomotives. So even pipework is
common to all locomotives in a class and many of the parts, even to the extent
of the whole boiler, are interchangeable between classes. There is also a startling reduction in the amount of pipework when the boiler an fittings are all designed and made together. Generally one valve to control and shut off
each unit where we have multiple shut offs.
You get on the footplate and the immediate impression is “there’s
nothing here. Where are all the
controls?”.
Still a tremendous day highly recommended to anyone
visiting the UK.
So a lot of progress and hopefully a lot more to come.
Nigel