Saturday, November 26. 2011
Steam Department Update 11-26-2011 Posted by Nigel Bennett
in Steam Department at
23:00
Comments (0) Steam Department Update 11-26-2011This Saturday we had a surprisingly good turnout. Steam Department volunteers must have felt the need to work off the turkey. On 1630 work continued steadily. Collin and Phil worked on the firebox end tube plugs. Another 40 are out. The technique is now well developed but there is a limit to how long you can you can work at this. Since you have first to gas cut the tube end to a suitable length for removal the atmosphere in the confined space of the boiler when you use an acetylene cutting torch does become "a little warm". Still, the fireman's side is now largely clear. Mike and Bob removed the stays from the firebox corner. All the rivets and stays are now out so they are now working on cutting out the damaged corner plate. Not simple as the replacement tube sheet fitted in the 1930's was welded into place. A great deal of reorganization of the shop was achieved that will provide Dennis with a better area for welding, under lifting gear that can move and position heavy parts, as well as free the space in which we can both swage the fire tubes for 1630 and set up the rig to pressure test the super heater elements. The new fork lift enabled us to move the large timbers being seasoned for the Shay up onto racking so freeing a lot of floor space. The Shay saw considerable progress. A "A" frame outside the shop was broken down and reassembled over the truck - one of those jobs that sounds easy until you are trying to align bolt holes in the legs and beam, both of which are heavy enough to need 2 people to move!!. Anyway, we achieved it and then it was possible to lift the bolster off the truck. So now the springs that are to be replaced are free and clear. Small snag - the truck must also be examined for damage or cracks which means removing 50 years of hardened grease and muck. Meanwhile Rick was completing the cover over the vertical lathe to protect this during the winter. We were also able to progress a number of machining tasks. Thanks everyone for a very productive day's work Nigel Sunday, November 20. 2011
Steam Department Update 11-19-2011 Posted by Nigel Bennett
in Steam Department at
08:27
Comments (0) Steam Department Update 11-19-2011Two good weekends of progress since the last update. While I was not at Union on 11/14 at least I had a chance to see working steam. This is a 1934 Stanier mogul built by the UK London Midland & Scottish Railway in the UK and one of 2 locomotives running 11/14 on the Severn Valley Railway. A very interesting comparison to our #26. She looks a lot smaller but this is actually due to the height restriction (12ft 6in vs 14ft). Actually she has a slightly greater tractive effort despite bigger wheels and a fairly advanced superheated boiler for a substantially better continuous horsepower. On 1630 we are now hopefully reaching the end of the "destructive" phase. Eric, Collin and Jason have established a good technique for knocking out the ends of both the small tubes and now the larger superheater flues. The large ones were really tough as the metal is thicker so hammering on its own does not collapse them. Careful grinding is needed to weaken the ring before hammering will work. Great care is needed to avoid damage to the tubesheets. Anyway, they have the process refined to the point that the ends are popping out fast now. The front tubesheet is now clear of all cut ends, large and small, while a substantial number of both types were removed from the back sheet yesterday - no photographs of the back tubesheet, your scribe was too stiff and lacking in dedication to crawl into the firebox with a camera at the end of day!!. Interesting to compare the view now with that a few weeks ago. All the ends are now gone. A small number of flues and smaller tubes can be seen still in place in the center. It is hoped that the inspection can be completed without removing these. Every one of these was hammered out by the guys using an air hammer inside the boiler ... and this is by no means all of them as the pile would have blocked the lower holes. Brian did a great job cleaning off the last of the rust and insulation from the back head so we are now ready to start the thickness testing. Just to remind ourselves what has been achieved. This is the same area as it was (and what we have to reconstruct !!) and after removing the cladding and insulation. Mike, Bob, Ralph and others have continued the painful process of driving out the rivets to allow the firebox corner patch to be fitted. They are now working on the last one. Bet they are going to be real dissappointed when there are no more of these to do !!. Cameron and Brian did a difficult but essential job that had become urgent. With winter approaching it is essential that there is no water in the super heater elements now stored in the box car that could freeze and crack the element. The shape of these elements (16 feet long with each tube bent to make 4 passes along this length) makes it very difficult to get water out. So each one had to be man handled and blown thru with compressed air. Good job guys! We are now starting to set up tasks to prepare for the reassembly. The actual assembly is some way out but we want to ensure that parts are ready ahead of time where we can. One major job is "swaging" (shrinking the diameter) of the new tubes at the firebox end ready to fit when we start to retube the boiler. This means setting up a production area where the ends of 200+ tubes can be heated to red heat then quickly put into the swager where a compressed air cylinder shrinks the end of the tube against a die to the correct size. Substantial progress has been made in clearing the area at the South end of the shop for the swager and furnace to be mounted in the next couple of weeks. The pallets are ready for Jeff to move out to the boxcar on Sunday and then we can think about setting up the swager. Hopefully before too long we can demonstrate what this does!. There has also been major progress on the Shay. Last weekend Tom and the team achieved what has been the target for quite some time, jacked the front of the loco and pulled out the truck. So yesterday it stood with a large gap where the front truck fits. The truck now sits in front of the locomotive and work has now started on cleaning it to allow the bolster to be removed and the springs to be accessed. This gives a good idea of how the Shay is constructed. The front of the locomotive sits only on the bearing in the "cup" that can be seen in the middle of the bolster at center of the truck. The weight is transfered from the bolster to the frame and wheels by the springs that are currently hidden under the bolster. Altogether a good couple of weeks progress. Nigel Saturday, November 5. 2011Steam Department Update 11-5-2011This will teach me to send in information!. Think I drowned Bob in input for a couple of weeks so now I have to do it myself. Probably very fair and thank you Bob for loading my last two efforts. I don't think I have the ability to load pictures yet so this one will be text only. Lots of activity today though much of it was not directly on 1630 but rather taking advantage of the great weather to get set up for productive work when the weather is not so favorable. On 1630 itself:
Major activities during the winter will be cleaning and testing the superheater elements and swaging the new tubes (heating and compressing the ends of the tube so that it can be fitted into the tubeplate) to prepare for this:
In other areas:
So a lot of progress in a number of areas. No update from me next week as I have to go to the UK on business. |
Blog AdministrationCategory TreeCalendar
QuicksearchSyndicate This Blog |
|||||||||||||||||||||||||||||||||||||||||||||||||
Powered by s9y.
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...