It was another day of progress in the steam shop. As mentioned last week, the objective is quite a few weeks of "more of the same".
The focus was on re-tubing 1630 and this week saw steady progress:
· a further bale of 37 new tubes was brought into the shop. This means that more than half the total (about 170) are now in the shop;
· Jerry had cleaned off the swaged ends on the batch that were swaged last week. These were annealed at the other end and moved up to the locomotive;
· 28 tubes from the new bale were swaged. This takes us to about 45% of the total swaged. At least this now seems to be a "production" process. We were doing one every 2 -2 1/2 minutes yesterday. The limitation is space. It is not safe to stack a whole bale (37 tubes) on the "hot" side. 28 was found to be about the safe maximum;
Here you can see the actual swaging operation as the red hot end of a tube is hammered between the jaws
· Ed continued work on the ferrules by cleaning the rough edges on those that are cut. He also confirmed with the electric car shop that they have an operational annealing oven that is suitable. So next weekend he will aim to anneal the ferrules so that we have a large supply ready for installation;
· Master tubes were cut to each of 5 standard lengths and the inside boiler team (Eric and Collin) test fitted these to the boiler. The results were good. Each tube provides the required projection at front and rear when fitted to holes identified for that color;
· Later in the day the master tubes were used to cut the first 10 tubes ready for fitting.
For those of you visiting the shop there is now a clear progression. New tubes are brought in at the South end, swaged and annealed. Once this is done they move up to a stack on the engineer's side of the locomotive. From here they are taken to the chop saw, cut to one of the standard lengths and then stacked on the fireman's side. From here they will be lifted into the boiler and placed in the tube sheets.
On the patch we encountered a, hopefully minor, set-back. When fitting the new plate it became clear that two additional rivets will be too close to the weld line and so will have to be removed and refitted. With the 11 that are already out, this will bring to 13 the number that have to be replaced and refitted. A nuisance as these 7/8th rivets are tricky beasts and require a good deal of work to get out.
In other areas
· the new air tank was fitted with plugs and connections so that it is now water tight. A pressure gauge was fitted and it was filled with water. This will allow the water that we need to hydro-test it to warm up in the shop during the week and also serve as a reservoir when testing the super heater flues. (Hydro tests need to be done with warm water).
· good progress was made on cleaning out the valve block for the planer. This has now been freed of gunge and the valve passages polished.
I am leaving tonight for a 10 day business trip to the UK so will not be at the shop next Saturday. So there will not be an update next weekend.
Nigel
This time I am not so tardy as usual with posting the late news for the Russell snow plow project. But to start out this report we want to welcome two long time IRM volunteers - they reported today to help on the plow project and join the fine restoration team we have already.
Cheryl and Bob Kutella started the mortises on the drill press.
Let me introduce Cheryl Lint. She has helped a lot in the Strahorn Library and especially with our annual vintage transport event. Today she was in the wood shop and I recruited her to assist on the framing for the last window opening on the plow, the one boarded up on the south wall. We cut and planed timber for the framing, and then proceeded to drilling and mortising to put the four pieces of the frame together. In no time at all they were all drilled out and Cheryl was handling a paring chisel like a pro, chopping them out square and smooth. Thanks, Cheryl, you are welcome back anytime!
Wally Unglaub came down from Milwaukee and also helped on the CGW X 38 project. He started out removing paint from the replacement headlight casting.
And them Wally moved on to prime paint some new pieces of interior lining and trim for the plow. Thanks go to you also, Wally.
I know, this is a terrible picture, but no matter where I stood the sun was almost directly into the lens. Last week I said the north door was to be closed up, and here, Jim Leonard has finished that task. Ready for winter, now.
Our trustworthy Ray Pollice was on hand and worked on paint removal on the front end and bottom edge of the plow wedge.
Inside the box, Jim Leonard continues the sometimes tricky installation of more of the tongue and groove lining. You can see three dots left of the window. These are mounting bolts and a conduit entry for the telephone communication lines to the pusher locomotive. That is one of the reasons we are putting all the lining in the back wall - so we can finish up more of the back wall exterior.
On the outside you see here the telephone jack receptacle mounted properly for the first time at IRM. In many of the preceeding month's BLOGs you have seen this mystery object loose and dangling.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]