Sunday, February 17. 2013
Steam Department Update 02-16-2013 Posted by Nigel Bennett
in Steam Department at
12:33
Comments (5) Steam Department Update 02-16-2013It was a productive day at the steam shop although the weather was rather unkind, given our priorities. On 1630 the whole focus was upon continuing the fitting of fire tubes. As noted last week, our first priority was on trying to make the smaller air motor work with sufficient power to drive the tube rollers and so avoid trying to handle to the large motor in confined spaces. Moving the Sullair to the North end and rigging a holding reservoir to assure minimal pressure drop as the motor works should have been simple. It took Phil and me rather longer with a few challenges such as melting the wheels out of huge blocks of ice that had frozen it to the ground !. However, Glenn's good work over the summer paid off. The compressor starts well even at 15 degrees. The effort was a success. The smaller air motor with this enhanced air supply will successfully drive both the straight and flaring tube rollers. This unimpressive looking reservoir, close to the locomotive, proves invaluable in maintaining pressure as the tube is rolled. The results were impressive. We were able to both largely complete expanding the tubes in the firebox and reach about 25% completion of rolling at the smokebox end.
We now have just two tubes in the main area to refit. We decided to expand all tubes before addressing the ones where the ferrule "popped" during expansion. Only one did so this week. So we have that and the one from last week to refit before we have all fitted (aside from those between the super heater flues). Rolling the tube ends is now a rapid process but is driven by preparation for the next step, which is flaring those tubes that are to be beaded after the first hydro test. These need to be fairly accurate to 1/4 inch projection at each end and the flaring is more effective if the length is adjusted before this is done. So, next week, a number of tubes that have excess length will need to be cut back to 1/4 inch with the angle grinder before flaring. This was expected. The tube sheets are not flat so each tube length is unique and must not provide less than the required projection, so you cannot hope to get each tube correct to 1/16th as they are fitted. Here you can see some of the tubes (for example the two just left of the lowest super heater flue) that project further and will need to be trimmed before flaring. Hopefully in the coming weeks we can get two teams working. Once the smokebox end of a tube is rolled, the firebox end can be flared. So it should be possible to have teams working in both firebox and smokebox at the same time. The developing number of tubes with blue paint marks is an indication of substantial progress In other areas: · The move of the McCabe was completed. This location will allow it to be used without further movement but keeps it out of the way. · Jeff managed to get the scissor lift moved to the shop despite the icy conditions. This will allow work to start next week on installing the new air system into the South shop. A demonstration ride on the lift provided a rare opportunity for a look at work in the shop from above. Looking the length of the shop, Jerry is relocating material to make way for the McCabe and, at the far end, work continues rolling tubes into 1630. Looking toward the West wall, the team is working on the shaper. · Stu and Mike worked on reassembly of the planer. Sorting out how the levers should link to the hydraulic control block appears to be a challenge judging by Stu's expression! So, overall another week of good progress. Nigel Friday, February 15. 2013Wood Shop Update - February 13, 2013I suppose many of my regular readers here are wondering where the report for this week is. I will try to explain. Departing from the usual format, the commercial comes first. I have spent a substantial number of hours this week, going over donation reports and constructing our own ledger sheets. Other departments are doing the same. GOOD NEWS! It is looking from our unofficial tallies that we are very close to reaching the funding goals for Barn 14. That does not mean the donations should stop. To my knowledge no single piece of equipment has its own restricted fund balance high enough to pay its own way in 100%. But each department realizes the importance of this opportunity and other funds can legitimately be applied to the project to reach full funding. There have been unspecified donations to the project and in the past the Board of Directors has 'shared' that out to five departments. Each department has received donations for indoor space for their equipment and that may be applied to one or more cars under their umbrella. And finally, each department has other donations not specifically for one car or project. That may also be partitioned to get the most cars inside the quickest. The final thing to mention is we are working to an estimated cost of the project, and we should not be surprised if the bids come in and the total rises marginally. I would consider a good, really good, estimate to be within 5%. So you all have the chance to continue your remarkable support of any particular car or locomotive, any particular department fund, and know it will yield results soon. For the rest of us, we are anxiously awaiting the confirmation from our Financial Department that our unofficial numbers are accurate. On to the news. I always like to start the reports with progress on the Chicago Great Western X38 snowplow. Why not? It is my department project and my team. Here, Dave Rogan is trimming just a whisker of thickness from a door stile tenon. Our motto is you can always take more off but not moron. Hmm, that did not come out quite right, but I am giddy with the prospect of the Barn. Dave, Jim Leonard and Rich Witt are assembling and fitting the parts together for the second new X38 door. The first door fitting is complete and it was assembled and put into the press after gluing. This view shows Victor Humphreys and John Faulhaber with a pile of new lumber on the cart. It has just gone through the planer and is destined to become many feet of tongue and groove millwork for the new roof on Michigan Electric 28. The wide lumber is ripped to two inch wide slats before being ready for the shaper to do the T&G milling. These are LOOONG boards and a dedicated crew of five ran them through the table saw at the rate of one cut every fifteen seconds or so. Seen above are Victor, Buzz Morisette, Jim Leonard, Jeff Brady, and Dave Diaz. Dave Diaz also painted a whole slew (is that the technical term?) of window post caps for Cleveland Transit System 4223. Henry Vincent is at the small band saw trimming tenons on a new bottom rail for the door work on Chicago Aurora & Elgin 36. That is the sequence on any wood work project, perhaps more so when you are patching in new wood for a repair, such as this work for CA&E 36. Henry is touching up the thickness by hand sanding as he fits, and then perfects the fit. We continue to move ahead on two new windows for Boston & Maine 1094. Here, Rich Witt is working on a masonite template for the top shape of these windows. It will be critical to using that to guide two routing operations, establishing the needed cross sections. Buzz has a good eye and a careful hand and this final version of the template is being checked by Rich. Smooth! Gerry Detloff is applying the first piece of new tongue and groove wood slats to the roof of Lake Shore Electric 810. We made those only a few short weeks ago and despite the cold temperatures, Gerry was out in the barn nailing them on. And as usual a lot of other work went on. One that comes to mind was making a new wood piece for the awning on the Frisco Decapod in the Steam Shop.
Sunday, February 10. 2013
Steam Department Update 02-09-2013 Posted by Nigel Bennett
in Steam Department at
13:52
Comments (2) Steam Department Update 02-09-2013While it was a part day in the shop for me, as I attended the Board meeting in the morning on behalf of the department, a larger team braved the snow and ice and good progress was made in a number of areas. On 1630: · the first of the cladding sheets, as well as a number of cab fittings were brought down from storage above the machine shop for inspection, cleaning and painting. There is a great deal of this to be done in preparation for the time when we will be able to start refitting them. Much of this is an unpleasant, dirty job as the sheet metal must be wire brushed to get rid of rust and bits of lagging. However there is now an area set up to allow cladding sheets and other parts to be painted and allowed to dry (at the opposite end of the shop from the dust generated by the cleaning process!).
Above are some of the first results including sections of the cladding, that make up the covering of the boiler backhead in the cab, and the mounting plate for the pressure gauges. · on the tube fitting there was significant progress, more in the areas of developing processes for the next steps than in fitting large numbers of tubes. o While I was at the meeting, Collin and the guys completed removal of the rogue tube from last Saturday and put a new one in. o The new roller has arrived and we spent a good deal of time working out how best to use it. This roller is designed to both expand the end of the tube and simultaneously flare the projecting end of the tube, ready for beading. We used this to start work on the smokebox tube ends. The size of this roller should allow it to be used on both the firebox ends and those tubes at the smokebox end that require beading. Because it is a great deal easier to work in the smokebox we decided to work out how best to use it on smokebox tube ends. This proved to be a very good decision. It certainly does expand and flare the tube ends quickly and effectively. Once in place and properly driven, the process is complete in maybe 30 seconds. The snag that became obvious was that the additional force required to turn this roller, as it not only expands the tube but flares the ends at the same time, is more than our smaller air motor can provide. This is a significant issue. The smaller air motor weighs about 30 pounds and can be reasonably controlled by one person. The bigger one drives the expander with no problem but weigh 50 pounds or more. Manually supporting and locating this beast on to the expander for every hole, which we can easily do with the small motor, is pretty exhausting work for two people, as Phil and I found out. Some more development is required. While we certainly could expand the smokebox ends this way it would be slow. The operators require frequent breaks!!. Next week we will need to explore other options. We probably need to find ways of supporting the motor in places from which we can drive the expansion of multiple tubes using the flexible drive shaft, rather than attaching the motor directly to the expander and therefore carrying the full weight of the motor to every tube end. Clearly we need to develop methods that can also be used in the firebox. ... If the big motor is tough to handle in the smokebox it will be a nightmare in the firebox with the arch tubes in the way!. o Despite this we successfully expanded a number of smokebox ends. I have changed the progress measures to reflect the way we now expect to work. At the smokebox end only some tubes need to be flared (those that will subsequently be beaded) and we will do this simply by using a different roller for the expansion. So this weekend we actually flared 7 and left 4 un-flared as they will not be beaded. However in all cases this did all that we need to do to the tube before the first hydro test. At the firebox end, flaring will be a separate step. Beading will not be done at either end until after the first hydro test (so that any leakage can be corrected by additional rolling). Here you can see the results on the tubes directly below the super heater flues from column P and to the right where the ends are now flared when compared to the raw tube ends in the rows below. o At the firebox end we continued to fully seal tubes that were previously set into place. Unfortunately we still hit an occasional one that shoots out the ferrule in this process and needs to be replaced. This seems to happen with those tubes that were originally set with the roller rather than they expander. At least we are now largely thru the ones that were set in this way. · The sight feed lubricator was located and Jerry started work on cleaning and checking this essential component. · The ring spacer required for the one super heater flues with an extra large hole was completed ready for refitting of the super heater flues. In other areas: · Jerry and Mike made good progress on clearing the shelving at the South West corner of the shop to make an area against the wall to store the McCabe flanger. This will be a major improvement. The flanger is, on occasions, a critical machine and had a major role in producing the patch. However, between those occasions, it a huge lump of metal that cannot readily be moved any great distance and takes up a lot of useful space!!. So the objective is to provide a storage space against the wall to free up useful space in the fabrication area when it is not required. It would be really nice if we could store it out of the shop in a container. However, it is so heavy that only the large Buildings and Grounds forklift can handle it .......... and that does not fit thru the doors of the shop! · Mike started on rebuilding the air pump for #428. He has been doing a lot of research on the cross compound air pumps and will look after all of them. He also checked out the valves on 1630's pump which looks to be in good shape after the work done a couple of years back. · Tom continued with machining the shoes and wedges for 428. Above shows one of the shoes that will position the axle boxes in the frame. These are new iron castings as the originals were worn beyond repair. Each must be planed to exact dimensions to enable the eventual refitting of the axles. A slow and tedious process as each axle box requires one shoe and one wedge. So, overall another week of good progress. Nigel |
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]