Sunday, May 31. 2015Steam Department Update May 2015
http://www.irm.org/events/steamdeptbenefit.html What a difference a month can make in the Steam shop. The South end of the shop now presents a remarkable sight, wide open in a way that has not been seen in many years.
This is driven by a Buildings & Grounds project to install sprayed insulation on the roof. The shop is one of the few heated buildings in the museum and cutting wastage of heat is a high priority. The existing panel insulation has been prone to detach and this project is to some extent an evaluation of a new method to insulate the type of structure used widely in the museum. Anyway, the contractors start the first week of June and need clear access to the South shop. This has driven and been enabled by some substantial activity on our projects.
First and foremost was #1630. By the end of May, she was routinely located outside in the preparation area, coaled, watered, greased and ready for another weekend of operation.
The shine on the paintwork in this picture is no good things as far as I was concerned!. It indicates frequent heavy rain while I was doing the preparation. Clearing the firebox and laying a half ton base of coal for lighting up can be less than fun with 100% humidity and periods of heavy rain!. For anyone wondering what is the strange curved object attached to the walkway and standing well above the top of the boiler, this is the hoist that we use to lift the fan onto the chimney. So this is a clear indication that she is ready to fire and awaiting installation of the fan early the next morning.
Still she ran well again on Saturday despite frequent rain, rapidly falling temperatures and winds developing to near gale force as the day progressed. Sadly not too many visitors to see it!. Those who braved the weather were rewarded with some spectacular sights of steam trailing across the corn fields.
With #1630 gone from the shop, other big changes were possible. Shay #5 was linked to its tender again, albeit temporarily and this allowed her and #428 to be moved North into the main and North buildings. So, aside from a big house cleaning, what was achieved in May?.
Obviously the work early in the month focused on #1630. In recent years May has become a month of frenetic activity as we prepare for operation and so it was this year. Many people took days off work and there was activity in the shop several days each week as we worked thru the list of tasks to get 1630 into operation.
As was strongly suspected last month, it proved impossible to be ready for operation May 16th/17th. However steam testing was completed May 21st and a full weekend of operation was achieved for the 3 day Memorial Day weekend and we are running the weekend of May 30/31st as a substitute for the 16/17th. Given the weather this may not been seen by many visitors!!. Oh well, some you win!.
It is startling how much faster things can move when we can have teams working several days each week. In the first two weeks of May:
Dennis finished a great deal of welding including:
building up the mounting for the tender draft gear;
welding new plate into the bottom of the tender to provide a solid surface for shoveling;
straightened the tender footplate on the engineer’s side. This had a strange “hump” dating back decades to some unknown accident damage and now provides a level surface for the first time in memory;
attached the tear drops to the grate shakers.
Phil spent a lot of hours in the cramped space under the ash pan, assisted by a number of others working outside, to reinstall and adjust the wedges on #5 axle.
On the first weekend of May, the major task of refitting the draft gear into the packet under the tender was achieved. This took a lot of brainstorming. The challenge was how to lift this unwieldy assembly (several hundred pounds and nearly 3 feet long) into a narrow space under the tender and above the axle. It is being above the axle that really provided the challenge. The draft gear must be raised into the pocket. It cannot slide in from the rear. However the depth of the draft gear draft gear is such that it barely fits above the axle and below the pocket. So the whole tender must be jacked up by the thickness of anything put under the draft gear to support it on the fork lift.
The eventual solution was to balance the assembly with as much projection beyond the forks as possible. It was then secured with a bar below the forks and steel banding around the assembly. Here JD and Trevor work on this mounting.
It looked precarious but the acid test (large volunteer jumps up and down on the projecting end!) proved that it was solid. This way only the thin tips of the forks had to fit above the axle. With this set up the fitting went relatively smoothly and the tender was again complete with a coupler and ready to push forward onto the locomotive. Once it is back in place, it is difficult to visualize all the effort that has gone into making it look so normal!. JD then completed the operation over the next few days with a couple of heavy contacts when coupling to break the wood blocks in the draft gear and release the spring mechanism to its normal operation.
In the second week the footplate welding as completed, the tender pushed forward to the locomotive and the drawbars fitted to make her a single unit again. With this done, she was moved to allow the fitting of the coupling rod on the fireman’s side and she was again mechanically complete.
Around these major activities, a lot of other people were working to:
Rebuild the reverser air cylinder;
Make and fit the new steam feed line to the air compressor;
Load and fit the brick arch;
Clean and refit the injector starter valves;
Refit all the connections between locomotive and tender;
… and numerous other little tasks.
However, by Wednesday she was ready to switch out to the steam service lead and load with coal and water. During this came the “ceremonial last task”. With the assistance of Dave Diamond operating the boom truck, the dome cover was lifted into place.
On Thursday came the acid test. The fire was lit and steam raised. All the essential tests of critical equipment such as safety valves, injectors and air compressor proved very successful. Once the steam test was completed a number of test runs, first light engine and then with train were completed and we were satisfied that she was again operational.
Having now fired a couple of days it is clear that she is significantly better than last year (after all the Winter work we would be pretty disappointed if this were not the case!!). A number of nagging steam leaks are gone. The work on the rear axle has significantly reduced knocking that was apparent last year and the rod bearing that tended to run warm is now cool despite having much less play than last year. So a very successful outcome to the Winter work program.
It is on Shay #5 that we have the biggest news. We can now clearly see our way to a second operating steam locomotive in the near future.
She is currently a single unit again and at the North end of the shop.
However the real achievements are not obvious.
Phil’s efforts over the last couple of months have overcome the problem that has sidelined this locomotive for many years. He successfully cleared the tell-tale holes on all but 20 firebox stays. So all stays in the boiler are now fully compliant with current FRA requirements and the 20 had all been removed for replacement.
Additional thickness testing was carried out on some parts of the boiler to ensure that we have all the data to complete the form #4 and this indicates that all parts of the boiler and firebox shell are suitable for normal operating pressure.
In the last week, with Brian Davies (who leads this project) up from Florida, all 20 of the stays previously removed were replaced. (This involves re-tapping the firebox sheets and machining stays to fit each location). Good progress was also made on peening the ends of a number of the new stays.
Work has also been progressing on exact measurement of the tube sheet and tubes to identify exactly what ferrules are required to fit around the tubes in both front and rear tube sheets.
The remaining work on this locomotive is clearly defined and not as big as it might appear. So when will we see her in steam?. A lot of thought is going into this question at present.
The steam department at IRM has traditionally worked almost entirely on a volunteer basis. Near miracles have been achieved this way but it is slow. In practical terms a job that would take 2 men 10 days to complete in a traditional back shop would take us 2 months, probably more once you consider that both guys may not be available every weekend and there are inefficiencies in putting a job down and picking it up again a week later.
In the last few months we have, to a limited extent, used donated money to employ people on a part time basis to concentrate several days a week on major jobs and this has allowed us to complete some tasks that had previously been stalled.
So this is the big question being considered now. The work required to get #5 into steam is now clearly defined:
Re-tube the boiler and hydro test;
Fit (weld and rivet) the new smokebox bottom sheets (inner and outer) and then fit the exhaust assembly into the new steelwork;
Lag the boiler and fit the sheet steel cladding;
Produce and fit a new front beam and walkways;
…………. Plus the various minor tasks to fit accessories and reconnect the drive mechanism.
Several aspects of this work are of the type that would take months to do entirely with volunteer effort but a matter of weeks if we “bite the bullet” and pay people to work full time on them.
On a purely volunteer basis, we should probably be able to get her into service sometime next year. If we have the funds to accelerate the key tasks, it could be a lot quicker.
So a lot rests on the level of interest. If you are in favor of accelerating the steaming of Shay#5 by paying to get key work done quickly, consider a donation to the Shay #5 fund. My own view is clear!. I will offer to match donations received during June up to a total of $2,000.
Now we go into a few months of very different activity. There is a lot of work required each week to address any minor maintenance on #1630 then fuel her and prepare for the next operating session. In parallel with this we hope to progress work on #5, the painting of #938 and various shop improvement projects. But there is always the contending attraction of taking time out to see #1630 running ……. and you can hardly deny us that pleasure!. Nigel
|
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]