Tuesday, April 22. 2014
Steam Department Update 04-19-2014 Posted by Nigel Bennett
in Steam Department at
21:03
Comments (2) Steam Department Update 04-19-2014
Another short blog this week and some nervousness!.
Despite significant progress this weekend, the key activity of spraying #1630 was not undertaken. This means that the timetable for planned first steaming on the 17th May is now tight.
The painter identified a number of areas where the preparation was not sufficient and there was furious activity on Saturday to ensure that all the additional rubbing down, screwing down of sheet metal and masking made us ready to paint next weekend. This was done and we now wait with great anticipation for next Saturday!.
Aside from the preparation for spray painting, good progress was made in other areas:
The steel work for the spark arrestor was fitted into the smokebox. It now fits and the welding to the smokebox sides can now be carried out. The sheet metal may need to come out one more time for final adjustment but we are on the final leg. There was much muttering and cursing about the weight of the new steel that has to be hauled around and carefully positioned in the enclosed space of the smokebox. It is a LOT heavier than the old steel work …….. which was 50% corroded away in many places!!.
Christian and Jason did most of the steel fitting. Christian is actually taking a break in this shot. The main work requires crawling up behind the new sheet metal to fit bolts into the assembly from high up and behind the platework.
Stu, Ed and a team successfully recommissioned the water supply. This is critical as we must move forward to hydro test as quickly as we can once the paint is applied.
Jim rubbed down the bell mount and headlight on Saturday then painted them on Sunday.
The connectors were successfully removed from the ends of the old (and seriously corroded) steam supply pipe to the air pump. This was a job with considerable concerns as the connector at one end is a very old and unusual type. Separating it, so that it can be repaired and reused on the new pipe that has been professionally formed to the correct series of bends, is essential. There was a significant exposure had this connector been damaged during removal. However, Tom and Dennis, with careful use of the “blue wrench”, separated it without damage. This will actually allow it to be considerably improved as long standing damage can now be corrected by building up and turning the connector in the lathe.
So. Good progress in several key areas. However, the road to operation will not be open until the spraying is complete. Then one helluva lot of jobs will need to be carried out quickly. My fingers are crossed!.
On a different note – Time to start making plans for this year’s Steam Department Benefit at Sanfilippo. This year's benefit event will take place on Sunday, June 29. There will be door prizes, as well as a 50/50 raffle during the benefit event. Time to tour the magnificent Sanfilippo collection, a concert on the Wurlitzer Theatre Pipe Organ, and a silent film accompanied live will once again be a part of the benefit event. New this year will be a special raffle for a CAB RIDE ON 1630! This will be the only chances to ride in the cab of the restored steam engine!
Tickets (same price as last year, $69.99 per person) are now on sale and can be obtained by going to www.irm.org or by calling the Illinois Railway Museum at (815) 923-4391.
We thank you for your past support in attending a previous benefit event at the Sanfilippo Estate, and look forward to seeing you again this year!
Nigel
Tuesday, April 15. 2014
Steam Department Update 04-12-2014 Posted by Nigel Bennett
in Steam Department at
10:30
Comments (0) Steam Department Update 04-12-2014
A short blog today. It was, as expected, a weekend with rather limited activity in the steam shop. The need for many people to attend the rules briefing, tests and safety meeting in preparation for running this year meant that a lot of us were not available to work in the shop. Then the Museum Annual General Meeting in the evening occupied many of us later in the day. The outcome of that meeting leaves me with a substantially greater commitment and means that I must be more circumspect in my musings in future blogs. My thanks to those who voted for me and I hope that I can deliver on expectations.
Anyway, in the shop, we overcame a minor setback and prepared for the critical spray painting of #1630, which we now expect to get under way next weekend.
The setback was on the smokebox of #1630. Collin and Jason worked on fitting the sheet metal and mesh that will form the spark arrestor. This is now close to ready for welding into place after some minor adjustments. However, last week we had resolved the issue of leaks around the smokebox front ring and believed that we had thereby avoided the need to remove the smoke box front. Unfortunately Dennis found that it was not possible to complete the welding of the steel and mesh of the new spark arrestor with the smoke box front ring in place. It was therefore necessary to remove this after all.
The big concern was that this has not been achieved before without use of the boom truck and consequent need to pull the loco out of the shop. This would have been “very bad news” as she is all taped up and ready to spray. However a method was developed, based upon fabricating a bracket that could be attached to the bolts which normally attach the bell bracket. This allowed the ring to be lifted in the shop using the fork lift.
The team on Saturday removed the door and fabricated the bracket for lifting the ring.
A group including Phil, Christian, Jeff and myself carried out the lift of the ring on Sunday so there is now clear access for then spark arrestor to be fitted.
Activity next weekend is centered around spray painting the locomotive. This will restrict activity in the shop, so we expect to be working on activity outside the shop such as activating the water supply in the box car.
Nigel
Sunday, April 6. 2014
Steam Department Update 04-05-2014 Posted by Nigel Bennett
in Steam Department at
17:53
Comments (12) Steam Department Update 04-05-2014
Back to Union after a couple of weeks in the UK. Lots of progress in the last two weeks and a hectic day on Saturday. The site looks very different with the snow gone and a frenzy of activity leading up to opening day. It is not normally this bad but the weather delays mean that work normally done in February and March has been concentrated into just a few weeks.
Frank and the track team, with assistance from the scouts camping on site, were hard at work on the track of the steam lead. This has proved to be a nightmare. The section of track in front of the service box car was very poor and was lifted in December to set new ties. Unfortunately the area was then covered by snow and has only just re-appeared!. On Saturday the new track was laid and we now have excellent track in the area where we will service 1630. This overcomes concern that, after all the work in the last couple of years, she could have fallen thru the track in her service area. Many thanks to Frank and his team.
(Thanks to David for the above pictures)
Unfortunately this is not the end of the job. We have only recently become aware that the big T&NO 2-10-2 (#975) rode up on the switch between the steam lead and the car line when being moved for the Transformers filming. Substantial work is required to repair this switch over the next few weeks and we will work with Frank’s team on this. However, we may need water for testing before this is done and the water car was stuck in the yard behind the damaged switch. So a very careful piece of switching was done under Frank’s supervision to pull the water cars out over the partially repaired switch with the BrownHoist. All went smoothly and we now have the water cars by the shop and can get water when required.
Another interesting exercise followed!. The damage highlighted the next major question. Why did #975 cause such damage when moved?. She was moved at short notice and without steam department staff present so we did not see the event. After an hour with a lot of oil and much shunting of #975 back and forth on the “Y” with the BrownHoist we think the problem is identified and resolved. Absent lubrication, the bearing plates of the trailing truck were not moving. After applying a lot of oil and pushing slowly in and out of the curve, there was an loud bang and the truck started moving from side to side again. More oil and a few more trips back and forth into the curve and she slides smoothly from side to side. A big 2-10-2 will never be happy on the curves around our site … but if lack of lubrication before movement turns it into a 2-12-0 !!!.
(Oh well. I have just heard from Jamie that we investigated the wrong locomotive. It was #2707 not #975 that damaged the switch. At least #975 is now well lubricated!.) Back in the shop the main effort was focused on preparing 1630 for spraying of the cab and boiler. A lot of different tasks were progressing in parallel.
Jim and Rick were filling and sanding areas of the cab side. In the past two weeks, Dennis has done a lot of weld repairs to the cab sides and these are now being finally prepared for spraying. While I was away, the decision was taken to remove and repaint the lettering, as it was proving too difficult to preserve the existing letters. So the cab sides are now completely stripped and stencils are being prepared.
Eric and many others worked on sanding down and masking the superstructure of the locomotive. The smokebox is now sheeted to protect it from over spray. All brass pipes and fittings, that are not to be sprayed, have been either removed or protected.
The injector starter valves were removed from the sides of the firebox, as these were too large and tricky to spray around.
The cab front windows are masked. Now we are ready for the painter to review readiness to actually do the spraying.
Jason, Collin and others worked on the smokebox front. Some leaks were detected in this during the November test runs. We had considered removing the front sheet and fitting a thicker gasket. However, the team identified that the leaks were clearly identifiable to a small number of specific areas, visible when Collin was shut in the darkness of the smoke box and lights were held on the outside!. These were sealed with a high temperature sealant. So this issue should now be resolved without the need to lift off the smokebox front again.
One of the large areas that has been completed while I was away is the top of the tender. This is not an area usually seen by the public, but it sure looks good despite a couple of Nigel’s dusty boot prints!.
Aside from 1630 most of the effort was focused on the switching to bring the water cars to the shop and resolve the issue with #975. However, in the shop:
Tom was working on the adjustments to the planer. It has actually been set up to start some work (the axle box for a leading truck). However it is not currently advancing the cutter horizontally or vertically between cutting strokes as it should. So work is progressing to work out why this is and how to correct it.
I worked with Collin and Bob on the new house air compressor. We now have most of the parts in hand for this and will plan to activated it soon.
While the trip to the UK was largely for a family visit, I was able to fit in a couple of visits to UK railways.
At the Bluebell Railway in Sussex I was warmly welcomed by a couple of the teams building largely new steam engines. The 84030 team are building a replica of an extinct class of BR 2-6-2T locomotive from parts of a similar 2-6-0 while the Atlantic team are building a replica of a 1911 LBSCR 4-4-2 using a boiler that survived in industrial use. In the latter project much of the rolling chassis is now complete. The new axle boxes and wheel make an interesting comparison to our efforts with #428.
The cylinders have been fabricated and are in place on the frames.
High quality work is obvious on the Bluebell in the wood working as well as the locomotives. These are shots of a superb set of late 19th century Metropolitan Railway varnished wood coaches, the restoration of which has won awards. These have been rebuilt in recent years from an extremely run down condition.
I subsequently visited the Severn Valley Railway for the last day of their Spring gala with 7 or 8 locos in steam. A pause to wait the crossing with another train gave me the chance to look closely at one of their GWR Manor class locomotives. It really highlights how different the layout and painting of this is when compared to our #1630. Looking in this way, there is no exposed pipework. It all runs below the sheet metal, which is almost completely unbroken. A very different approach when I think of all the holes that we have to adjust and fill around the many pipes and studs on our locomotive.
There was no work at the shop on Sunday as many of us attended the memorial for our late and sorely missed friend Bill Chyna. Many thanks to Kath and Beth for the invitation to a very pleasant afternoon remembering the good times.
Next weekend is likely to be rather quiet as many people will need to attend the rules training and / or test in preparation for running this season.
Nigel
|
Blog AdministrationCategory TreeCalendar
QuicksearchSyndicate This Blog |
|||||||||||||||||||||||||||||||||||||||||||||||||
Powered by s9y.
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...