Sunday, December 16. 2012
Steam Department Update 12-15-2012 Posted by Nigel Bennett
in Steam Department at
12:14
Comments (4) Steam Department Update 12-15-2012I suspect that a number of steam shop volunteers are, like me, feeling rather stiff, aching and bruised this morning. However, that is an indication of a very productive day yesterday. On 1630 the re-tubing is almost at the next key milestone. All but 17 of the tubes below and around the super heater flues are now loaded into the boiler and, by end of day those 17 are all cut to length. So it should not take more than an hour to load these next week. Those following the progress chart will notice a discrepancy between the full total of 180 and the target (171) that we are currently working toward. These are the 9 fire tubes that lie in between the super heater flues that have been removed. These will not be loaded at this time but slotted in as the super heater flues are fitted. This will not be done until the 171 are secured by expanding. After a couple of hours hammering ferrules into the remaining holes in both tube sheets, loading started in earnest. Here Phil stands on top of the large pile of tubes on the staging.
Phil selects a tube of the correct length and passes it to the team who feed it into the next hole in the front tube sheet. Slowly it gets more and more restricted in the barrel. Matt (believe me this is Matt !!)guided the tubes thru the barrel at the sides and here at the bottom under the super heater flues. By this stage he was looking rather uneasily at the space left for him to make his exit !.
Shortly after this, Matt squeezed his way out thru the remaining gap leading to the access hatch, having finally checked that no rogue objects remained in the boiler. Hopefully this is the last time that anyone will be able to get to the bottom of the barrel for the next 16 or so years !!. Squeezed in between the siphons in the firebox I was guiding the ends of the tubes into the rear tube sheet. Once Matt was out, we continued loading tubes by sliding them in on top of the ones below. The trick to this is the guy in the firebox (normally me !) who has to catch the end of the tube with a hammer handle, lift and then guide the end into the rear tube sheet. By the end of day you can see the 17 remaining gaps in the front sheet and the large number of tubes now in place can be seen thru the super heater flue holes.
Inside the boiler is a very different picture when compared to where Matt was lying a few hours earlier The rear tube sheet now is now largely full with the small area of projecting ferrules indicating where the remaining tubes will be fitted.
Comparing this to the shot at start of day shows just how many tubes have been moved into the boiler. The staging area beside the locomotive is now empty. We are starting to get space back into the shop. It is amazing the sheer volume of tube that fits into the boiler. The one thing that slowed us towards the end was that you can no longer keep a stock of cut tubes ready to load. With only a few to go, they have to be exactly the sizes required for the remaining holes. So we stopped loading in mid evening, having loaded all the precut tubes. We then cut the exact sizes needed for those 17 holes ready for next Saturday. Work also started on annealing the super heater flues ready for loading and expanding. This will be a different technique from the fire tubes as they are too large in diameter to fit the furnace and will need to be heated using the acetylene torches. The first of these was annealed yesterday (1 down 15 to go). Meanwhile work continues on fitting the corner patch to the firebox. Here Mike and Jerry are drilling the patch using the pillar drill. Much to our relief, Dennis our welding expert who has been away for a number of weeks, made it in yesterday. This was critical as the team fitting the patch need to work closely to his requirements in shaping and fitting the patch. Dennis was also able to start on welding the gear for the wheel lathe while Mark started work on freeing the back head on its slides so that it should move when the gear is attached. Overall a very successful day. Nigel Sunday, December 9. 2012
Covered space for steam collection Posted by Nigel Bennett
in Steam Department at
16:12
Comments (0) Covered space for steam collectionIn parallel with bringing #1630 back into operation we urgently need to improve the storage of our non operating steam locomotives. Many of our locomotives are currently stored outside where they are deteriorating. As detailed on the Illinois Railway Museum main website, the museum is currently planning an additional covered storage area. Space in this building will be provided based upon the cost of the building, which works out at about $215 per foot length. This is a substantial cost for a large steam locomotive which can be about 100 feet in length. Some of our best examples, notably the Burlington Hudson #3007, do not have dedicated covered track space. (While it is currently under cover it is occupying general department space and would potentially have to be put outside again when we have locomotives in operation). Other items that we would dearly like to get under cover, where they could be cosmetically restored for better display, are the Rock Island 4-6-2 #938 and C&O 2-8-4 #2707. Please consider donating to the fund raising for barn #14 nominating the steam department. As an added incentive, we have a number of the "Burlington Bulletin" books on the S-4 Hudsons including #3007, which we will provide to anyone who can donate $25 or more to the steam department for covered space. Nigel Sunday, December 9. 2012
Steam Department Update 12-08-2012 Posted by Nigel Bennett
in Steam Department at
15:17
Comments (10) Steam Department Update 12-08-2012There were two very separate activities at the steam shop this weekend. Outside, the Kansas City Southern tender from Galt arrived and had to be unloaded and put back on its trucks (which had arrived separately during the week). Here the rather unusual trucks of this tender await the arrival of the tender itself. The tender is a fairly substantial items as can be seen from comparison to the B&G building as it enters IRM for the first time. A good deal of careful back and fore was required to position the tender (still on the trailer) centrally over the track so that the mounting points would be in the correct position to fit into the trucks. Once in place steel beams were located under the body. The trailer had then to be raised, blocks placed under the beams, and then lowered a number of times until there was sufficient height to set jacks under the beams. Finally the jacks were all placed and the tender could be raised off the trailer. The trailer is free and starts to move out from under the tender. The trucks are chained to the trailer and each other so that they are pulled under the tender, at the correct spacing, as the trailer pulls out. The job of lowering the tender back onto its trucks so that the pins aligned and the pivot points located into the sockets in the trucks proved to be a long and tricky exercise. It was well past dark by the time this was completed so pictures of the completed tender are for next week !. On 1630, things looked bleak in the morning. We are absolutely dependent for tube loading on those of the team who can fit into the boiler. Having arranged a morning and afternoon shift, as it is more than one person can do to work in these conditions all day, Collin's car failed and he was not able to get to Union in the morning. However, while we lost the morning shift, Jason did sterling work in the afternoon. Here we see him "relaxing" between loading tubes. It is not a environment in which you can work for more than a few hours at a time. We have now completed loading of the tubes down both sides of the super heaters. The fireman's side, looking forward, now looks pretty full compared to earlier views when we were sand blasting. Looking toward the firebox on the engineer's side also shows the boiler filling rapidly. This also shows the positioning of the copper ferrules, which are set slightly below the surface of the tube sheet in the firebox, where the end of the tube will be beaded, but projecting into the boiler barrel, where the copper can be seen around each of the new tubes. Mike continued work on drilling the rivet holes in the patch. The accurate alignment of these holes is proving to be a significant challenge. Nigel |
Blog AdministrationCategory TreeCalendar
QuicksearchSyndicate This Blog |
|||||||||||||||||||||||||||||||||||||||||||||||||
Powered by s9y.
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...