Sunday, December 2. 2012
Steam Department Update 12-01-2012 Posted by Nigel Bennett
in Steam Department at
12:17
Comments (0) Steam Department Update 12-01-2012It was a productive day at the steam shop again very largely focused on 1630. On 1630: · Matt and Stu stripped and cleaned the check valves. These critical valves are where the water is fed into the boiler (from the injectors). These will be essential to even the earliest hydro tests. Since these valves are directly attached to the boiler they must be fully pressure tight to allow any testing. (The first tests will be done when the tubes have been rolled into place to identify any that require further rolling to make a perfect seal. At this point no accessories will be connected to keep the test very simple). It was inevitable that sand blast material got into the valves. In addition, one suffered from occasional leakage when last in use. Both were cleaned and lapped. The seat was replaced on the engineer's valve so these should now be in good shape for testing and service. · The firebox patch is now ground to shape and fits well onto the mud ring. Mike and Jerry were starting to drill the first hole. Initially a bolt will be fitted. Once the patch is rigidly bolted into place the bolts will be replaced, one at a time, by rivets. This requires considerable care as the holes in the mud ring are at different angles so each must be drilled thru the patch using guides to ensure that each is an exact match to the ring. Once the bolts are in place the patch can be rigidly secured and finally adjusted to form a perfect match to the sheets. · The last (hopefully) of the tubes were swaged and annealed. We have a few extra tubes that will be held in case of need should any be damaged in fitting but, on current calculation, we now have enough prepared to fully tube the boiler. In the next few weeks, when we have sufficient people available, we will swage the tubes for Shay #5. Having all the equipment set up and people now familiar with it will make it a lot more efficient to do these now. · As mentioned last week, the decision was taken to fit copper ferrules to the front tube sheet. Although the front sheet is often not ferruled, fitting ferrules will give greater assurance of a leak free seal. Unfortunately this means removing the tubes that were previously loaded. During the day the tubes were removed from the engineers side and the first 30 were reloaded with ferrules fitted. The process was, as always, somewhat tentative at first. However, once the method was established it moved a lot faster so we should be able to have all the tubes, that were previously loaded, refitted with ferrules in place and move on to new ones next weekend. After final cleaning the valve block for the planer was painted so that should be available for reassembly in the near future. Nigel Sunday, November 25. 2012
Steam Department Update 11-24-2012 Posted by Nigel Bennett
in Steam Department at
18:42
Comments (2) Steam Department Update 11-24-2012This Saturday saw continued progress in the Steam shop toward re-tubing 1630. The penultimate bale of 37 tubes was swaged and annealed while the final bale was brought into the swaging area ready for processing. The work done last Saturday on cleaning the rough edges from the dies of the swager seems to have worked well. No further problems were encountered with rough surfaces on the swaged tube ends. Good progress was made with cutting and loading so that, by end of day, we had 96 tubes loaded into the boiler. This time Collin and Jason had the "hidden" role of fitting ferrules into the fire box tube sheet. Here Collin is hard at work fitting ferrules and adjusting the position of the tube to the correct projection beyond the tube sheet. Overall progress today was very good. The boiler is now starting to look distinctly full of tubes. However, we have now decided that it would be safer to fit ferrules to some or all of the front tube sheet holes in order to reduce the risk of leakage. This will require some measurement and testing and may require us to reload some of the tubes. So that will be the main activity next week. Meanwhile Mike, Bob and Tom worked on the final shaping of the firebox patch. Ed and Matt continued with fitting the new pipe work along the boiler. In other areas, Ralph worked on the axle boxes for 428 and prepared the surface of another box for babbit facing using the Bullard lathe. Nigel Sunday, November 18. 2012
Steam Department Update 11-17-2012 Posted by Nigel Bennett
in Steam Department at
11:27
Comments (2) Steam Department Update 11-17-2012This weekend was "more of the same" at the steam shop, which was good as that is exactly what we need at this stage to get 1630 back together. Also, looking back, it is just about a year ago that I started logging detail of activity in the steam shop. It makes an interesting trail of what we have achieved so far. The focus is now on preparing tubes for fitting and progress this week was good: · we broke the record by swaging and annealing 43 tubes in the day. This is well over half as many as we have processed in all previous days combined. The other positive development is that several people learned the technique during the day so that we now have a number of people who can carry out this process. Here we can see Eric and Mark heating a tube in preparation to swage. And a nice shot of the swager actually forming the end of the tube. The one set back was that the ends of the last tubes swaged were not as smooth as they need to be. This proves to be the result of "mushrooming" of the edges of the dies. We polished this off in the evening so should be ready to continue next week. However it probably means that we should not do so many tubes at one time. We suspect that the issue may be that, over time, heat transfers to the dies and that is probably what allowed the deformation. Looking at the picture above it is easy to see how this could happen !!. · We started on loading tubes into the boiler and made good progress. 39 tubes were placed. We started at the sides as these are the most awkward to fit. Thanks to Roger for the photographs as I was buried in the smoke box doing the unseen bits!!. Most of the tubes in the bottom section will simple be pushed thru their hole in the front tube sheet and guided into the matching hole in the rear tube sheet with the ferrule already in place in the rear tube sheet. The ones at the side are more tricky. Because of the steam pipes, the tube cannot be passed thru its hole in the front tube sheet except at an angle that prevents it being fully inserted. So, in this area, the tubes are inserted thru one of the large super heater flue holes then moved to their actual location with help from someone in the boiler. Once in place, they are pushed forward to allow the guy in the firebox to fit a ferrule and then finally slid back into position. The picture show the external part of the operation and not Eric (in the boiler) and me (in the firebox) struggling in the confined spaces !!. · The stack of tubes on the fireman's side, that looked so large last week, is now virtually gone but we have a good supply ready to cut to length. We brought another bale of 37 into the swaging area. Very satisfying, there is now only one more bale left in the boxcar so the end is in sight. An interesting statistic on the tubes we are fitting. No wonder the piles look so large, the total length of the small tubes in 1630's boiler is a bit more than 0.6 MILES. · Another substantial task is Jerry's work on cleaning up the swaged ends of the tubes. Each must be polished with a sanding wheel on the die grinder to remove the scale formed in swaging. Jerry has put in many hours of work during the week to ensure that the tubes that we swage one weekend are polished and ready to use the next. So progress continues and it is really good to see obvious re-assembly work taking shape after so much stripping. The target will be to load all the required tubes before we start to expand them into the tube sheets. Actually fitting the tubes into the boiler starts the time clock on the certification period so we do not want to do this before all is ready to push forward. In other areas, Bruce was working on the detail measurements for rebuilding the axle boxes on 428. Nigel |
Blog AdministrationCategory TreeCalendar
QuicksearchSyndicate This Blog |
|||||||||||||||||||||||||||||||||||||||||||||||||
Powered by s9y.
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...