As we go into winter mode, I have decided to at least log on the majority of the report I send to the board every month. This way, even if I run out of time to write updates, our remote friends and visitors will have a bit of information.
In adfor a dition, we hope to have the Yard 5 set open for volunteers during the Holiday train event. While it is not planned as a public area, our friends will have a place to go for a cup of coffee or tea or cocoa, and a place to "set a spell".
GENERAL DEPARTMENT PROGRESS
The month of October was spent mostly supporting Terror on the Railroad.
The screamliner set was successful, and we encountered no significant mechanical issues throughout.
The wheel switch on the CRIP coach is delayed until spring, and expenses estimate is included in the 2010 budget.
We hope to complete several projects this winter, as well as awaiting the completion of Barn 11.
CBQ 993, a Havelock built baggage car is now en route, having left St Louis 11-8 via UP through Pekin and Proviso.
CBQ 1309, a baggage car owned by IRM at least since 2001, has been located recently and we have begun to inquire about the method of movement to finally get it home. Info coming from the Executive Director includes availability of a flat car in the area. A crane service has been identified by the Colorado Railroad Museum as someone they know. We project making progress on this car over the winter and hope to move it in early 2010.
INDIVIDUAL EQUIPMENT REPORTS
DLW coaches (3)
Two cars are service.
The third car is still undergoing required structural welding. The repairs are now progressing, with deck plates being installed.
Glen Springs
Roger Kramer has made significant progress on the car. Batteries have been reinstalled, and basic electrical function of the car has been reactivated. Exterior cabinet doors have been reattached, and latch mechanisms have been restored.
ATSF 2544
One side of the coach area has now been installed, and the second side of “modern” seats is being removed, to allow for completion of the area for spring. All seat frames are now located, and the prep work on the second set will be conducted over winter.
http://www.irm.org/gallery/ATSF2544
John McGloughlin
Interior restoration continues, as well as metal and paint work on one vestibule
Dover Strait
Most interior painting is complete, with some ceiling to be completed in spring. Light fixtures were removed and refinished, now being reinstalled.
B&M 3288/1094
No significant changes, beyond the continued progress. Jack continues on the coach area of the car. Windows are reinstalled. Seat frames are being located and installed. We await the assistance to use the forklift and retrieve the steps from the material yard. Once they are located behind the barn, prep work can begin.
RDC 9933
We have begun to disassemble more seating for repairs.
We have also disassembled one bathroom wall, to restore the proper doorway.
Our off season restoration plans include further repairs to baggage rack lighting circuits, as well as a planned spring effort to repair the secondary air circuit to provide interior brake control as well as a horn.
http://www.irm.org/gallery/CNW9933
CBQ Silver Ridge
Electrical conversion of low voltage DC fixtures has been completed
We are proceeding to backdate some of the bedrooms to original salmon
In addition the hope is to continue to backdate more bedrooms and bathrooms to original CBQ colors.
ACL Birmingham
The kitchen has some backdating to be done, but it will take a secondary role as we focus on Silver Ridge and the ventilation system.
Saturday's gang began with Greg Frech, JD Marzec and Adam Robillard.
We received 100tons of ballast this past week and it was time once
again to load ballast cars and continue working on surfacing yard 11
(outside of the barn) as well as the tail track lead at the Yard 13
diamond. Greg and JD were on the Model 50 Burro crane crew and sorted
material throughout the yard. We had lots of scrap, rails, timbers,
etc scattered all over the yard and they spent all morning loading the
gondola and stacking material. In the meantime,
Adam loaded our green CNW ballast car with the Model 30 Burro crane.
Joel Ahrendt received his first lesson on the Model 30 as well and now
has a good taste at what it takes to load a ballast car. Typically
each full car takes roughly a day (8hrs) to load with the clam shell
bucket.
By lunchtime, Adam had nearly 3/4 of the ballast car full and asked to
use the diesel dept switch crew to help dump ballast. Jim West and
Warren Lloyd as the crew of the ComEd 15 switched Yard 11 and dumped
1/2 of the car on the tail track lead. Jim West ran the engine while
Warren, JD, Greg and Adam ran the doors. Finished with that Greg, JD
and Adam got out the Amtrak regulator and regulated the freshly dumped
ballast in prep for tamping. Dark took hold soon after and we called
it a day.
Sunday's gang was made up of Steve Lewkowycz, Jim West, Joel Ahrendt,
Warren Lloyd and Adam Robillard. The day's priority - Tamp and
Regulate. Steve L and Adam R started the day out by checking fluids
and starting up the Amtrak 6000 tamper in Yard 11. We took it to the
Yard 11 tail track and set up the machine. Steve L took to the
controls for his first time and made the first pass with only a minor
'cord' problem which continued to short out and trip the circuit
breaker.. A quick crop of the light buggy extension cord was in order
but remedied quickly. After the first pass was through we got the
Amtrak regulator out and plowed stone to prep for the next pass. By
this time we were joined by Jim W and Warren L who helped finish the
next few passes with the tamper. Jim ran the tamper for the rest of
the evening and did a fine job as this was only his second time at the
controls. We made three passes on the track now it no longer resembles
a roller coaster. Warren ducked out about the time Joel A showed up to
help out. The next steps were to tamp 11-4 and 11-2 tracks from the
Barn to the switches. We split into two gangs: Steve and Joel ran the
ballast regulator while Jim and Adam ran the tamper. We did our final
passes on both tracks and the crew on the regulator had them both
broomed and looking like mainline track by dark! The 6000 ran great
with no mechanical problems all day long.... Looks like the hard work
over the past few months is paying off. Thanks to all who helped this
weekend, especially Joel Ahrendt, Jim West and Warren Lloyd visiting
from the other departments, as we get ready to open up Barn 11!
Adam Robillard
IRM Track Dept
lzeje657@msn.com
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]