With Christmas close it was a small but active team at the steam shop this weekend.
The next major milestone on 1630 was achieved as planned.
The last 17 fire tubes were loaded so all except for the 9 that will be installed along with the super heater flues are now in place.
Then we moved on to rolling the fire box ends. As with each step, this was initially slow. It is critical that we fully understand the technique and can do it right each time before we start to do it on a large scale. However we made a good start, got more confident as the day progressed, and by end of day the first 15 were rolled. Looking closely at the view below you can see the effect. Comparing columns K, L and M to the adjacent columns, these are now tight in the tube sheet and set at a consistent 1/4 inch projection beyond the sheet.
Once we have proved that everything is watertight the projection will be beaded over. All tube ends in the fire box are beaded to protect the joint from the direct effects of the fire.
The rolling requires a team of three and is achieved by first setting the tube accurately with a 1/4 inch extension beyond the tube sheet. The team member in the smoke box then clamps that end of the tube to prevent movement. The roller is then inserted into the tube. Here you can see the construction of the roller. Three small hardened rollers are turned by the rotation of the tapered pin that is inserted thru the center.
The air motor is attached and rotates the central tapered pin.
The rotating pin is slowly drawn into the roller forcing the three hardened rollers out into the wall of the tube slowly increasing its diameter.
When the tube is fully expanded against the ferrule and tube sheet the taper pin has been largely drawn into the roller.
The motor is then reversed to free the pin and the process continues with the next tube.
In addition to the work on the fire tubes:
· annealing was completed on the 16 super heater flues, so these are now ready to load once the fire tubes are secured;
· drilling continued on the fire box patch. The holes are now complete on the front face. Once holes are made in the side face it will be finally formed to the mud ring along its whole length.
We also took advantage of reasonable, if cold, weather to jack the end of the KCS tender to remove the wood packing that was left between the rubbing plates when it was delivered. This should now be in a condition which will allow it to be shunted so that the box cars of parts can be relocated back by the road to allow access.
Nigel
Leading the repair and restoration on the Ely's observation end ceiling is Buzz Morisette. Here are a few more pictures of the progress in the repair. Please notice the one new roof support installed by Buzz on Wednesday December 5, 2012.
Now in two weeks time look at the changes and the efforts that went into improving the ceiling wood supports. These photos were taken 12-19-12. Please compare the progress in those two weeks. Remember it has been relatively mild for this time of year. Buzz has made the most of the "good" weather.
With the Holiday's falling on a week day, the progress has been slowed. January will again bring Buzz and friends back to the project. Another PROJECT.... is the Barn 14 fund raising. Do not forget to send your donation in before January 2, 2013 to qualify for that tax deduction on your 2012 tax return. The CNW bilevels, CGW X38 snow plow, B&M 3288 wood diner, CB&Q 3007 Hudson and CA&E 319 interurban will all Thank You for your support. Roger
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...