I suspect that a number of steam shop volunteers are, like me, feeling rather stiff, aching and bruised this morning. However, that is an indication of a very productive day yesterday.
On 1630 the re-tubing is almost at the next key milestone. All but 17 of the tubes below and around the super heater flues are now loaded into the boiler and, by end of day those 17 are all cut to length. So it should not take more than an hour to load these next week.
Those following the progress chart will notice a discrepancy between the full total of 180 and the target (171) that we are currently working toward. These are the 9 fire tubes that lie in between the super heater flues that have been removed. These will not be loaded at this time but slotted in as the super heater flues are fitted. This will not be done until the 171 are secured by expanding.
After a couple of hours hammering ferrules into the remaining holes in both tube sheets, loading started in earnest. Here Phil stands on top of the large pile of tubes on the staging.
Phil selects a tube of the correct length and passes it to the team who feed it into the next hole in the front tube sheet.
Slowly it gets more and more restricted in the barrel. Matt (believe me this is Matt !!)guided the tubes thru the barrel at the sides and here at the bottom under the super heater flues. By this stage he was looking rather uneasily at the space left for him to make his exit !.
Shortly after this, Matt squeezed his way out thru the remaining gap leading to the access hatch, having finally checked that no rogue objects remained in the boiler. Hopefully this is the last time that anyone will be able to get to the bottom of the barrel for the next 16 or so years !!.
Squeezed in between the siphons in the firebox I was guiding the ends of the tubes into the rear tube sheet.
Once Matt was out, we continued loading tubes by sliding them in on top of the ones below. The trick to this is the guy in the firebox (normally me !) who has to catch the end of the tube with a hammer handle, lift and then guide the end into the rear tube sheet.
By the end of day you can see the 17 remaining gaps in the front sheet and the large number of tubes now in place can be seen thru the super heater flue holes.
Inside the boiler is a very different picture when compared to where Matt was lying a few hours earlier
The rear tube sheet now is now largely full with the small area of projecting ferrules indicating where the remaining tubes will be fitted.
Comparing this to the shot at start of day shows just how many tubes have been moved into the boiler.
The staging area beside the locomotive is now empty. We are starting to get space back into the shop. It is amazing the sheer volume of tube that fits into the boiler.
The one thing that slowed us towards the end was that you can no longer keep a stock of cut tubes ready to load. With only a few to go, they have to be exactly the sizes required for the remaining holes. So we stopped loading in mid evening, having loaded all the precut tubes. We then cut the exact sizes needed for those 17 holes ready for next Saturday.
Work also started on annealing the super heater flues ready for loading and expanding. This will be a different technique from the fire tubes as they are too large in diameter to fit the furnace and will need to be heated using the acetylene torches. The first of these was annealed yesterday (1 down 15 to go).
Meanwhile work continues on fitting the corner patch to the firebox. Here Mike and Jerry are drilling the patch using the pillar drill.
Much to our relief, Dennis our welding expert who has been away for a number of weeks, made it in yesterday. This was critical as the team fitting the patch need to work closely to his requirements in shaping and fitting the patch.
Dennis was also able to start on welding the gear for the wheel lathe while Mark started work on freeing the back head on its slides so that it should move when the gear is attached.
Overall a very successful day.
Nigel
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]