It was a day of great progress and one very significant milestone in the steam shop yesterday.
The activity was largely on 1630:
· Fitting of the small tubes progressed very well using the methods established last week, with teams working both ends at the same time.
o Collin and Eric ground the projecting ends in the firebox and all of these are now ready to flare once they are sealed into the front sheet. As noted below, work on tubes in the firebox ceased for very good reasons in the afternoon;
o Phil cut replacements for the two tubes that had hit problems and these were fitted and expanded. So all the small tubes, other than the few that are in between the super heater flues and must be fitted as part of installing the flues, are now in place;
o Most of the ends that are to be beaded in the smokebox were also ground to length.
At times Brian and Eric were working simultaneously on this with an impressive rate of progress. Just a few on the fireman's side remain to be ground to length.
o Brian is rapidly becoming our expert on the tube roller.
Once the grinding of the engineer's side was complete he started again with the tube roller and worked steadily to the point that we are now substantially more than 50% complete in rolling tubes in the smokebox. Everything on the engineer's side and much of the lower area is now done.
· With installation of the small tubes nearing completion, Phil made good the paint (actually a specialized boiler treatment) on the 16 super heater flues to ensure that these are ready for installation.
· Phil also spent a couple of hours on the sand blast cabinet in the car shop cleaning up some of the rivets needed for the patch. ........... which brings us to the major landmark of the week;
· Dennis returned after a couple of weeks absence, due to illness in the family, and work restarted in earnest on the firebox patch. The tube fitting team moved out to allow full access to fit the patch.
o The patch was bolted into place, the last two rivet holes were drilled and bolts fitted thru them.
o After more cleaning, degreasing and tightening, the patch was finally secured in place and Dennis was preparing to weld when I left for the Soiree.
o I later received pictures from Phil. By the end of day the patch was fully welded into the inner firebox sheet !!.
o This is a huge step forward in correcting the problem that caused the locomotive to be pulled from service. It mean that we now have one more really tricky job to do before the repair is complete. All the bolts currently holding the patch must be replaced by rivets, which are 7/8 diameter and about 6 inches long. This will be a "fun" exercise but, once this is done, we will be close to the point where this part of the boiler is ready for hydro testing.
In other areas:
· Dennis completed welding the gear for the back head mechanism on the wheel lathe. Once the holes are drilled out and bolts fitted we should be able to assemble this part of the lathe and test it.
· Bob continued work on the planer;
· Dave machined new parts for the spring hangers on 428; and
· Jeff was able to install the first sections of the new compressed air supply to the South shop.
So, overall a very significant day for the steam shop.
No update next week as I am going to the UK on business. However, a lot is now in progress so I hope that there will be a lot more to report in two weeks time. I am hoping that there may be the opportunity to see some steam activity in the UK while I am there.
Nigel
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]