Steam Department Update 03-30-2013 Posted by Nigel Bennett
in Steam Department at
11:12
Comments (5) Steam Department Update 03-30-2013The number of people in the shop was a bit reduced at Easter weekend and it was unfortunately one of those days when a lot of hard work did not achieve as much as was hoped. On 1630: · The main focus was on loading the super heater flues. Unfortunately this proved a great deal more tricky than had been hoped. When the tubes were safe ended each was carefully measured with the objective that it was matched to a specific location with a certain amount of excess length to be ground off after fitting. When the first few were fitted it became clear that there is a significant variation from the intended lengths with some shorter and some longer. Clearly, where there is excess length it can be cut off. But if we have any that are too short to be fitted we would need to get more welding done. The key objective became to ensure that the shorter ones can all be used without the need to get a welder in again to lengthen any. So, instead of simply slotting each tube into its numbered hole, it became an exercise in loading and unloading tubes multiple times to ensure that the shortest tube that provides the required projection at each end is used in each hole. As each tube is 17 feet long and 5 1/2 inch in diameter, they are heavy beasts to fit and refit so it was a hard day's work made worse by the fact that it was unexpected. The first part is easy. The fork lift raises the tube to height and in this shot, Phil and Sean slide the tube into the hole in the tube sheet.
The next bit is more tricky. Once the tube is off the forks it becomes a giant lever pivoted in the tube sheet. Here Dave is assisting by controlling the end of the tube to ensure that is slides smoothly thru the hole and can be located in the rear sheet without dislodging the ferrule at that end.
Once it is in place there is a careful process of gauging the projection at each end to ensure we have the required 1/4 inch minimum. Given the length issue, a number were then removed and the process repeated to ensure that the shortest suitable tube was used in each hole. Anyway, by end of day we had all 8 on the engineer's side in place and the first on the fireman's side and have managed to place the shortest tubes.. · With Vince's assistance, Mike finished the tapping for the patch screw on the firebox corner. When I left sparks were flying from inside the firebox as Mike did the final grinding of surfaces inside the firebox ahead of riveting. We are waiting on the return of the air bucker from overhaul and can then set up for the riveting.
· Ed and Richard substantially completed the pipe runs along the boiler sides and started work on the cab pipe work. · During the last couple of weeks Kevin has done more needle chipping to prepare for painting both on 1630 and on the planer. Elsewhere: · Bob continued work on wiring the control system for the planer; and · Dennis finished building up the grease keep for the truck axle box on 428. So next week we target fitting of the remaining flues and then we can set up to roll them into place. Nigel Sunday, March 24. 2013
Steam Department Update 03-23-2013 Posted by Nigel Bennett
in Steam Department at
10:18
Comments (7) Steam Department Update 03-23-2013Not too much visible progress in the steam shop this weekend but actually a good deal that is not very apparent. On 1630 · The first two super heater flues are now loaded. This involved identifying and learning how best to use a whole array of new equipment.
o Jason successfully expanded ferrules into all 16 holes in the rear tube sheet last Sunday. These were chosen from two alternate thicknesses to provide a close fit on the flue as it is inserted from the front of the boiler. o For the large flues the loading process is, of necessity, more complex. Ferrules will be fitted in the front sheet only where the hole is enlarged beyond 5 1/2 inches in diameter. From measurements made yesterday this will be 10 of the 16 flues. o Fitting the front ferrule is very much part of the loading process. Given the size and weight of a 5 1/2 inch tube 17 feet in length, there is no possibility of expanding the ferrule into the sheet in a way that would allow the flue to passed thru the ferrule without displacing it. So the flue must be passed thru the front sheet, into the back sheet and pushed several inches beyond its final position into the boiler, clear of the front tube sheet. The ferrule can then be fitted and the flue drawn back into the front sheet. So fitting the front ferrules is an integral part of loading the flues. o Initial progress was slow as the ferrules must be expanded to the absolute limit of our largest rollers, which meant that they were not very secure. During the day we made a spacing ring that overcomes the problem so, based upon experience with the two now in place, we believe the rest should be much quicker. · Jane continued priming the inside of the cladding sheets so that these will all be ready to install over the lagging. She has now completed the batch we have in the shop so we will need to store these again and get another batch for cleaning and painting. The cladding will not look good at this stage as the outer face will not be prepared and painted until it is in place. However, priming the inside where it is subject to heat and damp from the lagging, is essential to preserve the sheet on the locomotive. · Eric and his Dad worked from pictures of the backhead, that we took before stripping, to locate all the valves and controls, lay them out in the machine shop and start work on servicing, cleaning and painting them. · Dennis weld filled the hole for the one patch screw that must be replaced. Mike and Tom then produced a guide and started to drill out the hole for threading. · Dennis weld repaired the two super heater elements that failed under pressure test last Fall. (Actually Dennis did this a couple of weeks ago and Nigel did not notice !!). Anyway, these are now ready for hydro testing once we get above freezing outside.
On 428 · The first of the two guides for machining the shoes and wedges was competed and Tom is starting to finish the ends of the cast iron shows on the shaper. The second, which will enable the machining of the angle on the wedges is approaching completion. · Dennis was brazing the grease cellars for the truck axle boxes. In other areas: · We moved the turret covers for #265 up on to the top of the locomotive. Time is moving on and the museum opens to visitors soon. We would be deeply unpopular with Buildings and Grounds if large lumps of metal are in the walkways of barn #9 as opening day approaches ! · We had hoped to get some tubes for the Shay out of the boxcar but investigation proved that this can only be done with fork lift access to the car as other heavy material must be moved to get at the tubes. (For efficiency we want to swage the Shay tubes when we do a few extra required for 1630. It takes several hours to set up and test the swager so we want to do a full batch rather than 5 tubes when we do so). However, we will now need assistance to shunt the KCS tender and re-spot the boxcars before we can do this. · Glenn and Richard worked on the safety covers for the new compressor. · Glenn assisted the track department in trying to start their crane. Unfortunately this proved "non trivial" as it seems the fuel lines are blocked. So it did not start today. · Jeff was finalizing the air supply in the new shop. - Yes this is Jeff. The extent of the hair cut led many to question if we had a new volunteer this weekend !. Most of the new outlets are now in place. These are all being structured with a drain on each down pipe to avoid water carry over. · Bob carried on from last week, positioning the planer. It is now not only in position but pretty much level. So a good day's progress and hopefully we are now set up to move forward quickly next weekend. Nigel Sunday, March 17. 2013Steam Department Update 3-16-2013After a hard day at the shop it is always good to be able to say that we achieved what we set out to do. Having a major target in sight certainly encourages you to keep going! On 1630: All the small tubes below the super heaters are now completely installed to the point at which we will first test them. (As mentioned previously, they should be water tight after expanding and flaring. So we aim to do an initial hydro test to identify any that need to be tightened before we roll over (bead) the ends of those that need to be so treated). · A number of us took turns to expand the firebox tube ends with the air hammer. The technique developed last week worked well. Brian rolled any tubes that showed signs of moving during expansion a little more to ensure they were tight. He has become our expert with the tube roller, having expanded almost all the ends into the front tube sheet. The expansion is a tough job. It takes a lot of effort to control the large air hammer and ensure that a smooth flare is produced. All this must be done while squeezed in above the arch tubes where the heat builds up nicely. However, we found that you could do 6 to 8 before running out of steam. As you weaken, you are able to apply less force to the hammer and the flaring becomes less effective. So the time to stop is pretty clear!!. Anyway, by constantly switching operator, we achieved the objective and flared more than 130 tubes in the day. Here you see Phil and Brian at the end of the job. In this case Phil operates the hammer while Brian watches the tube end closely for any sign of movement. This is critical as the guy on the hammer cannot easily see if the tube starts to move;
Meanwhile Mike and Ralph worked on the holes thru which the patch will be riveted to the mud ring. The preparation is everything. The hot rivet is hammered into its hole in maybe 25 seconds. However the shape it will take is determined by forming the hole and the design specifies that the rivets are not all the same. Some have conical heads with a small countersink into the sheet, while others are countersunk almost flush. Here Mike is cutting the countersink into which the rivet will be formed.
So, as is the way with this work, we now move on from techniques with which we have become familiar to new ones. The next step on the tubing is to fit the 16 large super heater flues (and the remaining 9 small tubes that lie between them). While the general principles are the same, the tools are distinctly different. You certainly cannot use an expander on a tube this size. Both ends and the ferrules at the firebox end will need to be rolled into place and these rollers are on a whole different scale from those we have been using. On 428: · Dennis continued with building up the truck axles boxes. The focus this week was on building up the ledges on which the grease cellar rests to provide lubrication to the journal from below; · While Dave and Phil continued building the machining guide to mount the axle box wedges in the shaper. Elsehwere in the shop: · A big visible step was made on the wheel lathe. The large gear, that was cracked and has been repaired, was finally fitted into place along with the clutch mechanism. The mechanism was broken, either when the lathe was acquired or in transit, and has been rebuilt with some missing and broken parts reconstructed from drawings. The gear is driven by an electric motor (behind the gear itself) and free wheels on the shaft unless the clutch is engaged (from a lever at the operator's station. The control linkage was also reinstalled and can be seen running across the end of the lathe to the clutch mechanism. Much to the relief of all involved, this now operates correctly when the control lever is moved!. · Stu, Bob and Eric positioned the planer. This may not look much but is a big step in activating this machine. This a very substantial weight that has, to this point, been resting on rollers. It has now to be finally positioned and leveled after which the rebuilt hydraulics can be reconnected. During the afternoon and evening the machine was positioned. Then the leveling screws were all cleaned up and located on steel plates. The machine was the raised off the rollers and slowly lowered so that it sits only on the leveling screws. Next it will need to be accurately leveled (it currently demonstrates that the floor is not accurately level!) and locked into place. Here you can see the early stages as Stu screws down one of the leveling screws to lift the main body of the planer and release the rollers that are still seen projecting from under the machine So next week we can start the next phase of the tubing. Nigel |
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]