Wednesday, November 25. 2015Thankful For A Lot! New Trolley Bus Arrives 11/25/2015.At 10:15am on Wednesday 11/25/2015, Seattle Gillig Trolley Bus 4123 rolled off the truck trailer under its own power! The bus was loaded in Seattle on Saturday afternoon. Thanks to the guys at Extreme Trucking, it safely made the cross-country trip in about 3½ days. As usual, the guys at MEHVA (Metro Employees Historic Vehicle Association) out in Seattle took care of us. They chose a coach that was in great shape and mechanically sound. They also sent along ever critical extra parts.
Our coach has a build date of February 13, 2002. It is exactly 13 years, 9 months and 12 days old. It may very well be the youngest piece of equipment ever to join the museum's historic collection.
We were able to make two test trips and it performed wonderfully. As this is such a new bus, there are a couple things that we are figuring out as we go and we have a couple outstanding questions for the MEHVA guys, but it was great running a bus that could easily still be in service. We are immediately getting busy emptying, cleaning, inspecting and testing the bus and will hopefully have it in service for the Christmas event in a week and a half.
In this season of giving thanks, those involved with this acquisition come to mind. First, thanks to all the guys out in Seattle for arranging this and taking care of the loading. Thanks to the Board of Directors for having the foresight to approve such an exciting new acquisition. As always, a HUGE thank you goes to Richard Schauer. He arranged the trucking and took care of all that was necessary to "de-shippify" the bus once it arrived - putting back all the things that had to be done/undone in order to ship it. Finally, THANK YOU to everyone who has supported the Trolley Bus Department over the years. With the previous acquisitions from MOT in St. Louis and this one, our trucking costs are in the $15,000 range. Even though vehicles are either donated or made available at scrap value, it still costs a considerable amount to transport them to the museum. Your past and continued support allows us to keep working and (hopefully) keep acquiring as exciting opportunities (like this one) arise.
We in the Trolley Bus & Motor Bus Departments wish everyone a wonderful Thanksgiving!!!! Sunday, November 22. 2015
You don't have to be mad .... but ! Posted by Nigel Bennett
in Steam Department at
19:32
Comments (8) You don't have to be mad .... but !
What a difference a few days makes in Illinois!!. In the last few weeks we have been working steadily thru the jobs needed to winterize #1630 and the support equipment while enjoying a long warm Fall. Then this weekend Winter arrived with a vengeance. Small problem, this was the weekend we had a rather critical activity scheduled!!. So, neither rain nor snow etc. (Also you don’t have to be mad to work in the steam shop but it sure helps at times.
The critical activity was the FRA observed hydro test of Shay #5 which was scheduled for Sunday. Clearly large quantities of water do not mix well with temperatures falling into single digits. However we managed.
On Friday Phil managed to fill the boiler and a reserve container in the shop before draining the bottle car that provides our supply of treated water. (Just ahead of the night when temperatures plummeted).
On Saturday I managed to get to the shop between the two bands of snow. Conditions on site were “interesting” and the work team was small.
Difficult to imagine that this was just 7 days after the shot of removing the dome cover from #1630!!. Congratulations to Chris and Jon who made it in. On the Shay the objective was to get the water circulating from the boiler thru the pool heater and then get this fired up so that boiler could be brought up to around 100F and allowed to equilibrate for the test. This was subject to some significant concern as the heater is outside and, should it not operate reliably, there would be a risk of it freezing and damaging the exchanger. Much to my relief, despite digging it out of the snow and having to shield it from further driving snow during the day, it started and ran reliably so the warm up worked well.
Actually, having been used to #1630, it is startling how much quicker #5 warms up and it seems to even the heat out much more effectively because of the relatively short barrel. In the shot above you can see the inlet from the heater feeding into the dome and the return running from the blow down back along the shop to the North.
Sunday was a very pretty day, even if it was 8F when I got back to the shop, and the team could get to the site without problems. The heater restarted without issue and the boiler was ready for testing by mid-morning when the FRA inspector was scheduled. The pressure was raised slowly to 240 psi (125% of the 190 psi at which she will operate). Jason, Phil and Collin worked with the inspector to check parts of the boiler for any sign of leakage but she proved extremely tight. One small area of a seam and the head of one stay will need minor peening but we have an acceptable pressure vessel!!.
This opens up a whole lot more work for the Winter (which is why we were so desperate to get this done before it became impossible to work with water!). The boiler can now be lagged and the various accessories and their pipework fitted. The smokebox riveting should be done soon and then the smokebox can be completed and the truck refitted.
Technically there is no reason that she should not be operational next season. The biggest barrier is MONEY!. The response to the Summer appear was disappointing ($600 plus $600 in matching). Funds for #5 are now low and her operation in 2016 is going to depend heavily on donations in the next few weeks.
So, aside from this weekend, what has been happening in the last few weeks?.
#1630
Work progressed as planned.
#5 – Shay
I am sure that Brian will provide a more detailed update however a lot of progress is apparent leading up to the test today.
#938
Phil and his team completed the Summer work by painting all the wheel and lower areas that have been stripped and primed. She looks a great deal more presentable and will hopefully be able to go under cover once the new barns come into service.
#428
With the cab now riveted, Jon has been working on painting the interior and planning the woodwork that can now be fitted.
Compressor shed
Jeff and Jerry have made huge progress on the pipe work for the new compressors. Max has set up most of the wiring. The smaller of the two compressors is linked in and workable. All the main pipe work for the large compressor, including the cooling loop has been installed. The one remaining item is the flanges to connect the large compressor to the pipework. Once these are made the whole set up should be in a state to test.
Before it can be commissioned a state inspection is required so we cannot put either into operation until the whole set up is complete.
So a busy and successful couple of weeks. Now we head into a busy Winter with the objective of completing two locomotives for next season.
Nigel
Wednesday, November 18. 2015
Model Railroad Display Update Posted by Nigel Bennett
in Model Railroad Display at
17:02
Comments (21) Model Railroad Display UpdateIt has been three years since the beginning of fund raising for the Model Railroad Display Building. At this time we are at about 50% of the funds needed to start work on the project. We are now looking at two or three designs for the building. So what is next?. This is where you can help with donations to the model railroad restricted fund. We can make this happen sooner rather than later with your help. Whether you are a modeler or not this will be an asset to increase the enjoyment of the visitor experience at IRM. I firmly believe IRM needs to be more entertaining to the typical visitor we get today and, just as we completed a children’s playground in 2012, this will be the next big thing. Please help with your donations to this cause. I can be contacted at the museum or by e-mail at havj13@aol.com. A big thanks to all who have donated to help with this project. Henry Vincent |
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]