What a difference a few days makes in Illinois!!. In the last few weeks we have been working steadily
thru the jobs needed to winterize #1630 and the support equipment while
enjoying a long warm Fall. Then this
weekend Winter arrived with a vengeance.
Small problem, this was the weekend we had a rather critical activity
scheduled!!. So, neither rain nor snow
etc. (Also you don’t have to be mad to
work in the steam shop but it sure helps at times.
The critical activity
was the FRA observed hydro test of Shay #5 which was scheduled for Sunday. Clearly large quantities of water do not mix
well with temperatures falling into single digits. However we managed.
On Friday Phil managed to fill the boiler and a reserve
container in the shop before draining the bottle car that provides our supply
of treated water. (Just ahead of the
night when temperatures plummeted).
On Saturday I managed to get to the shop between the two
bands of snow. Conditions on site were “interesting”
and the work team was small.
Difficult to imagine that this was just 7 days after the
shot of removing the dome cover from #1630!!.
Congratulations to Chris and Jon who made it in. On the Shay the objective was to get the
water circulating from the boiler thru the pool heater and then get this fired
up so that boiler could be brought up to around 100F and allowed to equilibrate
for the test. This was subject to some
significant concern as the heater is outside and, should it not operate reliably,
there would be a risk of it freezing and damaging the exchanger. Much to my relief, despite digging it out of the
snow and having to shield it from further driving snow during the day, it
started and ran reliably so the warm up worked well.
Actually, having been used to #1630, it is startling how
much quicker #5 warms up and it seems to even the heat out much more
effectively because of the relatively short barrel. In the shot above you can see the inlet from
the heater feeding into the dome and the return running from the blow down back
along the shop to the North.
Sunday was a very pretty day, even if it was 8F when I got
back to the shop, and the team could get to the site without problems. The heater restarted without issue and the
boiler was ready for testing by mid-morning when the FRA inspector was
scheduled. The pressure was raised
slowly to 240 psi (125% of the 190 psi at which she will operate). Jason, Phil and Collin worked with the
inspector to check parts of the boiler for any sign of leakage but she proved
extremely tight. One small area of a
seam and the head of one stay will need minor peening but we have an acceptable
pressure vessel!!.
This opens up a whole lot more work for the Winter (which is
why we were so desperate to get this done before it became impossible to work
with water!). The boiler can now be
lagged and the various accessories and their pipework fitted. The smokebox riveting should be done soon and
then the smokebox can be completed and the truck refitted.
Technically there is no reason that she should not be
operational next season. The biggest
barrier is MONEY!. The response to the Summer
appear was disappointing ($600 plus $600 in matching). Funds for #5 are now low and her operation in
2016 is going to depend heavily on donations in the next few weeks.
So, aside from this weekend, what has been happening in the last
few weeks?.
#1630
Work progressed as planned.
The boiler was washed out when the weekend weather was
reasonable and she then waited for the completion of #938 to free up her space
in the shop;
Last weekend the switch was carried out with #938 going
outside and #1630 coming into the North end of the shop. The switching involved some coordination with
Frank and the track team as they were using the last good weekend to replace
ties in the switches leading in to the steam shop. Thanks to Frank and his team for this. Some of the ties were getting very tired and
none of us fancy the idea of lifting #1630 out if she were to fall into the switch
because of this!.
Almost a ceremonial end of season ritual is the removal of
the dome cover to allow her to fit into the shop. Thanks to Max who did this lift with the boom
truck;
Once into the shop, the switching continued to split the
loco and tender and remove the drawbar for its annual inspection;
This weekend we have continued stripping in preparation for the
annual inspection and planned Winter work.
The small team yesterday removed the safety valves, firebox
lagging and gauges to enable routine annual inspection work;
Today Jason and the team were working on measuring the valves
and crosshead shoe. The major maintenance
activity for this Winter is the inspection, and probably fitting new rings, of
the valves on both sides and the fitting of new babbit to the upper shoe of the
crosshead on the fireman’s side as this has excessive play.
#5 – Shay
I am sure that Brian will provide a more detailed update
however a lot of progress is apparent leading up to the test today.
The broken stay, identified in the first water test, was
removed and a replacement machined and fitted.
Then the heads were formed. First
the outer end of the stay is bucked to prevent movement (while Phil is working
in the firebox to form the head there)
Then he moves outside and forms the outer head in the same
way.
Work then progressed thru the iterative process of applying
some hydrostatic pressure to the boiler, spotting any leaks, correcting those
leaks and moving to a higher pressure;
Once it was demonstrated that the tubes and super heater
flues were watertight, their ends were formed and beaded;
The boiler as then tested to 240psi to prove it was ready
for inspection.
#938
Phil and his team completed the Summer work by painting all
the wheel and lower areas that have been stripped and primed. She looks a great deal more presentable and
will hopefully be able to go under cover once the new barns come into service.
#428
With the cab now riveted, Jon has been working on painting
the interior and planning the woodwork that can now be fitted.
Compressor shed
Jeff and Jerry have made huge progress on the pipe work for
the new compressors. Max has set up most
of the wiring. The smaller of the two
compressors is linked in and workable.
All the main pipe work for the large compressor, including the cooling
loop has been installed. The one
remaining item is the flanges to connect the large compressor to the
pipework. Once these are made the whole
set up should be in a state to test.
Before it can be commissioned a state inspection is required
so we cannot put either into operation until the whole set up is complete.
So a busy and successful couple of weeks. Now we head into a busy Winter with the
objective of completing two locomotives for next season.
Nigel
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]