Sunday, December 18. 2011
CTS 4223 Update - December 17, 2011 Posted by Robert Kutella
in Cleveland Transit System 4223 at
11:09
Comments (2) CTS 4223 Update - December 17, 2011Sometimes you work for weeks and wonder what progress you have to show for it. Sometimes all that prep work comes together quickly and shows gratifying results. Such is the way of restoration work. The crew got busy early with Rod Turner on the ladder and Eric Lorenz working from the ground. New threaded inserts had to be installed to allow the marker lights to be installed - we hoped. Eric was up on a ladder most of the day, here wrestling the right rear marker into place. Meanwhile Alex Randow was working to mount several other items. This one is a fold up step to access the roof, here mounted on the side behind the exit doors. There are only three of these to scale the height, and not much to balance upon if you were the unlucky guy that had to climb up there. This is another of the items installed by Alex. Once up all the steps you were considered lucky to grab this rung and haul yourself upright. Woe be to you if it was rainy or snowy. Now to see what the opening paragraph was all about. Here is the rear end of the car with most of all the accessories and parts installed. Rear windows, retriever bracket and retriever, two rear marker lights, two rear stop lights, and the three rear bumpers. It looks like a complete car!! Sunday, December 18. 2011Wood Shop Update - December 17, 2011We would like to welcome new volunteer, Keith Letsche. Keith came out to help today and was put to work on the TMS truck rebuilding, and then given a taste of work being done on the CTS 4223 project. Shown here, he is restoring one of the many aluminum window sash. Thanks, Keith, it was a pleasure meeting you; I hope we will see in the future weeks. Tim Peters is getting frosted! Or rather, he has been sandblasting window glass for the CRT 1797. After glazing in the frames, it will be painted with the black field denoting the car number in the upper sash at each end of the sides. Getting tired of all the window work? Tim caught me in the act of goofing off trying to 'inspect' what he was doing. He never goofs off, and is almost a non stop machine. Here he has made several carefully fitted wood repairs to the motorman's door, and is sanding it down, to be ready to begin painting. A lot of other work went on, parts being processed through our mortiser machine, and some new stock for window bottoms sawn and sized, these destined for IC diner 3996. Sunday, December 18. 2011
Steam Department Update 12-17-2011 Posted by Nigel Bennett
in Steam Department at
10:31
Comments (0) Steam Department Update 12-17-2011There was a very good turnout this Saturday. Unfortunately the timing of the holidays means that the next two weekends are likely to be very limited. A few of us who have time off are planning mid week sessions so if anyone is available, drop me a note. I had to leave early this Saturday but, even so, saw a number of milestones reached and more was achieved after I left. On 1630: · Collin broke the tube end removal record by single handedly removing 61 tube ends, including many large ones, by early afternoon. This completed the job of removing all the tubes we plan to remove for this inspection. (As previously mentioned we currently plan to leave the central group of super heater flues in place as they do to obstruct access to the boiler barrel for inspection). This success highlights one of the sad facts of life in the museum environment. None of us are experts so we have to learn on the job. A lot of the tasks get a great deal faster as you learn the tricks but it may be years before they are required again. Had all the tube end removal been at the rate the guys can now do it, we could probably have done it in half the time. This week I got into the firebox AND remembered to put the memory card in the camera !!. So the shots below give a good idea of the work and the conditions in which the guys operate. In the morning all the fire tubes were out on the fireman's side. The ends of 6 flues remained, which were removed during the day. Cutting the excess metal from the end plug of a fire tube. The same exercise on a super heater flues clearly shows the cut being made. You can also see how close Collin must be to the cut in the confined space of the boiler. With the excess metal removed and the tube still hot you use the air hammer. You can see the top of the tube forced in and starting to pull free of the tubesheet. Now the side is being hammered to finally push it out. And, if all goes well, it suddenly pops out and lands in the firebox. · Now we move on to the cleaning and inspecting the boiler shell and firebox. Jason did some test cleaning of the barrel. This is important as we need to understand the condition of the boiler coating. This was applied at the last inspection 15 years ago and has not had many days of usage. If it is intact, and the mineral deposits can be removed without damage, this will substantially reduce the amount of sand blasting that is required. First tests looked encouraging. The coating in the areas tested seemed in excellent condition. However, we need to identify a reliable way of removing the mineral deposits, which are pretty tough. · We also started the set up of the sand blasting gear that is certainly required for the firebox. This will be another "nice" job. A helmet respirator (which arrived last week) will be essential for this activity. Now we have to plan and test the air supply. · When I left, Dennis had started working with the corner patch team to cut out the section to be replaced. Ralph tells we that this was completed during the evening. Another major milestone. · Set up continued for swaging the tubes. The furnace was moved into the area and initial cleaning and testing of the swager was carried out. This identified a couple of parts that need to be replaced before it can be operated. Hopefully I can get these next week and test during the week. · The last of the materials for storage were moved out to the boxcar and Jeff hopes to get the boxcar switched this weekend so that we can access the tubes, which are currently on the South side of the car. (This will be essential if we are to be able to get batches of tubes in for swaging during January). A major milestone was reached on the Bay City crane. Glen fired up the traction motor in place for the first time in 20-25 years. (It failed when being driven to the museum in the 1980's). Now it is back in place, cooling, muffler and transmission set up and runs very smoothly. Some of us were in favor of putting it into gear and seeing it move. However Glen is a little more "conservative" and believes in having the means to control and stop a beast this size before setting it in motion. So the power steering and air pumps will be fitted and tested before it goes anywhere!!. On 428, machining continued on the coupling rods and piston bushes. The steel has now arrived for building up the axle boxes but this depends on Dennis's availability to weld this into place as he has work on 1630 and the Shay ahead of this. Happy holidays and thanks to the team for a lot of hard work. Nigel Continue reading "Steam Department Update 12-17-2011" |
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...
Mon, 12-27-2021 16:28
Happy New Year to all the Departments at the Illinois railway Museum! Thanks for all the good work you do in railroad preservation. Ted Miles, [...]
Wed, 10-13-2021 13:33
Was the CB&Q 1309 every transported to IRM?I’ve been reading old issues of Rail&Wire and the car was mentioned several times.
Mon, 06-07-2021 22:40
I was wondering if in the model layout display what scale would you guys be using and would you be displaying model train history as well? Just [...]
Wed, 06-02-2021 17:27
Nice to see 428's cab back on. Looking forward to when it is operable!
Tue, 06-01-2021 16:47
I hope the work will continue on the UP #428. Now that they are the museum's connection to the national railroad network; she would be very [...]
Sat, 04-17-2021 23:07
What is the status of 126, the Milwaukee Buffet car that is in S. Dakota? Any guess on when or if it will get to IRM?
Wed, 04-14-2021 21:09
Perhaps it is time to scrap the remains of the c, B & Q 7128 to make room for the Villa Real. Ted miles, IRM member
Wed, 04-14-2021 15:26
Hi IRM my name is Jason and I was wonder If you guys would be willing to save a CN Dash8-40cm they are currently being retired by CN and being [...]
Fri, 04-09-2021 19:56
Bear in mind that the Nebraska Zephyr is an articulated train set, so cars cannot be inserted at will. Although cars and/or a second engine could be [...]
Wed, 03-31-2021 11:37
I believe Silver Pony is currently on the back burner, and has been put into storage in one of the barns. The car needs a lot of work done to it's [...]