Monday, October 7. 2013
Steam Department Update 10-05-2013 Posted by Nigel Bennett
in Steam Department at
21:54
Comments (3) Steam Department Update 10-05-2013
A great deal has been going on in the steam shop while I have been travelling to the UK. Thanks to Collin, Phil, Jim and Eric for series of updates on which this update is based.
Obviously most activity is focused on 1630 and getting her ready for a steam test
·
In the cab:
Last
weekend the firehole casting was fitted to the backhead
Collin had put in a lot of work during the week to fit
lagging blocks on the backhead;
On 10/5/13 Rick, Vince & Collin mudded the
backhead of the cab. The mudding on the 5th centered on filling in the holes,
so to speak. Approximately 10-12 buckets of mud were hauled into the cab and
applied.
After having mudded the backhead the group then began
the process of fitting the sheet metal which is akin to assembling a jig saw
puzzle. First, the individual pieces are attached to the backhead, then the
radius pieces which overlap both the backhead and wrapper sheet pieces, tying
everything together.
At the end of the day the mudding was largely complete
and all backhead pieces were in place. Additionally, several pieces of radius corner
sheet pieces had been fitted. This shows
what was achieved when compared to the first picture.
At this point we await the completion of some pipe
fitting work on the pressure pipe leading from the steam chests to a gauge in
the cab. Upon completion of that fitting the remainder of the sheet metal in
the cab will be finished.
·
On the boiler barrel
Eric "the crew chief" had his team working
on fitting the sheet metal over the boiler courses so the front course is now
covered.
Further lagging blocks were fitted so that the lagging
is extending steadily toward the firebox.
Jerry has been filling the gaps with insulating mud to
complete each ring.
·
Tom has finished
work on the throttle and this is now ready to refit, hopefully in the coming
weekend.
·
Work has continued
on the air pump. The seats of the
various valves are being cleaned and lapped to ensure efficient operation.
·
As noted last week,
Dennis has been cutting the numerous pieces of plate work for the smokebox. Each new piece is copied from and matched to
the original so that the "jigsaw" will fit together in the smokebox.
The
tricky part is that the copy cannot be exact!.
The comparison between new and old shows why replacement is
necessary. So the trick is that the copy
must match the old where it is complete but also be designed to replace the
metal that is no longer there!
In other areas:
· A good deal of effort went in to enabling the move of locomotives from the steam lead area.
As mentioned last week we had the great pleasure of finding out that a TV show may be filmed here at IRM. Or it was a pleasure until we as discovered that they wanted to film on the steam leads, which of course means all of our equipment on the steam leads has to be move. So, we were then faced with the ever "amazingly fun" task of lubricating all of our equipment... ALL OF IT.
So, the day began with checking our supply of oil and grease that we have. Ralph, Cameron, Brian, and Phil worked on lubricating the equipment out on the leads. Ralph, Cameron, and I took machine oil and went around to all of the engines and lubricated all of the rods.
The
reason for all of the work is that equipment that is seldom moved suffers from
the weather and the bearings would be damaged if it is simply moved as it is
with rain water as a lubricant !..
Brian took a soft grease gun and applied it to all the soft grease points. Then we checked the levels our journal box oil and discovered it to be empty. Tom had ordered a 55 gallon drum but it has not arrived yet. So, we went to the car department and they let us have some of theirs. Joel from the car department set up a new barrel for us and helped us fill up our cans. A big thank you to Joel for doing that. We were able to put car oil into most of the Journal boxes. I think Cameron came in on Sunday and finished up all of the boxes.
· Bob has continued working on the planer. It is now substantially painted and a filter has been fitted to enable the hydraulics to be activated
So a lot has been achieved and I hope to see it at first hand this Saturday, when I get back to the shop. Nigel
Tuesday, October 1. 2013Steam Department Update 09-28-13It seems very distant to be providing this update from the UK. For the input I must thank Collin and Jim. The immediate good news was that apparently we did not put Ethan and Evelina off. Both were back and hard at work on Saturday. On 1630: · Rick, Ed & Collin concentrated on lagging the back head. First, the pieces of sheet metal were fitted up against the firebox to determine where and how they fit together. After having accomplished that step it was determined that the firebox door should be added next as it serves as a template against which the insulation is cut. The previous week the fire door casting, weighing several hundred pounds, was lifted into the tank's coal bunker with the forklift. A team including Rick, Collin, and Eric dragged the door over to the stoker coal feed pipe and placed it so the mating flange to the backhead was horizontal. Rick then mixed up the special fire-resistant concrete and mudded the flange. This mud serves as the gasket between the fire door and the back head where traditional insulation would be consumed by the fire. This is a tricky operation as the concrete has to conform to the surface of the back head before setting up yet be solid enough that it does not fall out of the flange once the flange is vertical. On the initial attempt the mixture was not set up enough so the acetylene rig was brought over to heat up the flange and speed up the drying process. Then a paper was tied to the top of the flange to hold the concrete in place until the fire door casting could be bolted to the back head. Once in place and torqued down, Rick mudded the flange interface completing the seal against the back head. As a final step to the back head project, Rick & Collin determined the appropriate width of the insulation for the back head is 2". Since our insulation comes in 2 1/2" sheets, Rick ripped down the sheets, one at a time and then cut them down the center as well. So, when work resumes next week, the back head insulation work can proceed as all parts are now ready. On Sunday, Tom and Cameron worked on aligning the fire-hole door casting with the stoker riser so that the securing bolts can be fitted. · Work progressed steadily on the boiler insulation as well. Eric, Jerry, Ethan, Evelina, Brian and Jim continued lagging the boiler courses. Since Eric has led this project and we had several new volunteers Eric became known simply as "Crew Chief". In totality, the lagging blocks are in place on the first, second and much of the third courses with a significant portion of the infill mudding also accomplished in these areas. · Jim Opolony picked up, from the wood shop, the cab window frame that Collin put his shoulder through two weeks ago. Many thanks to Bob and the guys for their efforts in producing the beading. Ed worked on the frame, cleaning it up and preparing it for the installation of the glass. · Dennis worked on the sheet metal for the smokebox. A number of the pieces were cut to shape and checked against the old damaged sections to ensure a match. · Tom and Ralph worked on the throttle. · Mike and Brian continued work on the valves of the air compressor. In other areas: · Phil and several others worked on preparing the steam locomotives on steam row for movement. More heavy duty switching is in prospect!. · Stu and Jane worked on the planer and have now primed the main pillar So it sounds like another successful weekend.. Nigel |
Blog AdministrationCategory TreeCalendarQuicksearchSyndicate This Blog |
Powered by s9y.
Comments
Mon, 09-08-2025 08:22
Good job on the Burlington Nortern 9976. OK.
Tue, 08-12-2025 12:56
No new news that I have heard of thus far.
Tue, 08-12-2025 12:53
I'll also be doing another update on it soon. Keep en eye out for that.
Tue, 08-12-2025 12:47
A little work was done to it for Diesel Days this year. You'll see photos floating around for the temporary short term job that was done to make it [...]
Wed, 08-06-2025 13:01
Is steam car CN 15444 going to be coming to museum several times it was to be moved to muesum
Sat, 07-19-2025 18:56
Yeah, sadly it's still there as of 7/19/2025
Thu, 06-12-2025 19:14
Its been 14 years guys, where is the unit? Like really? Did you guys misplace it? Or are repairs taking that long? At this point be might we will have [...]
Wed, 04-09-2025 17:40
Jamie Thanks for the update. She's gonna shine like every thing else you guys do! Smeds
Thu, 03-06-2025 16:28
Yes, there is a wye. Those two have been MU'ed on diesel days a year or two ago.
Wed, 03-05-2025 14:04
7009 number boards look good. Is there a way to turn a locomotive around at IRM? In case you ever had a mind to connect 7009 and 6847?
Fri, 03-29-2024 21:26
We're slackers and spend more time working on the equipment in the shop than keeping all you readers updated. We'll work on it, but I'm sure updates [...]
Thu, 03-14-2024 08:02
What happened to the Department Blog? It's been over 2 years and I still regularly check for updates, but nothing comes...